Mapping the Work with PERT
Quantitative Analysis · Chapter 7: Project Planning with PERT and GanttSection 7.1 · lesson 31 of 5510 min · free with a free account
Free preview
Create a free account to keep watching
It takes a minute and costs nothing. Your free account unlocks all of Chapter 1 and 3 more lessons of Quantitative Analysis.
Lesson complete
Earn the 3 college credits for Quantitative Analysis
Enrolling adds a quiz after each lesson, the graded work and the official transcript. Recommended for credit by NCCRS.
Next lesson: Gantt Charts & Bar Charts →← Measuring More Than MoneyNext lesson: Gantt Charts & Bar Charts →
In this lesson
Network diagrams, the forward and backward pass, float, and the critical path.
- Read a precedence table and build an activity-on-node network
- Run the forward and backward pass to find ES, EF, LS and LF
- Compute total float and free float for every activity
- Identify the critical path and the minimum project duration
Transcript
Everything said in the video, section by section (1,627 words). Read along, or search it.
Project Scheduling · Section 7.1
Mapping the Work with PERT
Every large project is really a web of tasks that depend on one another. Some of those tasks can slip a little, and nobody ever notices. Others cannot slip at all. PERT is the technique that tells you which is which. It stands for Program Evaluation and Review Technique. In this section we build a project network from a table of dependencies. Then we sweep forward through it, to find the earliest each task can happen. Then we sweep backward, to find the latest each task can happen without hurting the deadline. The gap between those two answers is called float. Activities with zero float form the critical path. And the length of that path is the shortest time the project can possibly take.
Why PERT Exists
A Network View of a Large Project
PERT is a network-based way of planning, scheduling and controlling a project. The word network is doing real work there. The method treats the project as a connected structure, not as a list of jobs. That is what lets it answer questions a list simply cannot. Which tasks are genuinely critical? How short can this project be? The history explains the ambition. PERT was developed in nineteen fifty-seven by the United States Navy. They worked with Booz Allen Hamilton on the Polaris Fleet Ballistic Missile programme. That project involved thousands of contractors and sub-contractors, far too many to coordinate by intuition. PERT helped compress the original six-year schedule down to four years. For project management, that result was a landmark.
The Vocabulary
Activities, Precedence and the Network
Four words carry most of the machinery, so it is worth getting them exact. An activity is a well-defined unit of work, with a start, an end, and resources. Crucially, it consumes time. Time is what we will be adding up. A precedence relationship is a logical dependency constraint. It says an activity cannot begin until its predecessors are fully complete. Not mostly complete. Fully. The network diagram is a directed, acyclic graph of the whole project. Directed, because dependencies point one way. Acyclic, because a task cannot depend on itself. Activities can be drawn as arrows, or as boxes. An event, or node, is a milestone, where preceding work ends and succeeding work begins. In a node diagram, every node carries the four timing numbers we are about to compute.
Two Notations
Activity-on-Arrow vs Activity-on-Node
There are two drawing conventions, and they are easy to confuse. In activity-on-arrow, the arrows are the activities and the circles are events. In activity-on-node, the boxes are the activities, and events are implicit. Both encode exactly the same logic. The practical difference is the dummy activity. Activity-on-arrow sometimes needs a fake, zero-duration arrow, purely to express a dependency. That is an artefact of the notation, not a feature of the project. Activity-on-node never needs one. On a complex network, that makes the node form far easier to read. Which is why activity-on-node is the more common convention today. Everything we compute from here uses the node form.
Two Traversals
The Forward Pass and the Backward Pass
Every timing number in PERT comes from just two sweeps through the network. The forward pass runs left to right, from project start to finish. It asks a simple question. How soon can this happen? Earliest start is the maximum earliest finish among all immediate predecessors. Maximum, not minimum, because you have to wait for the slowest one. That single word is the most common mistake in the whole method. Earliest finish is then earliest start plus the duration, and start activities begin at time zero. The backward pass runs the other way, from the finish back to the start. It asks how late a task can happen without moving the deadline. Latest finish is the minimum latest start among all immediate successors. Minimum this time, because you must not hold up any of them. And latest start is simply latest finish minus the duration.
Slack
Total Float and Free Float
Now put the two passes side by side. The gap between them is float. Total float is latest start minus earliest start. Equivalently, latest finish minus earliest finish. The two always agree. It is the delay an activity can absorb before the project itself is delayed. Free float is a different, narrower idea. It is the earliest start of the successor, minus this activity's earliest finish. That is the delay you can take before any successor has to move at all. Here is the part that textbooks tend to bury. Total float is a property of a path, not of a single activity. If two activities share a path, spending float on one takes it away from the other. Free float, by contrast, belongs entirely to the individual activity. An activity whose total float is zero is called critical.
The Longest Path
What Makes a Path Critical
The critical path is the longest path from start to finish. Longest, measured in total duration. That sounds backwards until you see why. The project is not finished until every single path is finished. So the longest path sets the minimum possible project duration. Every activity on it has a total float of zero. Which means one day of delay anywhere on it is one day of delay for everything. A project may have more than one critical path, all of equal length. That makes management harder, not easier, because now there are two chains to protect. To shorten a project, managers crash it, adding resources to critical activities first. Crashing anything off the critical path just buys slack you already had.
Worked Example
A Software Deployment Project
Let us work a full example, a software deployment project with nine activities, labelled A through I. Each one has a duration in days, and a list of immediate predecessors. A is requirements gathering, four days, and it depends on nothing. B is system architecture design, three days, after A. C is database schema design, two days, also after A. So B and C can run in parallel, once A is done. D is backend development, six days, and it follows B. E is frontend development, five days, and it waits for both B and C. F is A P I integration, three days, after D. G is unit and integration testing, four days, after D and E. H is user acceptance testing, three days, after F and G. And I is deployment and go-live, two days, after H.
Forward Pass
Earliest Start and Earliest Finish
Now the forward pass. Start at time zero and move left to right. A has no predecessor, so its earliest start is zero and its earliest finish is four. B and C both follow A, so both of them start at four. B takes three days and finishes at seven. C takes two and finishes at six. D follows B alone. It starts at seven and finishes at thirteen. E is the first merge point, and merge points are where errors creep in. E waits for B and for C. B finishes at seven, C finishes at six. Take the maximum, which is seven. E runs five days and finishes at twelve. F follows D, running from thirteen to sixteen. G merges D at thirteen and E at twelve. Take thirteen, add four, finish at seventeen. H merges F at sixteen and G at seventeen. Take seventeen, add three, finish at twenty. I follows H, running from twenty to twenty-two. The earliest finish of the last activity is twenty-two, so the project takes twenty-two days.
Backward Pass
Latest Times and the Float They Reveal
Now turn around. Set the latest finish of the final activity to twenty-two. I takes two days, so its latest start is twenty. H must finish by twenty, so it has to start by seventeen. F and G both feed H, so both have a latest finish of seventeen. F takes three days, giving a latest start of fourteen. G takes four, giving thirteen. D feeds both F and G, so take the minimum of fourteen and thirteen. D gets a latest finish of thirteen, and a latest start of seven. Now the floats. Total float is latest start minus earliest start. A, B, D, G, H and I all come out at zero, while C gets two days, and E and F one day each. Watch C closely. Its total float is two, but its free float is only one. Delay C by two days and the project still lands on time. But E can no longer start as early as it could, and E's own slack absorbs the difference.
The Answer
Critical Path and Project Duration
So which chain is the critical one? A to B to D to G to H to I. Six activities, every one of them carrying zero total float. Their durations are four, three, six, four, three and two. Add them up and you get twenty-two days, exactly the project duration. That is not a coincidence. That is the definition. Off the path sit C, E and F. C has two days of total float, E has one, and F has one. They can be rescheduled inside those windows without touching the deadline. But do not read float as free time. Spend all of C's float, and E is left with no room at all. Float is a shared budget, and the network decides who is allowed to spend it.
Key Formulas
The Whole Procedure in One Place
Let us gather the formulas in one place. Earliest finish is earliest start plus duration. Earliest start is the maximum earliest finish across all predecessors. Latest start is latest finish minus duration. Latest finish is the minimum latest start across all successors. Total float is latest start minus earliest start, which also equals latest finish minus earliest finish. Free float is the earliest start of the earliest successor, minus this activity's earliest finish. And project duration is the earliest finish of the final activity. The procedure itself never changes. Tabulate, draw the network, forward pass, backward pass, float, then read off the critical path. And if you must shorten the project, crash on the critical path. Anywhere else, the finish date will not move.
About Quantitative Analysis at UPI Study
Quantitative Analysis (Math 250) is a self-paced online course of 55 video lessons in 13 chapters, from decision analysis and simulation to inventory and queuing models, project scheduling, linear programming and transportation models. It carries a NCCRS credit recommendation for 3 semester credits.
Every lesson transcript is free on pages like this one, and the videos are free with a free UPI Study account. Enrolling adds a practice quiz after each lesson, the graded work and final exam that earn the credit, lifetime access, and an official transcript on completion. UPI Study has helped over 130,000 students with college credits. ACE and NCCRS have over 2,100 cooperating colleges that will consider accepting credits; the final decision is with the universities.
Enroll now → Course details Download the syllabus All Math courses Every course with PRO →
Compare: Statistics vs Quantitative Analysis
Why take it here
Why students take Quantitative Analysis with UPI Study
Where the credit goes
Universities that work with NCCRS
Quantitative Analysis carries a NCCRS credit recommendation. These universities work with NCCRS; some are UPI Study's signed partners. ACE and NCCRS have over 2,100 cooperating colleges that will consider accepting credits; the final decision is with the universities.
Thomas Edison State UniversitySigned partner
University of the PeopleSigned partner
Charter Oak State CollegeSigned partner
Strayer UniversitySigned partner
Columbia Southern UniversitySigned partner
Indiana TechSigned partner
Penn StateWorks with NCCRS
Southern New Hampshire UniversityWorks with NCCRS
SUNYWorks with NCCRS
+many more cooperating universitiesFind my college →Find my college → Not listed? Ask Athena in the corner of this page, or book a 15-minute call.
FAQ
Questions students ask us
About Mapping the Work with PERT
What is PERT in project management?
How do you do a forward pass and a backward pass in a project network?
What is the difference between total float and free float?
What is the difference between activity-on-arrow and activity-on-node diagrams?
About the Quantitative Analysis course
How many college credits is Quantitative Analysis?
How much does Quantitative Analysis cost and what is included?
Which universities accept UPI Study credits?
How long does Quantitative Analysis take?
How are the exams done?
How do my credits reach my college?
Ready for the full course? Earn 3 credits in Quantitative Analysis.
55 video lessons, a quiz after each one, and the graded work that earns the credit. Recommended for credit by NCCRS.
3 credits · NCCRSEnroll →