Feasibility Studies, Team Dynamics, and Building the Work Breakdown Structure
System Analysis and Design · Chapter 9: Project Management, Scheduling, and QualitySection 9.5 · lesson 64 of 698 min · free with a free account
Free preview
Create a free account to keep watching
It takes a minute and costs nothing. Your free account unlocks all of Chapter 1 and 3 more lessons of System Analysis and Design.
Lesson complete
Earn the 3 college credits for System Analysis and Design
Enrolling adds a quiz after each lesson, the graded work and the official transcript. Recommended for credit by NCCRS.
Next lesson: Project Management Tools for Systems Development Work →← Project Scheduling Mastery: Techniques, Critical Path Analysis, Total Slack, and Free SlackNext lesson: Project Management Tools for Systems Development Work →
In this lesson
5 feasibility checks, ROI, payback and NPV, Tuckman's stages, and the work breakdown structure.
- Identify the 5 types of feasibility, and what each assesses
- Apply ROI, payback period, and NPV
- Describe Tuckman's stages, and common sources of team conflict
- Construct a WBS with work packages and a WBS dictionary
Transcript
Everything said in the video, section by section (1,069 words). Read along, or search it.
Project Management, Scheduling, and Quality
Feasibility, Teams, and the WBS
Before a project is committed to, someone has to check that it can succeed, and plan who will do what. This section covers five kinds of feasibility, three tools for weighing costs against benefits, and how teams develop, and clash. Then the work breakdown structure, which turns a project's scope into assignable pieces of work.
Before Committing Resources
5 Types of Feasibility
Before committing real resources, an analyst checks feasibility along five dimensions. Technical feasibility asks whether it can be built with the technology, skills, and infrastructure available. Economic feasibility asks whether the expected benefits justify the costs. Legal feasibility asks whether it complies with laws, regulations, and contracts. Operational feasibility asks whether the organization will actually use it, and whether it fits existing processes. And schedule feasibility asks whether it can be finished in the time actually available. A project can pass one check and fail another. A system that is affordable and technically achievable still fails operational feasibility, if employees refuse to change their workflow to use it.
Cost-Benefit (1 of 2)
ROI and the Payback Period
Economic feasibility is usually backed by numbers. Take a system that costs fifty thousand dollars to build, and saves twenty thousand dollars a year for four years. Return on investment compares net benefit to cost. Total benefits are eighty thousand dollars. Subtract the fifty thousand cost, and the net benefit is thirty thousand. Thirty thousand, divided by fifty thousand, is a return on investment of sixty percent. The payback period is how long it takes for cumulative savings to equal the investment. After year one, twenty thousand is saved. After year two, forty thousand. The last ten thousand takes half of year three's savings, so the payback period is two and a half years.
Cost-Benefit (2 of 2)
Net Present Value
Return on investment and payback share a blind spot. They ignore the time value of money. A dollar saved next year is worth less than a dollar saved today. Net present value, or N P V, discounts each future year's benefit back to today's value, before comparing it with the upfront cost. At an eight percent discount rate, year one's twenty thousand dollars is worth about eighteen thousand, five hundred today. Each later year is worth a little less, down to about fourteen thousand, seven hundred in year four. Together, the four years are worth about sixty-six thousand, two hundred dollars today. Subtract the fifty thousand dollar investment, and the net present value is about sixteen thousand, two hundred dollars. It is positive, so the project is worth pursuing. A negative N P V would say it is not. And a project whose benefits arrive slowly can show a healthy return on investment, yet a weak net present value.
Figure 9.5a
Tuckman's Stages of Team Development
Teams do not become effective the moment they are formed. Bruce Tuckman's model describes five stages most teams move through. Forming. Members are polite and uncertain, and rely on the leader. Storming. Conflict surfaces, as working styles and roles clash. Norming. Norms and trust build, and roles settle. Performing. Trust and productivity are high. And adjourning. The work wraps up, and the team disbands. The path is not strictly one-way. A smooth team that gains two new members may find conflict returning. It has been pushed back into storming. That is a normal part of the cycle, and the team can move back through norming toward performing.
Team Conflict
Sources, and Constructive Responses
Conflict is most likely during storming, but it can resurface whenever membership or direction changes. Differing goals, where members optimize for different outcomes, are answered by revisiting the shared objective. Role ambiguity, where no one is sure who owns a decision, is answered by clarifying ownership explicitly, in writing. Working-style differences, over pace, process, or communication, are answered by agreeing on shared norms. And competition for limited time, budget, or attention is answered by making trade-offs and priorities explicit. Not all conflict is harmful. Disagreement over ideas and approach, handled constructively, often improves the outcome. Conflict rooted in personality clashes, or unclear roles, tends to be destructive if it is left alone.
Figure 9.5b
A Work Breakdown Structure
A work breakdown structure, or W B S, decomposes a project's total scope into progressively smaller pieces. Here, an intranet redesign splits into four parts. Requirements and planning, design, development, and testing and launch. Each part splits again, into work packages, such as create wireframes, or build back-end. A work package is small enough to assign, estimate, and track on its own. Every W B S follows the one hundred percent rule. The pieces at every level must account for exactly all of the project's scope. No more, and no less. A W B S with design and development, but no testing, breaks that rule. The testing work would never be planned, estimated, or assigned.
The WBS Dictionary
Defining Each Work Package
Each work package is then documented in a W B S dictionary. Take create wireframes. It produces low-fidelity layouts for all core intranet pages. It is owned by the U X designer, takes five days, and is accepted when the product owner approves wireframes for every page. Or build back-end. It covers the server-side logic, database schema, and A P Is. It is owned by the back-end developer, takes fifteen days, and is accepted when every endpoint passes integration testing and matches the spec. That detail is what lets each package be assigned, estimated, and later verified as complete.
Key Terms
The Vocabulary of This Section
Let's lock in the key terms. Operational feasibility asks whether the organization will actually adopt the system. Return on investment compares net benefit to cost. The payback period is the time to recover the investment. Net present value discounts future benefits to today's value, and subtracts the investment. A work package is the smallest unit of a W B S, small enough to assign, estimate, and track. The one hundred percent rule says every level of a W B S covers exactly the whole scope. And a W B S dictionary defines each work package's scope, owner, and acceptance criteria.
Key Takeaways
What to Carry Forward
To pull this together. Technical, economic, legal, operational, and schedule feasibility are all assessed separately, because a project can pass one and fail another. Return on investment and payback are simple, but ignore the time value of money. Net present value accounts for it. Tuckman's five stages, forming, storming, norming, performing, and adjourning, describe how most teams develop. Task-focused conflict can improve a project, while role and personality conflict tends to harm it. And a W B S decomposes a project down to work packages under the one hundred percent rule, with a W B S dictionary defining each one.
About System Analysis and Design at UPI Study
System Analysis and Design (Computer Science 390) is a self-paced online course of 69 video lessons in 9 chapters, from the analyst's role and requirements to UML modeling, interface and database design, testing, maintenance and project management. It carries a NCCRS credit recommendation for 3 semester credits.
Every lesson transcript is free on pages like this one, and the videos are free with a free UPI Study account. Enrolling adds a practice quiz after each lesson, the graded work and final exam that earn the credit, lifetime access, and an official transcript on completion. UPI Study has helped over 130,000 students with college credits. ACE and NCCRS have over 2,100 cooperating colleges that will consider accepting credits; the final decision is with the universities.
Enroll now → Course details Download the syllabus All Computer Science courses Every course with PRO →
Why take it here
Why students take System Analysis and Design with UPI Study
Where the credit goes
Universities that work with NCCRS
System Analysis and Design carries a NCCRS credit recommendation. These universities work with NCCRS; some are UPI Study's signed partners. ACE and NCCRS have over 2,100 cooperating colleges that will consider accepting credits; the final decision is with the universities.
Thomas Edison State UniversitySigned partner
University of the PeopleSigned partner
Charter Oak State CollegeSigned partner
Strayer UniversitySigned partner
Columbia Southern UniversitySigned partner
Indiana TechSigned partner
Penn StateWorks with NCCRS
Southern New Hampshire UniversityWorks with NCCRS
SUNYWorks with NCCRS
+many more cooperating universitiesFind my college →Find my college → Not listed? Ask Athena in the corner of this page, or book a 15-minute call.
FAQ
Questions students ask us
About Feasibility Studies, Team Dynamics, and Building the Work Breakdown Structure
What are the five types of feasibility in a feasibility study?
How do you calculate ROI and payback period for an IT project?
Why is net present value better than ROI for judging a project?
What is the 100 percent rule in a work breakdown structure?
About the System Analysis and Design course
How many college credits is System Analysis and Design?
How much does System Analysis and Design cost and what is included?
Which universities accept UPI Study credits?
How long does System Analysis and Design take?
How are the exams done?
How do my credits reach my college?
Ready for the full course? Earn 3 credits in System Analysis and Design.
69 video lessons, a quiz after each one, and the graded work that earns the credit. Recommended for credit by NCCRS.
3 credits · NCCRSEnroll →