Performance Tracking, Monitoring, and Controlling: Keeping Projects on Course
System Analysis and Design · Chapter 9: Project Management, Scheduling, and QualitySection 9.9 · lesson 68 of 698 min · free with a free account
Free preview
Create a free account to keep watching
It takes a minute and costs nothing. Your free account unlocks all of Chapter 1 and 3 more lessons of System Analysis and Design.
Lesson complete
Earn the 3 college credits for System Analysis and Design
Enrolling adds a quiz after each lesson, the graded work and the official transcript. Recommended for credit by NCCRS.
Next lesson: Risk Management and Post-Project Reviews: Planning for Uncertainty and Learning from Experience →← Gantt Charts: Definitions, Uses, and Practical ExamplesNext lesson: Risk Management and Post-Project Reviews: Planning for Uncertainty and Learning from Experience →
In this lesson
Earned value, SPI and CPI, status reports, change control, scope creep, and KPIs.
- Define planned value, earned value, and actual cost
- Calculate and interpret SPI and CPI
- Explain status reports and the change control board
- Explain scope creep, and identify useful project KPIs
Transcript
Everything said in the video, section by section (1,070 words). Read along, or search it.
Project Management, Scheduling, and Quality
Keeping Projects on Course
A plan is only useful if you can tell when reality is drifting away from it. This section covers earned value management and the two ratios it produces, and how status reports turn tracking data into action. Then the change control board, the scope creep it guards against, and the key performance indicators that track project health.
Earned Value Management
3 Dollar Figures, Not a Guess
Earned value management, or E V M, measures project performance by comparing three dollar figures at a given point in time. That is far more reliable than a percent-complete estimate, which can be little more than a guess. Planned value, or P V, is the budgeted cost of the work that was scheduled to be done by now. Earned value, or E V, is the budgeted cost of the work that has actually been completed by now. And actual cost, or A C, is the real money actually spent to complete that work. So if the plan called for fifty thousand dollars of budgeted work by today, but only forty-five thousand has been finished, then fifty thousand is P V, and forty-five thousand is E V.
Figure 9.2
A Worked Checkpoint
Here is a worked checkpoint. The project's total budget is one hundred thousand dollars. By this checkpoint, the plan called for forty percent of the work to be done. So planned value is forty thousand dollars. In reality, the team has completed work worth only thirty-two thousand dollars, in budgeted terms. That is the earned value, highlighted. And it has spent thirty-eight thousand dollars getting there. That is the actual cost. Less work done than planned. And more money spent than the work was worth.
SPI and CPI
2 Ratios, a Quick Read on Health
P V, E V, and A C combine into two ratios. The schedule performance index, S P I, is earned value divided by planned value. Here, thirty-two thousand divided by forty thousand, which is zero point eight. The cost performance index, C P I, is earned value divided by actual cost. Here, thirty-two thousand divided by thirty-eight thousand, which is about zero point eight four. Above one means ahead of schedule, or under budget. Exactly one means right on plan. Below one means behind schedule, or over budget. A C P I of zero point eight four means only eighty-four cents of value is earned for every dollar spent. So this project is behind schedule and over budget, with the schedule problem slightly worse. A far more precise picture than simply saying it is behind.
Status Reporting
Tracking Data Stakeholders Can Act On
A status report is a regular, structured update that turns tracking data into something stakeholders can act on. Most status reports cover the same core ground. Progress against schedule and budget, through S P I and C P I, or plain-language equivalents. Accomplishments since the last report. Upcoming work, planned for the next period. Risks and issues that could threaten schedule, budget, or quality, and how each is being handled. And decisions needed. Anything stakeholders must weigh in on before work can continue.
The Change Control Board
Changes Weighed, Not Absorbed
Once a project's scope, schedule, and budget are formally agreed, that agreement becomes its baseline. A change control board, or C C B, is the formal group responsible for reviewing any proposed change to that baseline, and deciding whether to approve it. It usually includes the sponsor, the project manager, and key stakeholders. A change request follows a consistent path. Someone submits it. Its impact on schedule, budget, and quality is assessed. The board reviews that assessment, and decides. And if the change is approved, the baseline is formally updated. The point is that every change is evaluated deliberately, not absorbed quietly, without anyone weighing its true cost.
Scope Creep
"While We're in There..."
Scope creep is the gradual, uncontrolled expansion of a project's scope, without a matching adjustment to its schedule, budget, or resources. It rarely arrives as one large change. It is usually a series of small, individually reasonable-sounding additions. While we're in there, could we also add this? Quietly, they add up to a project doing far more than it was ever budgeted or scheduled to do. Picture a team member asking to slip in a small feature, with no formal request. That is scope creep in action. The change control board is the primary defense. Routing every addition through a formal request, however minor, forces its cost to be weighed openly. And a clearly documented scope, from the start, gives the team a reference point for recognizing when a request falls outside it.
KPIs
Key Performance Indicators
A key performance indicator, or K P I, is a specific, measurable metric tracked over time to gauge some aspect of a project's health. S P I and C P I are themselves K P Is, but projects usually track several others. Milestones completed on time shows how reliably the project hits its major checkpoints. The defect count trend shows whether newly discovered defects are rising, falling, or holding steady. Budget variance is the dollar difference between what was budgeted and what has been spent. Team velocity, on agile projects, is how much work the team completes per iteration. And a stakeholder satisfaction score captures how stakeholders rate progress and communication. A status report is not itself a K P I. It usually presents several K P Is, in its progress section.
Key Terms
The Vocabulary of This Section
Let's lock in the key terms. Planned value is the budgeted cost of scheduled work. Earned value is the budgeted cost of completed work. Actual cost is the money actually spent. S P I is earned value over planned value. C P I is earned value over actual cost. Below one signals a problem. The change control board is the group that reviews and approves changes to the baseline. Scope creep is the gradual, uncontrolled growth of a project's scope. And a K P I is a specific, measurable metric, tracked over time.
Key Takeaways
What to Carry Forward
To pull this together. Planned value is scheduled budgeted work, earned value is completed budgeted work, and actual cost is what was actually spent to complete it. S P I is earned value over planned value, and C P I is earned value over actual cost. Values below one signal a schedule or cost problem. A status report translates tracking data into progress, accomplishments, upcoming work, risks, and decisions needed. A change control board formally reviews every proposed change to the baseline, and routing every change through it is the primary defense against scope creep. And a K P I, such as budget variance or defect trend, is a measurable metric tracked over time to gauge project health.
About System Analysis and Design at UPI Study
System Analysis and Design (Computer Science 390) is a self-paced online course of 69 video lessons in 9 chapters, from the analyst's role and requirements to UML modeling, interface and database design, testing, maintenance and project management. It carries a NCCRS credit recommendation for 3 semester credits.
Every lesson transcript is free on pages like this one, and the videos are free with a free UPI Study account. Enrolling adds a practice quiz after each lesson, the graded work and final exam that earn the credit, lifetime access, and an official transcript on completion. UPI Study has helped over 130,000 students with college credits. ACE and NCCRS have over 2,100 cooperating colleges that will consider accepting credits; the final decision is with the universities.
Enroll now → Course details Download the syllabus All Computer Science courses Every course with PRO →
Why take it here
Why students take System Analysis and Design with UPI Study
Where the credit goes
Universities that work with NCCRS
System Analysis and Design carries a NCCRS credit recommendation. These universities work with NCCRS; some are UPI Study's signed partners. ACE and NCCRS have over 2,100 cooperating colleges that will consider accepting credits; the final decision is with the universities.
Thomas Edison State UniversitySigned partner
University of the PeopleSigned partner
Charter Oak State CollegeSigned partner
Strayer UniversitySigned partner
Columbia Southern UniversitySigned partner
Indiana TechSigned partner
Penn StateWorks with NCCRS
Southern New Hampshire UniversityWorks with NCCRS
SUNYWorks with NCCRS
+many more cooperating universitiesFind my college →Find my college → Not listed? Ask Athena in the corner of this page, or book a 15-minute call.
FAQ
Questions students ask us
About Performance Tracking, Monitoring, and Controlling: Keeping Projects on Course
What is the difference between planned value, earned value, and actual cost?
How do you calculate SPI and CPI in earned value management?
What is scope creep and how do you prevent it?
What should a project status report include?
About the System Analysis and Design course
How many college credits is System Analysis and Design?
How much does System Analysis and Design cost and what is included?
Which universities accept UPI Study credits?
How long does System Analysis and Design take?
How are the exams done?
How do my credits reach my college?
Ready for the full course? Earn 3 credits in System Analysis and Design.
69 video lessons, a quiz after each one, and the graded work that earns the credit. Recommended for credit by NCCRS.
3 credits · NCCRSEnroll →