Budget Control and Cost-Revenue Management
Healthcare Organization and Management · Chapter 11: Financial Planning and Resource Management in HealthcareSection 11.2 · lesson 65 of 10510 min · free with a free account
Free preview
Create a free account to keep watching
It takes a minute and costs nothing. Your free account unlocks all of Chapter 1 and 3 more lessons of Healthcare Organization and Management.
Lesson complete
Earn the 3 college credits for Healthcare Organization and Management
Enrolling adds a quiz after each lesson, the graded work and the official transcript. Recommended for credit by NCCRS.
Next lesson: Direct and Indirect Costs in Healthcare Finance →← Operating Budgets and Financial PlanningNext lesson: Direct and Indirect Costs in Healthcare Finance →
In this lesson
Using flexible budgets and variance analysis to explain healthcare overspending.
- Explain why comparing actual costs with a static budget misleads when volume changes
- Calculate a flexible budget and split a labor variance into volume, rate, and efficiency parts
- Distinguish paid, worked, and productive hours, and supply price from usage variances
- Write a variance explanation that states the cause, whether it will recur, and the action
Free study notes
Get this lesson's notes by email
The key points and 4 practice questions with answers, in your inbox. One email, free.
One email. Unsubscribe in one click.
Transcript
Everything said in the video, section by section (1,358 words). Read along, or search it.
Opening Case
The Biggest Unfavorable Variance in the Hospital
Jamal Carter manages Larkfield's emergency department, including its fast-track area for minor injuries. This month's report shows fast-track salaries $46,330 over budget, the biggest unfavorable variance in the hospital. He's asked to explain it at the divisional review. Is he overspending? Or is the report comparing against the wrong thing?
Control Cycle
Why the Original Budget Misleads
Budget control is the general control cycle applied to money. Set a standard, measure performance, compare, and act on the difference. In most settings the standard holds still. A budget's standard doesn't. It was built on a volume assumption. When actual volume differs, comparing against the original budget gives a number that's arithmetically right, and analytically worthless.
Definition
Favorable and Unfavorable Are Not Verdicts
A variance is the difference between a budgeted amount and an actual one. It's favorable when expense comes in below budget, or revenue above it. Unfavorable is the reverse. Those labels are arithmetic, not verdicts. A unit that underspent because it couldn't fill its shifts reports a favorable variance, and has a serious problem. A unit that overspent because it treated twenty percent more patients reports an unfavorable one, and may have done very well.
Flexible Budget
Recalculating the Budget at Actual Volume
The fix is a flexible budget: the budget recalculated at the volume that actually happened, using the original standard cost per unit. Jamal's plan was a thousand visits, at a standard of four staff hours per visit and fifty dollars an hour. That's the static budget, two hundred thousand dollars. Actual volume was eleven hundred fifty visits. At the same standards, eleven fifty times four times fifty is two hundred thirty thousand. So about two thirds of the gap is simply the cost of doing more work. Only sixteen thousand, three hundred thirty dollars needs explaining.
Volume Variance
The Cost of Doing More Work
Now split the variance into parts with different causes. First, the volume variance: flexible budget minus static budget. Two hundred thirty thousand minus two hundred thousand is thirty thousand dollars, unfavorable. That's not a cost-control failure. If revenue rose with the extra visits, it may pay for itself. To split the rest, we need the standard hours for the work actually done: eleven fifty visits times four hours is forty-six hundred hours.
Rate and Efficiency
Two More Parts Complete the Gap
Second, the rate variance, which is the price variance for supplies. It's the actual rate minus the standard rate, times the actual hours. Fifty-one dollars minus fifty, times his actual forty-eight thirty hours, is four thousand eight hundred thirty dollars, unfavorable. Third, the efficiency variance, which is the usage variance for supplies. Actual hours minus standard hours, times the standard rate. Forty-eight thirty minus forty-six hundred is two thirty hours. Times fifty dollars, that's eleven thousand five hundred, unfavorable. Add the three: thirty thousand, plus eleven five hundred, plus forty-eight thirty. That's forty-six thousand, three hundred thirty, the whole gap.
Interpretation
Each Variance Points Somewhere Different
Each part points somewhere different. Volume: check whether revenue moved with activity. If the volume will last, re-forecast instead of cutting cost. Rate: work on what drives it. Typical causes are a richer skill mix than planned, overtime premium, or agency cover. Efficiency: more hours per visit than standard. First check that the standard still fits today's case mix. Only then have a productivity conversation.
Labor Hours
Paid, Worked, and Productive Hours
Labor variances often come down to which hours are being counted. Paid hours are every hour staff are paid for, including vacation, sick time and training. Worked hours are hours actually on duty. Productive hours are worked hours spent on the department's core work, excluding meetings and training on shift. Standards usually use worked hours, while payroll reports paid hours. Mix them, and a department looks over standard for reasons unrelated to performance. A unit with a long-term absence shows high paid hours and unchanged worked hours. That's a cost pressure in the absence line, not a productivity problem.
Quick Check
Finding the Biggest Imaging Variance
Your turn, with new numbers. The imaging department planned eight hundred scans, at three staff hours per scan and forty dollars an hour. It actually did seven hundred sixty scans, using twenty-three seventy hours at forty-two dollars an hour. Of the three parts, which is the biggest unfavorable one: volume, efficiency, or rate? Pause, and work it out. Rate is the biggest unfavorable part. Two dollars over standard, times twenty-three seventy hours, is four thousand seven hundred forty dollars. Efficiency is tempting. The standard hours are seven sixty times three, or twenty-two eighty. Ninety extra hours at forty dollars is only thirty-six hundred. And volume is favorable: the flexible budget, ninety-one thousand two hundred, is forty-eight hundred below the static budget.
Supply Variances
Price Versus Usage for Supplies
Supplies split the same way, with different names. The price variance comes from paying a different unit price than standard: contract terms, off-contract buying, substitutions. The usage variance comes from using a different quantity per case: clinical practice, waste, expired stock, or a heavier case mix. The remedies sit with different people. Price is fixed by procurement, and by managers who stop off-contract buying. Usage is fixed by talking with clinicians about practice. Tell a department only that supplies are over budget, and it reaches for its one lever, buying less. That fixes just one of the two causes.
Materiality
When a Variance Deserves a Chase
Not every variance deserves a chase. A materiality threshold is the level below which a variance isn't investigated, set as a percentage of the line, a dollar amount, or both. Attention is scarce, and small variances often come from timing and coding effects that reverse on their own. Two exceptions keep the rule honest. A small variance that recurs in the same direction every month is material: it's systematic, and it compounds. And any variance on a line that should be zero deserves a question, whatever its size.
Explaining Variances
Cause, Recurrence, and Action
A variance isn't explained until three things are said: what caused it, whether it will recur, and what's being done. 'Volume was above plan' just restates the arithmetic. It isn't a cause. 'Agency cover for two vacancies at premium rates. Both posts now offered. Expected to resolve next month.' That's an explanation, because it can be tested next month. Recurrence is the question most often skipped, and the one finance needs most. A one-off affects a month. A recurring variance changes the full-year forecast.
Matching Fixes
A Deferral Is Not a Saving
The fix must match the part. Volume calls for a check that revenue moved too, and a re-forecast if it lasts. Rate calls for work on recruitment, skill mix and overtime approval. Efficiency calls first for a check of the standard. Beware fixes that close this month's gap and cost more later: deferring maintenance, freezing needed hiring, canceling training, staffing below safe levels. Each produces a favorable variance and a liability. The tell: the saving comes from not doing something, rather than doing something differently.
Quick Check
Extra Nursing Hours on 4 North
One more case. 4 North planned five hundred patients, at five nursing hours each and forty-five dollars an hour. It saw five hundred patients and paid twenty-seven fifty hours, at forty-five dollars an hour. It began taking post-surgical patients this quarter. Which variance is this, and what comes first? Pause, and decide. It's an efficiency variance: patients and rate match the plan, but hours run two hundred fifty over plan. The first step is to check the standard, not to push nurses harder. A heavier case mix needs a new standard. Rate is tempting, since the cost per patient rose. But the price of an hour didn't change; the number of hours did.
Case Resolved
Jamal Brings the Decomposition
Back to Jamal. He walks into the review with the decomposition, not a defense. Thirty thousand of the forty-six is volume: a nearby urgent care closed, and his fast track absorbed its patients. Eleven five hundred is efficiency: two new hires were still learning the routine. Forty-eight thirty is rate: weekend overtime. He brings what every monthly review needs: the flexible comparison, the parts, causes with recurrence answered, the full-year effect, and actions with dates. And he asks the question the report can't answer: did net revenue come with the extra visits, and will the volume last?
Key Takeaways
Variance Analysis in Five Rules
To recap. Compare against a flexible budget, not the static one. Split the gap into volume, rate, and efficiency, because each has its own cause and fix. Know whether you're counting paid, worked, or productive hours. Explain each variance with its cause, whether it will recur, and the action. And never mistake a deferral for a saving.
About Healthcare Organization and Management at UPI Study
Healthcare Organization and Management (Health 302) is a self-paced online course of 105 video lessons in 18 chapters, from health systems and the law to ethics, leadership, teams, strategy, informatics, finance, quality, human resources, marketing and evidence-based practice. It carries a NCCRS credit recommendation for 3 semester credits.
Every lesson transcript is free on pages like this one, and the videos are free with a free UPI Study account. Enrolling adds a practice quiz after each lesson, the graded work and final exam that earn the credit, lifetime access, and an official transcript on completion. UPI Study has helped over 130,000 students with college credits. ACE and NCCRS have over 2,100 cooperating colleges that will consider accepting credits; the final decision is with the universities.
Enroll now → Course details Download the syllabus All Health courses Every course with PRO →
Why take it here
Why students take Healthcare Organization and Management with UPI Study
Where the credit goes
Universities that work with NCCRS
Healthcare Organization and Management carries a NCCRS credit recommendation. These universities work with NCCRS; some are UPI Study's signed partners. ACE and NCCRS have over 2,100 cooperating colleges that will consider accepting credits; the final decision is with the universities.
Thomas Edison State UniversitySigned partner
University of the PeopleSigned partner
Charter Oak State CollegeSigned partner
Strayer UniversitySigned partner
Columbia Southern UniversitySigned partner
Indiana TechSigned partner
Penn StateWorks with NCCRS
Southern New Hampshire UniversityWorks with NCCRS
SUNYWorks with NCCRS
+many more cooperating universitiesFind my college →Find my college → Not listed? Ask Athena in the corner of this page, or book a 15-minute call.
FAQ
Questions students ask us
About Budget Control and Cost-Revenue Management
What is a flexible budget in healthcare?
How do you split a labor cost variance into volume, rate, and efficiency variances?
What is the difference between paid hours, worked hours, and productive hours in healthcare staffing?
What is a materiality threshold in budget variance analysis?
About the Healthcare Organization and Management course
How many college credits is Healthcare Organization and Management?
How much does Healthcare Organization and Management cost and what is included?
Which universities accept UPI Study credits?
How long does Healthcare Organization and Management take?
How are the exams done?
How do my credits reach my college?
Ready for the full course? Earn 3 credits in Healthcare Organization and Management.
105 video lessons, a quiz after each one, and the graded work that earns the credit. Recommended for credit by NCCRS.
3 credits · NCCRSEnroll →