Estimating Timelines When Activity Durations Are Uncertain
Software Engineering · Chapter 14: Project Estimation, Configuration, and Change ControlSection 14.1 · lesson 86 of 1037 min · free with a free account
Free preview
Create a free account to keep watching
It takes a minute and costs nothing. Your free account unlocks all of Chapter 1 and 3 more lessons of Software Engineering.
Lesson complete
Earn the 3 college credits for Software Engineering
Enrolling adds a quiz after each lesson, the graded work and the official transcript. Recommended for credit by NCCRS.
Next lesson: Building Quality into Software Through Management Systems →← The W5HH Framework: Asking the Right Project QuestionsNext lesson: Building Quality into Software Through Management Systems →
In this lesson
Making uncertainty explicit, instead of hiding it in 1 number.
- Explain what a single-point estimate hides
- Calculate a three-point (PERT) expected duration
- Describe size-based estimation: lines of code and function points
- Choose, and combine, the right approach
Transcript
Everything said in the video, section by section (839 words). Read along, or search it.
Project Estimation, Configuration, and Change Control
Estimating Timelines When Activity Durations Are Uncertain
This will take ten days. It sounds precise, but it usually is not. This section covers techniques that make the uncertainty in an estimate explicit, producing an estimate you can actually defend.
A Guess Dressed as a Fact
"This Will Take 10 Days"
A single-point estimate is often a guess, dressed up as a fact. It presents one number as though it were settled, with no sense of how much confidence to place in it. Most estimates are genuinely uncertain. The real duration could reasonably fall anywhere across a range. And a single figure hides exactly how wide that range is. The techniques here exist to make that uncertainty explicit and systematic, rather than pretending it is not there.
Three-Point (PERT) Estimation
3 Numbers Instead of 1
Three-point estimation asks for three numbers instead of one. An optimistic estimate, if everything goes right. A pessimistic estimate, if everything that could reasonably go wrong does. And a most likely estimate, which is the realistic middle expectation. These combine into a single weighted expected value. It is the optimistic figure, plus four times the most likely, plus the pessimistic, all divided by six. So the most likely figure gets four times the weight of either extreme.
Worked Example
O = 4, M = 6, P = 14
Here is an example. A task has an optimistic estimate of four days, a most likely estimate of six days, and a pessimistic estimate of fourteen days. Four, plus four times six, plus fourteen, is forty-two. Divided by six, that gives an expected value of seven days. The wide pessimistic tail nudges the expected value above the most likely figure, even though extreme outcomes are weighted as less probable.
Figure 1
The Shape Behind the Formula
This is a rough sketch of the shape three-point estimation assumes. Most outcomes cluster near the middle, around the most likely figure of six days. But there is a longer tail toward the pessimistic side, stretching out to fourteen. That tail is what pulls the expected value, seven days, above the most likely figure.
Worth Noticing
What the Weights and the Gap Tell You
Two things are worth noticing here. The four-times weighting on the most likely estimate is not arbitrary. It reflects an assumption that extreme outcomes, in either direction, are genuinely less probable than something closer to the middle. And a wide gap between the optimistic and pessimistic figures is useful information in itself. It flags a task that is still genuinely uncertain, and worth watching closely.
Estimating From Size
Size First, Then Effort
A different family of techniques estimates size first, and derives effort from it. Effort is roughly the size, divided by the team's historical productivity rate. A lines-of-code estimate sizes the work by code volume, often by comparison to similar past features, then divides by lines per day. It is simple, but crude. Code volume varies enormously by language and style, and does not capture problem complexity. A function point estimate measures functionality from the user's perspective, counting inputs, outputs, and data files. It stays independent of language, but is more involved to count.
Table 1
3 Techniques Compared
Here are the three techniques side by side. Three-point estimation measures a range of possible durations for one activity. It fits when the activity is understood, but its duration is uncertain. Lines of code estimates code volume, converted through team productivity. It fits when the team has reliable history, in a familiar language and domain. Function points estimate functionality, converted the same way. They fit when comparing size across languages, or benchmarking productivity over time.
Choosing an Approach
Not Either-Or
These approaches are not mutually exclusive. Size-based techniques fit estimating overall effort for a larger body of work, often before individual activities are even worked out. Three-point estimation fits a specific activity whose scope is understood, but whose duration carries real uncertainty. So a project might size its overall scope early with function points, then apply three-point estimates to the activities that turn out most uncertain. Either way, an estimate is a starting point, not a fixed promise. It should be revisited as more is learned.
Apply It
O = 2, M = 3, P = 10
Let's apply that. An activity has an optimistic estimate of two days, a most likely estimate of three, and a pessimistic estimate of ten. What is its expected duration? Two, plus four times three, plus ten, is twenty-four. Divided by six, that is four days. And the wide spread, from two to ten, flags this activity as one worth watching closely.
Key Terms
The Vocabulary of This Section
Let's lock in the key terms. Three-point, or PERT, estimation combines optimistic, most likely, and pessimistic duration estimates into one weighted expected value. The most likely estimate is the realistic middle expectation. It is weighted four times as heavily as either extreme. A function point is a size measure based on counted functionality, such as inputs and outputs, aimed at staying independent of programming language. And lines-of-code estimation converts an estimated code volume into effort, using a team's historical productivity rate.
Key Takeaways
What to Carry Forward
To pull this together. A single-point estimate hides the range of what could realistically happen. Three-point estimation's expected value is the optimistic figure, plus four times the most likely, plus the pessimistic, divided by six. A wide gap between the optimistic and pessimistic figures flags genuine uncertainty. Size-based estimates divide an estimated size by historical productivity. And the approaches can be combined, with every estimate revisited as more is learned.
About Software Engineering at UPI Study
Software Engineering (Computer Science 301) is a self-paced online course of 103 video lessons in 15 chapters, from process models and agile to requirements, design, user interfaces, reliability, security and project management. It carries a NCCRS credit recommendation for 3 semester credits.
Every lesson transcript is free on pages like this one, and the videos are free with a free UPI Study account. Enrolling adds a practice quiz after each lesson, the graded work and final exam that earn the credit, lifetime access, and an official transcript on completion. UPI Study has helped over 130,000 students with college credits. ACE and NCCRS have over 2,100 cooperating colleges that will consider accepting credits; the final decision is with the universities.
Enroll now → Course details Download the syllabus All Computer Science courses Every course with PRO →
Why take it here
Why students take Software Engineering with UPI Study
Where the credit goes
Universities that work with NCCRS
Software Engineering carries a NCCRS credit recommendation. These universities work with NCCRS; some are UPI Study's signed partners. ACE and NCCRS have over 2,100 cooperating colleges that will consider accepting credits; the final decision is with the universities.
Thomas Edison State UniversitySigned partner
University of the PeopleSigned partner
Charter Oak State CollegeSigned partner
Strayer UniversitySigned partner
Columbia Southern UniversitySigned partner
Indiana TechSigned partner
Penn StateWorks with NCCRS
Southern New Hampshire UniversityWorks with NCCRS
SUNYWorks with NCCRS
+many more cooperating universitiesFind my college →Find my college → Not listed? Ask Athena in the corner of this page, or book a 15-minute call.
FAQ
Questions students ask us
About Estimating Timelines When Activity Durations Are Uncertain
What is three-point estimation in project management?
How do you calculate a PERT expected duration?
What is the difference between lines-of-code and function point estimation?
What does a wide gap between optimistic and pessimistic estimates mean?
About the Software Engineering course
How many college credits is Software Engineering?
How much does Software Engineering cost and what is included?
Which universities accept UPI Study credits?
How long does Software Engineering take?
How are the exams done?
How do my credits reach my college?
Ready for the full course? Earn 3 credits in Software Engineering.
103 video lessons, a quiz after each one, and the graded work that earns the credit. Recommended for credit by NCCRS.
3 credits · NCCRSEnroll →