The W5HH Framework: Asking the Right Project Questions
Software Engineering · Chapter 13: Project Management, Planning, and Agile GovernanceSection 13.6 · lesson 85 of 1036 min · free with a free account
Free preview
Create a free account to keep watching
It takes a minute and costs nothing. Your free account unlocks all of Chapter 1 and 3 more lessons of Software Engineering.
Lesson complete
Earn the 3 college credits for Software Engineering
Enrolling adds a quiz after each lesson, the graded work and the official transcript. Recommended for credit by NCCRS.
Next lesson: Estimating Timelines When Activity Durations Are Uncertain →← Tackling Common Challenges in Software Project ManagementNext lesson: Estimating Timelines When Activity Durations Are Uncertain →
In this lesson
Not every planning tool is a chart - sometimes it's 7 questions.
- Explain W5HH, and how it differs from a scheduling tool
- Name the 7 W5HH questions, and what each surfaces
- Apply the framework to a simple project
- Explain why an unanswerable question is useful information
Transcript
Everything said in the video, section by section (764 words). Read along, or search it.
Project Management, Planning, and Agile Governance
The W5HH Framework: Asking the Right Project Questions
Not every planning tool is a chart. Sometimes the most useful thing a project can do, is simply make sure that seven basic questions all have real answers. This section covers the W five H H framework, and why its most valuable moment is when a question cannot be answered.
A Different Kind of Tool
Before Any Scheduling
A Gantt chart and a PERT chart both answer questions about timing and sequence. But they assume that scope and resources are already reasonably well understood. The W five H H framework, developed by software engineer Barry Boehm, addresses an earlier and more basic problem. It makes sure the project's fundamentals have actually been thought through, before scheduling any of it. The name comes from its seven questions. Five begin with W, and two begin with H. It is not a chart. It is simply a checklist.
Table 1
The 7 Questions
Here are the seven questions, and what each one is meant to surface. Why asks for the business reason the system is being built at all. What asks for the scope of what will actually be delivered. When asks for the schedule. Who asks who is accountable for each part of the work. Where asks where those responsible people sit, organizationally. How asks for the technical and managerial approach. And how much asks how much of each resource, like budget, effort, and time, the project needs.
Overlaps
Complements, Not Replacements
Two of these questions overlap with ground covered elsewhere. When corresponds to scheduling, covered through Gantt and PERT charts. And how much overlaps with estimating techniques. W five H H does not replace either of them. It simply insists that each question gets asked, as part of a complete picture, alongside the other five.
Table 2
Worked Example: A Feedback Portal
Suppose a company wants to build a customer feedback portal. Why? Complaints are scattered across email and phone calls, with no way to track them. What? A web portal where customers submit feedback, and support staff respond. When? A working version in ten weeks, ahead of the next launch. Who? One developer and one designer, reporting to the support team's manager. Where? Both sit within the support organization. How? Iteratively, with support staff reviewing a working version every two weeks. And how much? One developer, one designer, and a small budget for an email integration. Every answer is short and specific. W five H H is not asking for a lengthy plan, only for confirmation that someone can state each fundamental clearly.
Figure 2
When a Question Has No Answer
The real value of W five H H shows up, when a question does not have a ready answer. Ask each of the seven questions. If there is a clear, specific answer, that fundamental is confirmed. If there is not, that is not a failure of the framework. It is exactly the gap the framework exists to surface, early enough to do something about it. It shows where the project's real risk sits.
Not a 1-Time Checklist
Answers Go Stale
This is also why W five H H is not a one-time checklist, filled out at the start and set aside. Answers that were solid at the beginning can stop being true as work progresses. A who answer can go stale when a team member leaves. A why answer can shift when the business reason behind the project changes. Revisiting the seven questions periodically catches that drift, before it causes real damage.
Apply It
Nobody Can Answer Who
Let's apply that. For the feedback portal, the what and the why are both perfectly clear. But nobody can confidently say who is accountable for the portal's design. What does that suggest? It suggests real risk, regardless of how clear the other answers are. Without a specific person accountable, decisions can stall, or get made inconsistently. A clear scope and a clear business reason do nothing to prevent that on their own.
Key Terms
The Vocabulary of This Section
Let's lock in the key terms. The W five H H framework is a checklist of seven project questions, developed by Barry Boehm. Why, what, when, who, where, how, and how much. Project scoping is clarifying a project's fundamental reason, boundaries, and responsibilities, before detailed planning begins. And stakeholder accountability is clarity about which specific person is responsible for a given part of the project. That is the who question.
Key Takeaways
What to Carry Forward
To pull this together. The W five H H framework is a checklist of seven questions that confirm a project's fundamentals, before scheduling begins. It complements tools like Gantt charts, PERT charts, and estimating techniques. It does not replace them. Good answers are short and specific, not a lengthy plan. A question nobody can answer is valuable information, because it surfaces a real risk early. And the questions are worth revisiting, because answers drift as a project moves.
About Software Engineering at UPI Study
Software Engineering (Computer Science 301) is a self-paced online course of 103 video lessons in 15 chapters, from process models and agile to requirements, design, user interfaces, reliability, security and project management. It carries a NCCRS credit recommendation for 3 semester credits.
Every lesson transcript is free on pages like this one, and the videos are free with a free UPI Study account. Enrolling adds a practice quiz after each lesson, the graded work and final exam that earn the credit, lifetime access, and an official transcript on completion. UPI Study has helped over 130,000 students with college credits. ACE and NCCRS have over 2,100 cooperating colleges that will consider accepting credits; the final decision is with the universities.
Enroll now → Course details Download the syllabus All Computer Science courses Every course with PRO →
Why take it here
Why students take Software Engineering with UPI Study
Where the credit goes
Universities that work with NCCRS
Software Engineering carries a NCCRS credit recommendation. These universities work with NCCRS; some are UPI Study's signed partners. ACE and NCCRS have over 2,100 cooperating colleges that will consider accepting credits; the final decision is with the universities.
Thomas Edison State UniversitySigned partner
University of the PeopleSigned partner
Charter Oak State CollegeSigned partner
Strayer UniversitySigned partner
Columbia Southern UniversitySigned partner
Indiana TechSigned partner
Penn StateWorks with NCCRS
Southern New Hampshire UniversityWorks with NCCRS
SUNYWorks with NCCRS
+many more cooperating universitiesFind my college →Find my college → Not listed? Ask Athena in the corner of this page, or book a 15-minute call.
FAQ
Questions students ask us
About The W5HH Framework: Asking the Right Project Questions
What is the W5HH framework in project management?
What are the seven questions of W5HH?
What does it mean when a W5HH question cannot be answered?
How does W5HH differ from Gantt and PERT charts?
About the Software Engineering course
How many college credits is Software Engineering?
How much does Software Engineering cost and what is included?
Which universities accept UPI Study credits?
How long does Software Engineering take?
How are the exams done?
How do my credits reach my college?
Ready for the full course? Earn 3 credits in Software Engineering.
103 video lessons, a quiz after each one, and the graded work that earns the credit. Recommended for credit by NCCRS.
3 credits · NCCRSEnroll →