Scheduling Policies and Configuration Management Plans
Software Engineering · Chapter 14: Project Estimation, Configuration, and Change ControlSection 14.3 · lesson 88 of 1036 min · free with a free account
Free preview
Create a free account to keep watching
It takes a minute and costs nothing. Your free account unlocks all of Chapter 1 and 3 more lessons of Software Engineering.
Lesson complete
Earn the 3 college credits for Software Engineering
Enrolling adds a quiz after each lesson, the graded work and the official transcript. Recommended for credit by NCCRS.
Next lesson: Configuration Management Processes →← Building Quality into Software Through Management SystemsNext lesson: Configuration Management Processes →
In this lesson
Controlling how and when change arrives, so the schedule stays meaningful.
- Explain why schedules need configuration management policy
- Describe what an SCM plan contains
- Distinguish freeze periods, change windows, and escalating approval
- Explain baselines as the meeting point of schedule and configuration
Transcript
Everything said in the video, section by section (842 words). Read along, or search it.
Project Estimation, Configuration, and Change Control
Scheduling Policies and Configuration Management Plans
An estimated schedule assumes a certain amount of stability in what is being built. But requirements, designs, and code keep changing anyway. This section covers how configuration management controls when that change gets incorporated, so an estimate stays meaningful.
A Moving Target
Why Schedules Need Change Policy
A schedule built from estimation techniques assumes that the target it was estimating stays reasonably stable. But requirements, designs, and code continue to change throughout a real project. Change itself is not the problem. Embracing change can be a genuine strength. The problem is change with no policy governing how, and when, it gets incorporated. If the target keeps shifting right up to the deadline, nobody can commit to a date. Configuration management supplies exactly that discipline.
The SCM Plan
What the Plan Establishes
A configuration management plan, or S C M plan, is a planning-level document. It is not a step-by-step procedure for handling any one change. It identifies which artifacts, like code, documentation, requirements, and test plans, are formally placed under configuration control. It defines who has the authority to approve which kinds of change. It establishes the general approach for how changes are requested, evaluated, and incorporated. And it sets the policy for when, relative to the schedule, different kinds of change are actually permitted.
Scheduling Policies
When Change Gets Allowed
A few recurring policy patterns govern what change is allowed, at any given point in the schedule. A change window designates specific points, between iterations or at a milestone, where less urgent changes are batched and reviewed together. A freeze period restricts changes to only the most critical ones, as a milestone or release approaches. That protects the stability the deadline depends on. And escalating approval requires increasingly senior sign-off for a change as a committed date nears. That is because the cost and risk of any change grows, the less time remains to absorb its consequences.
Figure 1
Restriction Tightens Toward the Deadline
Here is one schedule, running from project start to release, with three change policies. Early on, the schedule is open, and most changes are freely accepted. Then comes a change window, where changes are batched and reviewed together. Then a baseline is set, and the freeze begins. Only critical changes are allowed from there to the release. And all the way across, approval requirements escalate as the deadline gets closer.
Worth Noticing
The Cost of Change Isn't Constant
This connects to a point made about the sequential approach, at the start of this course. The cost of a change is not constant across a schedule. It grows the later the change arrives. Treating every change request as equally easy to accommodate, regardless of timing, ignores that reality. And that is precisely why scheduling policies exist.
Baselines
Where Schedule and Configuration Meet
A baseline is a formally reviewed, agreed-upon snapshot of a set of configuration items, at a specific point in time. It becomes the reference point for measuring any further change. Once something is baselined, changing it means going through the formal change process, rather than editing it freely. And baselines are typically set at points that align with the schedule, like the end of a phase, or a major milestone. That makes a baseline both a scheduled event, and a configuration management concept, at the same time.
Table 1
4 Policies and Their Timing
Here are the four policies, and when each one typically applies. A freeze period restricts changes to critical or high-priority ones, as a release or major milestone approaches. A change window batches and reviews less-urgent changes together, at defined points between milestones or iterations. Escalating approval requires broader sign-off for changes, increasing as a committed date nears. And a baseline formally locks a reviewed snapshot as the reference point, at the end of a phase or a major milestone.
Apply It
A Tweak 2 Weeks Before Release
Let's apply that. Two weeks before release, during the freeze, a stakeholder asks for a small, non-critical tweak to a screen. Because it is not critical, it is held for the next change window, where it is batched and reviewed with other requests. If it were genuinely critical, it could still go ahead. But it would need senior, escalated approval, and it would go through the formal change process against the baseline.
Key Terms
The Vocabulary of This Section
Let's lock in the key terms. An S C M plan is a planning-level document identifying what is under configuration control, who approves changes, and when changes are permitted. A configuration item is an artifact, like code, documentation, a requirement, or a test plan, that is formally placed under configuration control. A freeze period is a window of time, typically near a milestone or release, during which only critical changes are permitted. And a baseline is a formally reviewed snapshot of configuration items, serving as the reference point for all further change.
Key Takeaways
What to Carry Forward
To pull this together. Without a change policy, an estimated schedule quietly becomes fiction. An S C M plan sets what is under control, who approves changes, how changes are handled, and when they are permitted. Change windows batch less urgent changes. Freeze periods restrict change near a release. And approval escalates as deadlines near. All of this exists because the cost of a change grows as the deadline approaches. And a baseline is where schedule and configuration meet, as both a scheduled event and a configuration reference.
About Software Engineering at UPI Study
Software Engineering (Computer Science 301) is a self-paced online course of 103 video lessons in 15 chapters, from process models and agile to requirements, design, user interfaces, reliability, security and project management. It carries a NCCRS credit recommendation for 3 semester credits.
Every lesson transcript is free on pages like this one, and the videos are free with a free UPI Study account. Enrolling adds a practice quiz after each lesson, the graded work and final exam that earn the credit, lifetime access, and an official transcript on completion. UPI Study has helped over 130,000 students with college credits. ACE and NCCRS have over 2,100 cooperating colleges that will consider accepting credits; the final decision is with the universities.
Enroll now → Course details Download the syllabus All Computer Science courses Every course with PRO →
Why take it here
Why students take Software Engineering with UPI Study
Where the credit goes
Universities that work with NCCRS
Software Engineering carries a NCCRS credit recommendation. These universities work with NCCRS; some are UPI Study's signed partners. ACE and NCCRS have over 2,100 cooperating colleges that will consider accepting credits; the final decision is with the universities.
Thomas Edison State UniversitySigned partner
University of the PeopleSigned partner
Charter Oak State CollegeSigned partner
Strayer UniversitySigned partner
Columbia Southern UniversitySigned partner
Indiana TechSigned partner
Penn StateWorks with NCCRS
Southern New Hampshire UniversityWorks with NCCRS
SUNYWorks with NCCRS
+many more cooperating universitiesFind my college →Find my college → Not listed? Ask Athena in the corner of this page, or book a 15-minute call.
FAQ
Questions students ask us
About Scheduling Policies and Configuration Management Plans
What is a software configuration management plan?
What is the difference between a freeze period and a change window?
Why does change approval get stricter as a release date approaches?
How should a non-critical change request be handled during a code freeze?
About the Software Engineering course
How many college credits is Software Engineering?
How much does Software Engineering cost and what is included?
Which universities accept UPI Study credits?
How long does Software Engineering take?
How are the exams done?
How do my credits reach my college?