Turning Intention into Action: The Planned Change Process

UPI Study › Courses › Principles of Management › Free lessons › Lesson 6.4 Free with a free account

Turning Intention into Action: The Planned Change Process

Principles of Management · Chapter 6: Leading Organizational ChangeSection 6.4 · lesson 28 of 11711 min · free with a free account

← Leading Through Uncertainty: The Manager's Role During ChangeNext lesson: Lewin's Change Toolkit: Unfreeze-Change-Refreeze and Force-Field Analysis →

Earn 3 college credits for Principles of ManagementRecommended for credit by NCCRS · Business 101 · self-paced · one payment, lifetime access

In this lesson

Turning intention into action.

  • Distinguish planned from emergent change
  • Describe the 8 stages of planned change
  • Explain how a change is diagnosed before it is designed
  • Recognize the common failure pattern

Transcript

Everything said in the video, section by section (1,546 words). Read along, or search it.

Leading Organizational Change

The Planned Change Process

Most change efforts start with good intentions. Many of them end exactly where they started. This section lays out the general process that turns an intention into a change that actually holds. We begin by separating planned change from the emergent change that happens anyway. Then we walk through the eight stages of planned change, and what each one produces. We spend real time on diagnosis, the stage most often skipped, and the classic error it prevents. Then the change agent, the design of the intervention, resourcing, evaluation, and institutionalization. And we'll name a failure pattern you will recognize the moment you see it in a real organization.

Planned and Emergent

Not All Change Is Designed

Planned change is change deliberately designed and managed, through a defined sequence of stages. Emergent change is different. It arises gradually from ongoing organizational activity, without being centrally designed in advance. It's worth being honest about this from the start. A substantial share of the change inside real organizations is emergent, whatever any formal plan says. Informal adjustments, workarounds, and gradual shifts in practice accumulate on their own. They often move faster than any planned initiative. So this framework describes the planned side of that reality. It's the right approach whenever a change is significant enough, or risky enough, to warrant deliberate design. It is not a claim that every organizational change follows, or should follow, this sequence.

8 Stages

Each Stage Produces What the Next One Needs

The general planned change process runs through eight stages. The key idea is that each stage produces a specific output the next stage depends on. Recognizing the need produces a stated trigger. Diagnosing the problem produces an understanding of the actual problem, rather than its presenting symptom. Identifying options produces a set of genuine alternatives. Selecting an intervention produces the chosen one. Planning the implementation produces a concrete plan, with resources attached. Implementing produces the change itself. Evaluating produces evidence of whether it worked. And institutionalizing produces a change that survives past the attention of the people who drove it. Skip a stage, and the next one starts without the input it needs.

Figure 6.4.1

The 2 Stages Most Often Skipped

Here are the eight stages laid out as one continuous path. Two of them are marked, because they are the ones most often skipped. The first is diagnosis, right near the start. The second is institutionalization, at the very end. Notice where both of them sit. Diagnosis comes before the visible activity of designing and implementing a solution. Institutionalization comes well after implementation has already produced its visible result. In both places, the active, visible work of change is either not yet underway, or no longer underway. That is exactly why both are so easy to shortchange under time pressure.

Diagnosis

Find Out What Is Actually Happening

Diagnosis is the deliberate gathering of data on what is actually happening, before deciding what to change. It's the stage most consistently skipped under time pressure. That connects directly to the diagnosis problem from Subchapter six point two. Skipping diagnosis is precisely what lets an organization change whichever target is easiest. The target actually responsible never gets identified. And diagnosis has a visibility problem. It happens before anything that looks like action. To a busy leader, it can feel like delay. In fact, it is what makes the action worth taking. Four methods are available for diagnosis, each with its own reach, and its own limitation.

Table 6.4.1

4 Diagnostic Methods, None Unbiased

Table six point four point one compares the four diagnostic methods on what they reveal, what they cost, and their bias. Interviews reveal rich, detailed, individually contextualized understanding, straight from the people closest to a problem. They're costly in time, especially at scale. And what people say may not match what they actually do. Surveys gather structured information across a large group, cheaply per respondent, though they're harder to design well. Their depth is limited, and the framing of the questions can shape the answers. Observation reveals what people actually do, independent of what they say they do. It's costly in time and access. And people often behave differently when they know they're being watched. Performance data offers objective, already-available measures, at very low extra cost. But it reflects only what the organization already chose to measure, which may not be what matters. No single method is unbiased. That's why good diagnosis often combines more than one.

The Diagnostic Error

The Presenting Problem Isn't Always the Real One

The most consequential diagnostic error has a name. Mistaking the presenting problem for the real one. The presenting problem is the issue as it was first described, often by whoever raised it. The error is accepting it as the real problem, without checking that the two are actually the same thing. Picture a department head who reports that her team needs more people. That's a presenting problem. Diagnosis might reveal the real problem is an inefficient handoff between two roles. No amount of extra headcount would fix that. The inefficiency would simply be reproduced, with more people involved in it. Accepting the presenting problem at face value is faster than diagnosing it. That's exactly why it happens so often, under the same time pressure that causes diagnosis to be skipped altogether.

The Change Agent

Inside or Outside?

Someone has to drive the change. That person or group is the change agent. The role can be filled from inside the organization or from outside, and each brings a different balance. An internal change agent brings existing organizational knowledge, and established relationships. She also has a stake in outcomes that persist after the change is complete. But she brings existing loyalties and political entanglements too. Those can compromise how objective she is perceived to be. An external change agent brings genuine outside objectivity, and specialized expertise the organization may lack. But she lacks the internal knowledge and relationships an insider has. And she typically has no lasting stake once the engagement ends. That can affect how invested she is in a solution actually holding.

Designing the Intervention

4 Design Decisions

Once a problem is correctly diagnosed, designing the intervention involves four related decisions. Scope is how much of the organization the intervention touches. Sequence is the order in which its parts are carried out. Pace is how quickly it proceeds. And the pilot decision asks whether to test the intervention on a small scale, before committing to it fully. That last decision hides a distinction worth making explicit. A pilot that genuinely tests whether something works is designed to produce real information. That includes the possibility that the intervention should be abandoned, or substantially revised. A pilot that merely demonstrates is designed, consciously or not, to confirm a conclusion leadership has already reached. On paper, the two look similar. Both involve a small-scale trial. Only the first one is genuinely diagnostic.

Plan and Evaluate

Resources, and a Baseline

Implementation planning specifies who does what, by when. It also specifies the resources committed to the plan. Time, budget, and personnel. This point deserves to be stated plainly. An unresourced change plan is an announcement, not a plan. A document describing what should happen, without allocating the time and resources to do it, communicates an intention. It doesn't commit the organization to an outcome. And that gap is exactly where many change efforts quietly fail. Evaluation asks what would show the change worked. The answer has to be measured against a baseline, established before the change began. Without that baseline, an organization can't tell genuine improvement from normal variation that would have happened anyway. So establishing the baseline is part of the diagnosis and planning stages. It can't be credibly reconstructed after the fact, once the change is already underway.

Institutionalization

Does the Change Survive Its Champion?

Institutionalization is the stage that decides whether a change survives, past the attention of the people who drove it. It previews the refreezing stage developed fully in Subchapter six point five. Here's the test. Does the change depend on the continued personal attention of its original champion? If so, it hasn't been institutionalized, however successful it looks. Genuine institutionalization embeds the change in structure, measurement, and routine, so it persists independently of any one person. Now put the pieces together, and a familiar failure pattern appears. A strong announcement, paired with weak diagnosis, no resourcing, and no baseline measurement. Then reversion to the previous state, within a year. Each element of that pattern traces to a specific stage being skipped or shortchanged. That's why the process is a full sequence, and not a menu of stages to pick from freely. Lewin's model in Subchapter six point five, and Kotter's eight steps in six point six, elaborate this same process. They don't replace it.

Case Vignette

Solving a Problem Harborline Never Had

Here is a composite case, constructed for instruction. A regional office of Harborline Manufacturing reported persistent delays in processing customer orders. Acting on that presenting problem, leadership approved a new order-management software system, to speed up processing. The rollout was announced with considerable fanfare. But no one had gathered data on where the delay actually occurred, before choosing the software. A brief diagnostic review, done only after the system was purchased, found the processing software had never been the bottleneck. The real delay sat in a manual approval step further upstream. That same approval was still required before an order could even reach the new software. The new system was implemented on schedule, and it worked exactly as designed. And order processing delays continued, almost unchanged. Leadership had jumped from recognizing a need straight to selecting an intervention. It skipped the one stage that would have caught the mismatch, before any money was spent.

About Principles of Management at UPI Study

Principles of Management (Business 101) is a self-paced online course of 117 video lessons in 17 chapters, from the classical schools and the four management functions to leadership, motivation, change, human resources, strategy and ethics. It carries a NCCRS credit recommendation for 3 semester credits.

Every lesson transcript is free on pages like this one, and the videos are free with a free UPI Study account. Enrolling adds a practice quiz after each lesson, the graded work and final exam that earn the credit, lifetime access, and an official transcript on completion. UPI Study has helped over 130,000 students with college credits. ACE and NCCRS have over 2,100 cooperating colleges that will consider accepting credits; the final decision is with the universities.

Why take it here

Why students take Principles of Management with UPI Study

The core of every business degreePrinciples of Management covers how organizations plan, organize, lead and control their work. It is a core course in business administration and management degrees, and the base for later courses in leadership, organizational behavior and strategy.
Credit at a fraction of the priceThe same 3 credits can cost $750 or more at a US college. Here it is one payment, self-paced, with lifetime access.
Finish your degree soonerTransfer credits reduce the courses you still owe, so you can graduate earlier or lighten a heavy semester.
Strengthen an applicationA completed college-level course on an official transcript shows admissions and scholarship committees you can do the work.
Study on your own scheduleNo start dates, no deadlines. Watch the lessons, practice, and take the final when you are ready.
130,000+students helped with college creditsACE and NCCRS have over 2,100 cooperating colleges that will consider accepting credits; the final decision is with the universities.

Where the credit goes

Universities that work with NCCRS

Principles of Management carries a NCCRS credit recommendation. These universities work with NCCRS; some are UPI Study's signed partners. ACE and NCCRS have over 2,100 cooperating colleges that will consider accepting credits; the final decision is with the universities.

Find my college → Not listed? Ask Athena in the corner of this page, or book a 15-minute call.

FAQ

Questions students ask us

About Turning Intention into Action: The Planned Change Process

What is the difference between planned change and emergent change?
Planned change is deliberately designed and managed through a defined sequence of stages, while emergent change arises gradually from ongoing activity without being centrally designed. Much real organizational change is emergent, through workarounds and gradual shifts in practice. A planned process is the right approach when a change is significant or risky enough to warrant deliberate design.
What are the stages of the planned change process?
The general planned change process has eight stages: recognizing the need, diagnosing the problem, identifying options, selecting an intervention, planning the implementation, implementing, evaluating, and institutionalizing. Each stage produces an output the next one depends on. Diagnosis and institutionalization are the two stages most often skipped, because they happen before or after the visible work of change.
What is the difference between a presenting problem and the real problem?
The presenting problem is the issue as it is first described, often by whoever raised it, while the real problem is what diagnosis reveals is actually happening. For example, a manager may say her team needs more people, but the real cause might be an inefficient handoff between two roles. Adding staff would simply reproduce that inefficiency with more people involved.
How do you diagnose a problem before making an organizational change?
Diagnosis means gathering data on what is actually happening before deciding what to change. Four common methods are interviews, surveys, observation and existing performance data. Each has limits: people may say one thing and do another, survey wording shapes answers, people act differently when watched, and performance data covers only what was already measured. Combining methods and setting a baseline helps later evaluation.

About the Principles of Management course

How many college credits is Principles of Management?
Principles of Management (Business 101) carries a NCCRS credit recommendation for 3 semester credits. ACE and NCCRS have over 2,100 cooperating colleges that will consider accepting credits; the final decision is with the universities.
How much does Principles of Management cost and what is included?
$250, paid once, with lifetime access: all 117 video lessons, a practice quiz after each, the graded work and final exam, and an official transcript when you finish. Students who want several courses choose UPI Study PRO instead.
Which universities accept UPI Study credits?
UPI Study has signed partner agreements with universities such as Thomas Edison State University, University of the People and Charter Oak State College, and works with universities such as Penn State, SNHU and SUNY. ACE and NCCRS have over 2,100 cooperating colleges that will consider accepting credits; the final decision is with the universities. Use "Find my college" on this page to check yours.
How long does Principles of Management take?
It is self-paced with no deadlines. The 117 lessons total about 24 hours of video; most students add reading and practice time and finish in a few weeks to a few months, on their own schedule.
How are the exams done?
Quizzes and assignments are online in the course. The final exam is taken online with proctoring; a person on the UPI Study team checks assignments, usually within two days.
How do my credits reach my college?
When the course shows 100% complete, request the official transcript from your dashboard. It is sent to the college you name, and you can send it to more than one. Check your college first with "Find my college" on this page, or ask Athena.

Ready for the full course? Earn 3 credits in Principles of Management.