Acceptance Criteria and Procurement Planning Strategies

UPI Study › Courses › Project Management › Free lessons › Lesson 3.8 Free with a free account

Acceptance Criteria and Procurement Planning Strategies

Project Management · Chapter 3: Building a Comprehensive Project PlanSection 3.8 · lesson 22 of 7314 min · free with a free account

← Risk Identification and Comprehensive Risk PlanningNext lesson: Project Communication Plan Development →

Earn 3 college credits for Project ManagementRecommended for credit by NCCRS · Business 230 · self-paced · one payment, lifetime access

In this lesson

Writing checkable acceptance criteria and planning what to buy and when.

  • Write acceptance criteria that are specific, testable, unambiguous, pass or fail, measured, and tied to a verification method
  • Describe an acceptance procedure covering reviewers, methods, review window, rejection records, and sign-off
  • Compare make and buy options on cost, break-even quantity, capability, capacity, control, risk, and schedule
  • Calculate the latest procurement start date by counting back from the need date

Free study notes

Get this lesson's notes by email

The key points and 4 practice questions with answers, in your inbox. One email, free.

One email. Unsubscribe in one click.

Transcript

Everything said in the video, section by section (1,826 words). Read along, or search it.

Opening Question

One Kiosk, Two Stopwatch Readings

The Marrowfield Arts Center has a new self-service ticket kiosk in its lobby, and today is its acceptance test. The contract says: the kiosk prints a ticket within 10 seconds. Omar, the supplier's technician, times it at about 8 seconds. Dana Reyes, the project manager, times the same purchase at 13. Omar starts his stopwatch when payment is approved, and stops when printing begins. Dana starts when a patron touches Pay, and stops when the ticket leaves the slot. Both read the same sentence honestly. So did the kiosk pass? And what should the sentence have said?

Definition

Conditions the Accepting Party Agrees To

Acceptance criteria are the conditions a deliverable must meet before the accepting party agrees it's complete, and satisfies what was asked. They're written during planning, not at the end, because a standard invented after the work is done, gets argued over by people who already know the result. They come from two earlier products. The scope statement lists a deliverable, like a ticket kiosk in the lobby. A requirement says what it must do: sell a ticket without staff help. The criterion turns that requirement into a condition someone can check. A criterion with no requirement behind it is an unrequested extra, or a sign of a missing requirement. A requirement with no criterion is a promise nobody can confirm.

Six Properties

What Makes a Criterion Usable

Six properties separate a usable criterion from a hopeful one. Specific: it names the exact deliverable and the exact behavior being judged. Testable: an inspection, measurement or trial can produce evidence. Unambiguous: two competent readers who haven't conferred take the same meaning. Pass or fail: partly met means undecided. It carries a measure, the quantity and threshold that decide pass from fail. And it names a verification method: who checks, with what instrument, under what conditions. The properties depend on each other. A threshold with no method invites a fight about how the number was obtained. That's exactly what happened at the kiosk. And the accepting party, the role with authority to say yes, sits right beside each criterion.

Examples

Three Criteria a Stranger Could Check

Here are three criteria from the center's launch, each ending in a number a stranger could check. Online ticket page: a customer can buy a ticket without staff help. Ten of ten scripted test purchases complete in five screens or fewer, on a phone and a laptop. Printed program board: every show and price matches the signed price list. Zero mismatches, and every line readable from a two-meter mark. Staff quick-reference guide: a staff member who's never seen it processes a sale with the guide alone, in four minutes or less, asking for help no more than once. That last one judges a guide by a newcomer, because a guide judged by its author always seems clear. Thresholds come from the requirement, not from what the builder already knows it can hit. A threshold set for the builder's comfort doesn't measure the owner's need.

Rewriting Weak Criteria

From Sounds Fine to Measurable

Weak criteria usually start as phrases that sound fine in a meeting. The page responds quickly becomes: a search on the center's standard tablet returns results in two seconds or less, in at least 19 of 20 timed trials. Nineteen of twenty tolerates the odd slow result, without hiding a pattern. The board looks professional becomes: only the two approved typefaces and the approved logo, with zero deviations from the one-page style sheet. Staff are trained becomes: all six counter staff attend the 45-minute session, and each correctly processes three of three practice sales. Each rewrite forces a decision that had been postponed, while changing it still costs a conversation, not rework. But don't overshoot. A criterion more precise than the need can reject a deliverable that serves it.

Where Criteria Live

WBS Dictionary and Quality Metrics

Criteria live in two places. The WBS dictionary entry for the work package that makes the deliverable, so the worker sees the target when work begins, not at handover. And they link to quality metrics. A metric defines what is measured and how, like response time in seconds. A criterion applies a threshold on a metric, to one deliverable, at one handover. It borrows the metric's definition, so the same measurement is never defined twice.

Acceptance Procedure

Who Reviews, How, and Who Signs

The acceptance procedure is the agreed sequence for presenting, examining, and accepting or rejecting a deliverable. It answers five questions. Who reviews? People competent to run the methods, and independent enough from the builder to report a failure. They examine and report; the accepting party decides. How? The methods in order, with the test environment and data, so a second person could reproduce the result. How long? The review window is the days after delivery within which the accepting party must respond. If it passes in silence, does silence count as acceptance? That's a contract term, for counsel. How is rejection recorded? A written entry: the criterion missed, the evidence, the date, the observer, and the correction required. And who signs? Sign-off is a recorded statement by a named authority. The plan names a role, so one person's absence can't stall the project.

Quick Check

Which Lobby Display Draft Is Checkable

Quick check. Three drafts for the lobby display. Which one could two strangers check, and get the same answer? Pause, and decide. The second. It names a position, a count, and a pass condition, so the check produces evidence. Bright, clear and easy have no measure, and a readable size still leaves each reader to decide what readable means.

Make or Buy

Six Factors From Cost to Schedule

Planning also decides what to buy. Make-or-buy analysis compares producing an item yourself with buying it from an outside seller. Six factors are compared. Cost: the total for the whole quantity, one-time and repeating. Capability: do we have the skills and tools? Capacity: do we have the time and people free when it's needed? A team can be fully capable and still have no capacity. Control: can we direct design, quality and changes? Risk: what could go wrong, and who bears it? Buying moves some risk, but moving risk isn't removing it. And schedule: can it be ready by the need date?

Worked Example

Forty Display Stands and Break-Even

The center needs forty identical wooden display stands. Sam's workshop could make them: a one-time setup of $600 for tools and a jig. Then each stand needs $22 of materials, and 3 hours of labor at $18 an hour, which is $54. That's $76 per stand. Forty stands at 76 is $3,040, plus the setup: $3,640 to make. A supplier quotes $85 per stand, plus one $120 delivery charge. Forty times 85 is 3,400, plus 120: $3,520 to buy. Buying is cheaper by $120. The break-even quantity is where the totals match: the difference in fixed charges, 480, divided by the saving per stand from making, 9. About 53 stands. Below that, buying is cheaper on cost alone. Above it, making is. But the gap is small. With a quarter-hour less labor per stand, making saves 180, and comes out 60 cheaper. And the other factors can reverse a close result.

Quick Check

Sixty Stands Tips the Balance

Quick check. Same quotes, but the center now needs sixty stands. On cost alone, which option is cheaper? Pause, and decide. Making. Six hundred plus sixty times seventy-six is five thousand one hundred sixty. Buying is sixty times eighty-five plus one hundred twenty: five thousand two hundred twenty. Sixty is past the break-even of about fifty-three, so the nine-dollar saving per stand now outweighs the bigger setup.

Applying the Factors

Why the Kiosk Was Bought

The same analysis decided the kiosk itself. The center's part-time volunteer technician could have built the software, and his time carried no charge. But he was committed to the box-office system in those same weeks: a capacity problem. And nobody else could maintain custom software: capability and control. So Dana bought, accepting a higher cash cost and dependence on one supplier, for a firm delivery date and a support arrangement. Should every factor be priced? One view: express it all in money, or preference sneaks in. The other: some things, like independence from one seller, can't be honestly priced. How accurate such estimates are is empirical. How much weight control deserves for its own sake is a question of values.

Procurement Plan

What It Covers From Need to Closing

Procurement is acquiring goods or services from outside. The procurement management plan says how it will be done, from deciding what to buy to closing the agreements. It covers what is to be bought, with quantities and specifications; the approach for finding and comparing sellers; and the roles, including who may sign. Then lead times, the elapsed time of each step; the standard documents the organization already uses; and constraints, like spending ceilings, approval thresholds, and legal rules for counsel. It names the documents to expect: requests for information, quotation and proposal, a statement of work, and the contract. They're developed later in the course.

Source Selection

Weighted Criteria Set Before Offers Arrive

Source-selection criteria are the factors, set in advance, for comparing sellers' offers. Each gets a weight, usually totaling 100. Why in advance? Once offers arrive, evaluators can see who's cheapest or familiar, and weights chosen then can drift, consciously or not, toward a favorite. For the stands: meeting the specification, 30. Price, 25. Delivery reliability, 20. Warranty and support, 15. Relevant past work, 10. Weights should follow the project's priorities. If the biggest threat is a fixed opening date, rating delivery below price contradicts it. Some requirements work better as a pass or fail screen, like holding a required license. And remember: source-selection criteria judge promises before award; acceptance criteria judge the delivered work.

Timing

Counting Back From the Need Date

Finally, timing. The need date is when a purchased item must be accepted and ready. The latest procurement start date is the last day you can begin and still make it. Work backward through five stages: solicitation, selection, contracting, delivery, and acceptance. With a need date of June 1st, the lead times are 14, 10, 12, 30 and 5 days: 71 days in all. Count back: May's 31 days reach May 1st, April's 30 reach April 1st, and 10 more reach March 22nd. That's the latest start. Check forward: each stage starts the day the last one ends, and acceptance ends on June 1st. Use calendar days, converting any working-day quotes. Starting later makes the date unreachable, day for day. And a 10-day buffer would move the start to March 12th.

Back to the Kiosk

Start, Stop, Count, and Limit Written Down

Back to the kiosk. Omar and Dana each read the ten seconds honestly. The criterion had a threshold, but no verification method. Dana rewrites it. Timed by stopwatch, from a patron touching Pay until the ticket fully leaves the slot, at least nine of ten test purchases finish in twelve seconds or less. The supplier wouldn't sign ten seconds on the patron's definition, so Dana accepted twelve, after a week of negotiation. Now the start, the stop, the count and the limit are all written down. The next test has one answer.

Key Takeaways

Criteria, Procedure, Make or Buy, Dates

To recap. Every acceptance criterion needs a measure with a threshold, and a verification method. The acceptance procedure settles who reviews, how, how long, how rejections are recorded, and who signs. Make or buy weighs cost alongside capability, capacity, control, risk and schedule. And the latest procurement start date is found by counting back from the need date.

About Project Management at UPI Study

Project Management (Business 230) is a self-paced online course of 73 video lessons in 12 chapters, from starting and defining a project to planning, budgets, scheduling tools, proposals, contracts, execution, monitoring, closure, teams and certification. It carries a NCCRS credit recommendation for 3 semester credits.

Every lesson transcript is free on pages like this one, and the videos are free with a free UPI Study account. Enrolling adds a practice quiz after each lesson, the graded work and final exam that earn the credit, lifetime access, and an official transcript on completion. UPI Study has helped over 130,000 students with college credits. ACE and NCCRS have over 2,100 cooperating colleges that will consider accepting credits; the final decision is with the universities.

Why take it here

Why students take Project Management with UPI Study

How projects are planned, run and closedProject Management teaches how to deliver work on time and on budget: scope, schedules, the critical path, budgets and earned value, risk, contracts, monitoring and closing a project, and leading the team. It is a common course in business, management and engineering degrees.
Credit at a fraction of the priceThe same 3 credits can cost $750 or more at a US college. Here it is one payment, self-paced, with lifetime access.
Finish your degree soonerTransfer credits reduce the courses you still owe, so you can graduate earlier or lighten a heavy semester.
Strengthen an applicationA completed college-level course on an official transcript shows admissions and scholarship committees you can do the work.
Study on your own scheduleNo start dates, no deadlines. Watch the lessons, practice, and take the final when you are ready.
130,000+students helped with college creditsACE and NCCRS have over 2,100 cooperating colleges that will consider accepting credits; the final decision is with the universities.

Where the credit goes

Universities that work with NCCRS

Project Management carries a NCCRS credit recommendation. These universities work with NCCRS; some are UPI Study's signed partners. ACE and NCCRS have over 2,100 cooperating colleges that will consider accepting credits; the final decision is with the universities.

Find my college → Not listed? Ask Athena in the corner of this page, or book a 15-minute call.

FAQ

Questions students ask us

About Acceptance Criteria and Procurement Planning Strategies

What are acceptance criteria in project management?
Acceptance criteria are the conditions a deliverable must meet before the accepting party agrees it is complete and satisfies what was asked. They turn a requirement into something checkable, such as ten of ten scripted test purchases completing in five screens or fewer. They are written during planning, because a standard invented after the work is done gets argued over by people who already know the result.
Why does an acceptance criterion need a verification method as well as a threshold?
A threshold without a verification method lets two honest people measure the same thing differently and reach opposite results. A criterion that says a kiosk prints a ticket within 10 seconds failed because one tester timed from payment approval and another from touching Pay. A usable criterion states who checks, with what instrument, under what conditions, and exactly where measurement starts and stops.
How do you calculate the break-even quantity in a make-or-buy analysis?
Divide the difference in fixed costs by the saving per unit from the cheaper-per-unit option. If making costs a $600 setup plus $76 per stand and buying costs $85 per stand plus a $120 delivery charge, the break-even is 480 divided by 9, about 53 stands. Below that quantity buying is cheaper on cost alone, and above it making is cheaper.
How do you find the latest procurement start date?
Count backward from the need date through the lead times of each procurement stage: solicitation, selection, contracting, delivery, and acceptance. With a June 1 need date and lead times of 14, 10, 12, 30, and 5 days, the total is 71 calendar days, so the latest start is March 22. Starting any later pushes the finish past the need date day for day.

About the Project Management course

How many college credits is Project Management?
Project Management (Business 230) carries a NCCRS credit recommendation for 3 semester credits. ACE and NCCRS have over 2,100 cooperating colleges that will consider accepting credits; the final decision is with the universities.
How much does Project Management cost and what is included?
$250, paid once, with lifetime access: all 73 video lessons, a practice quiz after each, the graded work and final exam, and an official transcript when you finish. Students who want several courses choose UPI Study PRO instead.
Which universities accept UPI Study credits?
UPI Study has signed partner agreements with universities such as Thomas Edison State University, University of the People and Charter Oak State College, and works with universities such as Penn State, SNHU and SUNY. ACE and NCCRS have over 2,100 cooperating colleges that will consider accepting credits; the final decision is with the universities. Use "Find my college" on this page to check yours.
How long does Project Management take?
It is self-paced with no deadlines. The 73 lessons total about 15 hours of video; most students add reading and practice time and finish in a few weeks to a few months, on their own schedule.
How are the exams done?
Quizzes and assignments are online in the course. The final exam is taken online with proctoring; a person on the UPI Study team checks assignments, usually within two days.
How do my credits reach my college?
When the course shows 100% complete, request the official transcript from your dashboard. It is sent to the college you name, and you can send it to more than one. Check your college first with "Find my college" on this page, or ask Athena.

Ready for the full course? Earn 3 credits in Project Management.

73 video lessons, a quiz after each one, and the graded work that earns the credit. Recommended for credit by NCCRS.

Project Management
3 credits · NCCRS
Enroll →