Project Communication Plan Development

Project Management · Chapter 3: Building a Comprehensive Project PlanSection 3.9 · lesson 23 of 7313 min · free with a free account

← Acceptance Criteria and Procurement Planning StrategiesNext lesson: Logic, Paths, and Schedule Optimization →

Earn 3 college credits for Project ManagementRecommended for credit by NCCRS · Business 230 · self-paced · one payment, lifetime access

In this lesson

Planning who gets what information, how, how often, and from whom.

  • Analyze each stakeholder's information needs by content, detail, frequency, format, and confidentiality
  • Choose push, pull, or interactive communication based on urgency, sensitivity, audience size, and need for dialogue
  • Build a communication matrix with one owner per row and an escalation path with a time trigger
  • Calculate the number of possible communication channels using n times n minus one, divided by two

Free study notes

Get this lesson's notes by email

The key points and 4 practice questions with answers, in your inbox. One email, free.

One email. Unsubscribe in one click.

Transcript

Everything said in the video, section by section (1,759 words). Read along, or search it.

Opening Question

News That Arrived From the Wrong Source

On an earlier renovation, Marrowfield's library director, Marcus Bell, heard about a delayed shelving delivery from the supplier's own phone call, not from the project. And the front-desk staff first saw their rearranged work area, on the morning they were due to work in it. Several were furious. Nobody had been lazy. So what was missing? Now Dana Reyes is planning the next renovation, and she means to find out.

Purpose

Right Information, People, Time, and Form

What was missing was a communication plan: who receives what information, in what form, how often, from whom, and what happens when a problem must move up. Its purpose: the right information, to the right people, at the right time, in a usable form. Each part can fail on its own. Accurate news can reach the wrong person, arrive three weeks late, or come as a forty-page report to a sponsor who needed one paragraph. Left to habit, communication follows friendship and convenience: people sitting nearby hear everything. A plan replaces that with need.

Three Inputs

Stakeholder Register, RACI, and Organizational Rules

Priya Nair, the planning analyst, gathers three inputs. First, the stakeholder register: who's affected, what they need, and how engaged each should be. A stakeholder who should move from neutral to supportive needs more than status notices. One who just needs to stay informed may need only a short periodic note. Second, the RACI chart. It already names who's consulted or informed about each deliverable, and who's accountable, which suggests who should own the related messages. Third, organizational rules the project didn't choose: a required report template, contract information only to named people, formal decisions in writing. They're cheaper to find before the plan than after.

Requirements Analysis

Five Questions for Every Audience

Communication requirements analysis asks five questions of every register entry: what information, at what level of detail, how often, in what format, and with what confidentiality. Marcus, the director, funds the work. He needs a short weekly summary of cost, schedule and risk, plus immediate word of any threat to the opening date. It's confidential: it includes contract prices. The contractor needs daily or weekly detail, drawings and access times, and a way to ask questions. That calls for an exchange, not a note. The front-desk staff need advance notice of moves and training dates, and a chance to say what won't work in practice. Neighbors need a plain-language notice before noisy work begins, and a way to complain. The needs differ in kind, not just volume. No single status report serves all four.

Sender-Receiver Model

Encoding, Channel, Decoding, Feedback, and Noise

To decide how a message should travel, picture the sender-receiver model. A sender has something to convey to a receiver. The sender encodes the meaning into words, numbers or images. It's transmitted through a channel, like an email, a conversation or a posted notice. The receiver decodes it back into meaning, and feedback, the receiver's response, shows the sender whether the meaning arrived. Noise is anything that distorts the message on the way: a bad audio line, jargon, or an inbox so full the message is never read. The lesson: sending isn't communicating. Only feedback shows whether the receiver understood something close to what you meant. The model is criticized as too mechanical, since receivers actively interpret. Feedback partly answers that. For planning, it's a checklist: when a message fails, at which step did it fail?

Communication Methods

Push, Pull, and Interactive

Methods are classed by who starts the exchange. Push communication is sent to chosen recipients without a request: a weekly status email, a mailed notice. The sender controls delivery, but push doesn't show whether anyone read or understood it. Pull communication puts information where people retrieve it when they choose: a project website, a document library, a dashboard. It suits large audiences and bulky material, if people know to look. Interactive communication is a real-time exchange: a meeting, a call, a workshop. It has the richest feedback, but costs the most time, and needs people available together. Four factors decide. Urgency: how fast must it arrive? Sensitivity: how bad if it's misread or misdirected? Audience size. And the need for dialogue: questions, negotiation, agreement.

Quick Check

A Wall That Cannot Be Built

Quick check. A survey shows the planned wall can't be built as drawn, and work stops tomorrow unless the architect agrees a fix. Which method fits best? Pause, and decide. Interactive. It's urgent, and it needs dialogue: the contractor and architect must ask questions and agree a fix. A pushed note would wait to be read, and a pull website would wait to be found. Neither gets an agreement by tomorrow.

Choosing a Channel

Formal or Informal, Written or Spoken

Then the channel. Formal channels follow rules and leave a record: a signed change request, minutes, a scheduled report. They support accountability, but they're slower. Informal channels, like a hallway chat, are quick and build relationships, but leave no record, so decisions made there are easy to forget or dispute. Written channels give a durable, checkable record. Spoken ones carry tone and allow instant correction. Match channel to message. A decision that commits money is written and formal. A first warning that a deadline's at risk is often spoken first, then confirmed in writing. A message sent through a channel the receiver doesn't use or trust is, for practical purposes, not sent.

Communication Matrix

One Row per Audience, One Owner

Dana gathers these decisions into a communication matrix: one row per audience, with columns for content, method, frequency, owner, and escalation path. Marcus: a one-page weekly summary, pushed, plus same-day notice of any threat to the opening date, because a weekly rhythm alone could let bad news wait six days. The contractor: a weekly site meeting, interactive, because the work needs questions and agreement. Neighbors: a pushed notice at least five working days before noisy work, since they're many, and no dialogue is needed first. Finance: cost reports posted on the first working day of each month, pull, with access restricted, because the content is confidential. Every row has exactly one named owner. When a message is everyone's job, it quietly stops the first week the owner's away.

Completeness Test

Register Describes People, Matrix Describes Actions

The matrix also tests completeness. Every stakeholder in the register appears in some row, or is consciously left out, and every row traces back to the register. Don't confuse the two. The register describes people: who they are, what they want, how engaged they should be. The matrix describes actions: what's sent to them, by what method, by whom, and when. The register is the input; the matrix is the output.

Escalation Path

Time Triggers That Move Problems Up

Each row also needs an escalation path: the route a problem takes to higher levels of authority when it isn't solved where it arose. A workable path defines the levels, like work owner, project manager and sponsor; the time triggers that force a move up; and who is told at each level. Why triggers? Without one, bad news gets held in hope, and by the time it moves up, the options have narrowed. Dana's rule: tell the sponsor when the opening date is expected to slip by more than three working days. Sam Kowalski, the site supervisor, hears that shelving planned for working day 20 will arrive on day 27. The slip is 7 days, more than 3, so Marcus hears within a working day. Had it been day 22, a 2-day slip, Sam would handle it himself and report it in the weekly summary.

Debate

Are Fixed Escalation Triggers Wise

Fixed triggers are disputed. For them: people naturally delay bad news, a stated trigger removes the awkward judgment call, and it protects junior staff from blame for raising alarms. Against: a fixed number can't tell a trivial slip from a serious one, and mechanical escalation floods senior people with minor items. Whether triggers lead to earlier reporting is empirical, and depends on the setting. How much to value predictability over flexibility is a question of values.

Channel Formula

Why Big Teams Need Structure

Here's why big teams need structure. A communication channel, for counting, is one two-way line between a pair of people. Among n people, the number of channels is n times one less than n, divided by two. Each person can talk to every other, but that counts each pair twice. Two people: one channel. Five people: ten. Eight people: twenty-eight. Add a ninth person, and it's thirty-six: eight new channels. At twelve people, it's sixty-six. People rose sixfold from two; channels rose from one to sixty-six. So plans use sub-teams, named leads, regular meetings, and one place for shared information. A hub, where everyone talks through one person, needs only n minus one lines, but overloads the hub. The formula counts possible channels, not messages actually sent, and treats every pair as equal. It's a warning that people add coordination cost, not a precise measure.

Quick Check

Growing a Team From Six to Ten

Quick check. A team of six grows to ten. How many more possible communication channels does it now have? Pause, and decide. Thirty more. Six people have six times five over two: fifteen channels. Ten people have ten times nine over two: forty-five. Forty-five minus fifteen is thirty. Four is the added people, and forty-five is the new total, not the increase.

Completing the Plan

Glossary, Templates, Constraints, and Updates

A matrix alone isn't a complete plan. It also needs a glossary, so everyone decodes the project's terms and abbreviations the same way. Templates for recurring messages, like status summaries and minutes. Constraints, like budget, languages, time zones, or audiences without reliable internet, who can't rely on a pull website. And a process for updating the plan: who may change it, when it's reviewed, and what forces a revision, like a new stakeholder, a scope change, or complaints about late messages. Finally, test the plan on its audiences before relying on it. Show Marcus a sample summary. Ask the front desk if a session time works. That's feedback, applied to the plan.

Back to the Library

Friday Summaries and Front-Desk Sessions

Back to the question: what was missing last time? Not effort. A decision about who needed what, and by which method. This time, Marcus gets a push: five lines every Friday, with any threat to the opening date phoned in the same day. Amara Osei, who leads the front-desk staff, gets interactive sessions before each stage of work, because their cooperation depends on understanding. At the first session, Amara spots that the planned layout blocks the book-return door. Only dialogue would have found that. The trade-off: evening sessions lengthen Dana's week, and Marcus gets less detail than he may later want. Both are recorded, on purpose.

Key Takeaways

Audiences, Methods, Owners, and Channels

To recap. Analyze each audience: what they need, in what detail, how often, in what form, and how confidential. Choose push, pull or interactive by urgency, sensitivity, audience size, and the need for dialogue. Give every row of the matrix one owner, and an escalation path with a time trigger. Channels grow as n times one less than n, over two, so structure communication as teams grow.

About Project Management at UPI Study

Project Management (Business 230) is a self-paced online course of 73 video lessons in 12 chapters, from starting and defining a project to planning, budgets, scheduling tools, proposals, contracts, execution, monitoring, closure, teams and certification. It carries a NCCRS credit recommendation for 3 semester credits.

Every lesson transcript is free on pages like this one, and the videos are free with a free UPI Study account. Enrolling adds a practice quiz after each lesson, the graded work and final exam that earn the credit, lifetime access, and an official transcript on completion. UPI Study has helped over 130,000 students with college credits. ACE and NCCRS have over 2,100 cooperating colleges that will consider accepting credits; the final decision is with the universities.

Why take it here

Why students take Project Management with UPI Study

How projects are planned, run and closedProject Management teaches how to deliver work on time and on budget: scope, schedules, the critical path, budgets and earned value, risk, contracts, monitoring and closing a project, and leading the team. It is a common course in business, management and engineering degrees.
Credit at a fraction of the priceThe same 3 credits can cost $750 or more at a US college. Here it is one payment, self-paced, with lifetime access.
Finish your degree soonerTransfer credits reduce the courses you still owe, so you can graduate earlier or lighten a heavy semester.
Strengthen an applicationA completed college-level course on an official transcript shows admissions and scholarship committees you can do the work.
Study on your own scheduleNo start dates, no deadlines. Watch the lessons, practice, and take the final when you are ready.
130,000+students helped with college creditsACE and NCCRS have over 2,100 cooperating colleges that will consider accepting credits; the final decision is with the universities.

Where the credit goes

Universities that work with NCCRS

Project Management carries a NCCRS credit recommendation. These universities work with NCCRS; some are UPI Study's signed partners. ACE and NCCRS have over 2,100 cooperating colleges that will consider accepting credits; the final decision is with the universities.

Find my college → Not listed? Ask Athena in the corner of this page, or book a 15-minute call.

FAQ

Questions students ask us

About Project Communication Plan Development

What is the difference between push, pull, and interactive communication?
Push communication is sent to chosen recipients without a request, pull communication is posted where people retrieve it when they choose, and interactive communication is a real-time exchange. A weekly status email is push, a project dashboard is pull, and a meeting or call is interactive. Interactive gives the richest feedback but costs the most time, while push does not show whether anyone read it.
How do you calculate the number of communication channels on a project team?
Use the formula n times n minus one, divided by two, where n is the number of people. Five people have 10 channels, eight people have 28, and twelve have 66. Growing a team from six to ten raises the channels from 15 to 45, an increase of 30. The formula counts possible channels, not messages, so it warns of coordination cost rather than measuring it.
What should a project communication matrix include?
A communication matrix has one row per audience, with columns for content, method, frequency, owner, and escalation path. For example, a sponsor might get a pushed one-page weekly summary plus same-day notice of any threat to the opening date. Every row needs exactly one named owner, and every stakeholder in the register should appear in some row or be consciously left out.
What is an escalation trigger in a communication plan?
An escalation trigger is a stated condition, often a time threshold, that forces a problem to move to a higher level of authority. If the rule is to tell the sponsor when the opening date is expected to slip by more than three working days, a seven-day delivery slip is escalated within a working day. A two-day slip stays with the site supervisor and goes in the weekly summary.

About the Project Management course

How many college credits is Project Management?
Project Management (Business 230) carries a NCCRS credit recommendation for 3 semester credits. ACE and NCCRS have over 2,100 cooperating colleges that will consider accepting credits; the final decision is with the universities.
How much does Project Management cost and what is included?
$250, paid once, with lifetime access: all 73 video lessons, a practice quiz after each, the graded work and final exam, and an official transcript when you finish. Students who want several courses choose UPI Study PRO instead.
Which universities accept UPI Study credits?
UPI Study has signed partner agreements with universities such as Thomas Edison State University, University of the People and Charter Oak State College, and works with universities such as Penn State, SNHU and SUNY. ACE and NCCRS have over 2,100 cooperating colleges that will consider accepting credits; the final decision is with the universities. Use "Find my college" on this page to check yours.
How long does Project Management take?
It is self-paced with no deadlines. The 73 lessons total about 15 hours of video; most students add reading and practice time and finish in a few weeks to a few months, on their own schedule.
How are the exams done?
Quizzes and assignments are online in the course. The final exam is taken online with proctoring; a person on the UPI Study team checks assignments, usually within two days.
How do my credits reach my college?
When the course shows 100% complete, request the official transcript from your dashboard. It is sent to the college you name, and you can send it to more than one. Check your college first with "Find my college" on this page, or ask Athena.

Ready for the full course? Earn 3 credits in Project Management.

73 video lessons, a quiz after each one, and the graded work that earns the credit. Recommended for credit by NCCRS.

Project Management
3 credits · NCCRS
Enroll →