S-Curves and Information Systems in Project Tracking

UPI Study › Courses › Project Management › Free lessons › Lesson 5.7 Free with a free account

S-Curves and Information Systems in Project Tracking

Project Management · Chapter 5: Project Management Tools and Analytical TechniquesSection 5.7 · lesson 36 of 7312 min · free with a free account

← Monte Carlo Simulation for Risk Assessment and PlanningNext lesson: Anatomy of a Project Proposal: Key Elements and Goals →

Earn 3 college credits for Project ManagementRecommended for credit by NCCRS · Business 230 · self-paced · one payment, lifetime access

In this lesson

Tracking cumulative cost against the baseline and the data behind it.

  • Build cumulative baseline and actual cost curves and explain why they often form an S shape
  • Calculate deviation as actual minus planned and state whether it is measured against spend to date or the whole budget
  • Explain why a cost curve alone cannot separate a saving from a delay or a data gap
  • Describe how project information systems, dashboards, data quality, and access controls support tracking

Free study notes

Get this lesson's notes by email

The key points and 4 practice questions with answers, in your inbox. One email, free.

One email. Unsubscribe in one click.

Transcript

Everything said in the video, section by section (1,706 words). Read along, or search it.

Opening Question

Eight Units Below the Line

Fernhollow Regional Bus Company is replacing passenger-information screens at its depots and on its buses, over twelve monthly periods. Devika, the project controller, tracks the money on a cumulative cost curve. At the midpoint, the plan says 46 cost units spent by now. Actual spending is 38. Grant, the sponsor, sees a gap of 8 below the line, and calls it a saving. He wants to release part of it to another project. Is a line below the plan really a saving? The curve alone can't say, and this lesson shows why.

Cumulative Figures

Running Totals Against the Cost Baseline

Start with why curves are cumulative. A reporting period is a fixed slice of time, like a month, for which figures are recorded. One period's figures don't show how much has been spent altogether, or how much should have been spent by now. A cumulative figure is the running total, from the start up to and including a stated period. Because spending adds, a cumulative line never falls, except to correct an error. The plan it's compared against is the cost baseline: the approved budget, spread across the periods in which the money is planned to be spent. The same method works for effort in hours.

Why an S

Slow Start, Build-Up, Peak, and Taper

Plotted against time, many cumulative curves look like a stretched letter S: flat at first, steep in the middle, flat again at the end. Four stages explain it. A slow start: people are assigned, contracts agreed, and few activities can begin, because most depend on earlier ones. A build-up: as early activities finish, the waiting ones open up, more people join, and orders are placed. A peak, with the most activities at once, the largest team, and the heaviest purchases. Then a tapering finish: testing, handing over and closing, with fewer people. The link is slope. A cumulative line's slope in any period equals that period's spending, so spending that rises and then falls draws an S. But the S is typical, not guaranteed. A huge first-month purchase gives a steep start, and a constant team gives something close to a straight line. And it isn't the simulation curve from the last lesson. That one plots probability against possible outcomes. This one plots spending against calendar time.

Worked Example

Building a Ten-Period Baseline Curve

Building the baseline curve is repeated addition. The planned total at the end of a period is the previous total, plus that period's planned spend. Take a ten-period project with a budget of 100 cost units. Planned spending runs 2, 4, 8, 14, 18, then 18, 14, 10, 7 and 5. Running totals: 2, 6, 14, 28, 46, then 64, 78, 88, 95, and 100. The last total must equal the approved budget, which catches any addition error. Periods 1 to 3 spend 14 units, periods 4 to 7 spend 64, and the last three spend 22. Slow, steep, slow: an S.

Actual Curve

Plotting Actuals Up to the Status Date

Actual figures are added as they become known. The status date, normally the end of a period, is the last point to which actual data have been collected and checked. Here the status date is the end of period 6. Actual spending was 2, 3, 7, 11, 16 and 17, so the running totals are 2, 5, 12, 23, 39, and 56. Periods 7 to 10 are shown as not yet incurred, never as zero. A zero would claim nothing was spent, in a period that hasn't happened. The actual line is never drawn past the status date. What might be spent later is a forecast, a separate exercise.

Deviation

Size, History, and Direction of a Gap

A deviation is actual minus planned, at the same point in time. A negative difference means the actual line sits below the baseline. At the end of period 6, that's 56 minus 64: minus 8 cost units. Size: 8 is 12.5 percent of the 64 planned so far, but 8 percent of the whole budget. A report should say which it uses. History: the period differences are 0, minus 1, minus 1, minus 3, minus 2, and minus 1. Together they make the minus 8. A cumulative gap only closes if later periods overspend. Direction: in period 6 the gap grew by only 1, against 3 in period 4, so the lines are nearly parallel. That's a reading of shape, not a forecast. Whether a gap needs action depends on the tolerance, the deviation an organization agreed in advance to accept before escalating. There's no universal number.

Quick Check

Cumulative Position After Month Three

Quick check, on a new project. It budgets 5, 10 and 15 units for its first three months, and pays out 4, 9 and 12. Where does it stand after month 3? Pause, and decide. 5 units under budget. It planned 30 in total and spent 25, so actual minus planned is minus 5. 3 under is only month 3's own difference. The cumulative gap adds every month: 1, 1, and 3.

Key Limitation

Saving, Delay, or Missing Data

Here's the most important limit. A cost curve records money against time, not how much work that money bought. A line below the baseline can mean three different things. The work is on plan and cost less, a real saving. Or the work is behind, so planned activities haven't happened, and their costs haven't arrived yet. Or the money was spent but not yet recorded, a data problem. The curve looks the same in all three cases. Picture two projects, both at 56 against a planned 64. On North, all the scheduled work is done, for less. On South, only part is done. North has a saving, and South a delay. Telling them apart needs a measure of work accomplished beside the money. That's earned value, applied in subchapter 9.5, and its value is itself debated.

Information Systems

Time Entry, Cost Records, and Progress Reports

Where do the actual figures come from? A project information system: the tools, records and routines a project uses to collect, store, combine and report its tracking data. Three streams feed it. Time entry: hours worked, recorded against tasks or cost codes, which give labor cost as hours times an agreed rate. Cost records: purchases, invoices and payments in the finance system. And progress reports: what's complete, what remains, and what's blocking it, from the people doing the work. Each has a typical weakness: hours entered late or from memory, invoices lagging the work, and optimistic completeness near deadlines. The data flow in order. They're entered at source, checked, consolidated into running totals, and reported. A mistake at entry travels unchanged through every later stage.

Dashboards

Few Measures and Meaningful Status Lights

A dashboard is a one-screen summary: a few selected measures, with charts and status lights, so a reader sees the position at a glance. Three choices decide whether it works. Pick a few measures, each tied to a decision the reader really makes. Avoid clutter, since every chart takes attention from the others. And make the status lights meaningful. A red, amber or green light is trustworthy only when its thresholds were agreed and written down. And show the status date, so readers know how old the picture is. What goes on it, for whom, and how often comes from the communication plan, not from whatever the tool shows by default. Summary views are debated. Busy readers act on what they can absorb, but one color can hide a serious problem inside a healthy total.

Data Quality

Timely, Accurate, and From One Source

A curve drawn from poor data is a precise picture of the wrong thing. Three qualities matter most. Timeliness, recording close to the event. Accuracy, matching what happened, with the right amounts, codes and units. And a single agreed source, so two reports can't disagree because they used different copies. Late entry distorts the curve, so a gap at the status date may not be real. Should data be entered centrally, by a trained few, or by each person who did the work? Central entry is consistent. Distributed entry is closer to the event. Which works better depends on the setting.

Integration and Security

Shared Codes and Role-Based Access

Integration connects separate sets of project data, so nobody retypes figures from one tool into the next. A shared identifier, like a work package code carried in the schedule, the timesheet and the cost record, ties effort and cost to the same task. Then a gap can be traced to its part of the project. Information security here means controlling who can view, and who can change, project records. Access is set by role: those who view, those who enter, and those who approve. Keep the roles separate, so the person who enters a cost isn't the one who approves it, and keep an audit trail of who changed what, and when. Legal duties about personal and financial data differ by place and sector, so follow the organization's policies, and consult counsel. This is management guidance, not legal advice.

Quick Check

A Late-Entered Invoice

Quick check. A large delivery arrives in period 7, but its invoice isn't entered until period 9. What does the actual cost curve show for periods 7 to 9? Pause, and decide. Too low, then a jump. Periods 7 and 8 understate the real spending, and period 9 catches up all at once. It isn't a true dip, since the money was committed. And nothing pushes the curve above real spending. Any gap read in period 8 would be false.

Back to Fernhollow

Checking Before Calling It a Saving

Back to Devika and Grant. Her curve supports at least three accounts of the gap of 8. Supplier prices came in low, a real saving. Installation is behind, so purchases haven't happened yet. Or invoices arrived but weren't entered, so the actual is understated. A saving can be released. A delay means the money will still be needed. And unrecorded invoices mean the figure shouldn't be used yet. The steering meeting is in six days. She asks the work package leads what share of each installation is done. She asks finance for unentered orders and invoices, and compares contract prices with the baseline. She won't call it a saving until those are in. Grant gets a qualified message, and the release waits one cycle. An avoidable error costs more credibility than a delayed decision.

Key Takeaways

Curves, Deviations, Limits, and Data

To recap. A cumulative curve adds each period's figure to the running total, and often bends into an S. Deviation is actual minus planned, with its base stated. A cost curve alone can't tell a saving from a delay, because it doesn't show work done. And the curve is only as good as its data: timely, accurate, from one agreed source.

About Project Management at UPI Study

Project Management (Business 230) is a self-paced online course of 73 video lessons in 12 chapters, from starting and defining a project to planning, budgets, scheduling tools, proposals, contracts, execution, monitoring, closure, teams and certification. It carries a NCCRS credit recommendation for 3 semester credits.

Every lesson transcript is free on pages like this one, and the videos are free with a free UPI Study account. Enrolling adds a practice quiz after each lesson, the graded work and final exam that earn the credit, lifetime access, and an official transcript on completion. UPI Study has helped over 130,000 students with college credits. ACE and NCCRS have over 2,100 cooperating colleges that will consider accepting credits; the final decision is with the universities.

Why take it here

Why students take Project Management with UPI Study

How projects are planned, run and closedProject Management teaches how to deliver work on time and on budget: scope, schedules, the critical path, budgets and earned value, risk, contracts, monitoring and closing a project, and leading the team. It is a common course in business, management and engineering degrees.
Credit at a fraction of the priceThe same 3 credits can cost $750 or more at a US college. Here it is one payment, self-paced, with lifetime access.
Finish your degree soonerTransfer credits reduce the courses you still owe, so you can graduate earlier or lighten a heavy semester.
Strengthen an applicationA completed college-level course on an official transcript shows admissions and scholarship committees you can do the work.
Study on your own scheduleNo start dates, no deadlines. Watch the lessons, practice, and take the final when you are ready.
130,000+students helped with college creditsACE and NCCRS have over 2,100 cooperating colleges that will consider accepting credits; the final decision is with the universities.

Where the credit goes

Universities that work with NCCRS

Project Management carries a NCCRS credit recommendation. These universities work with NCCRS; some are UPI Study's signed partners. ACE and NCCRS have over 2,100 cooperating colleges that will consider accepting credits; the final decision is with the universities.

Find my college → Not listed? Ask Athena in the corner of this page, or book a 15-minute call.

FAQ

Questions students ask us

About S-Curves and Information Systems in Project Tracking

Why does a project's cumulative cost curve often look like an S?
A cumulative cost curve often forms an S because spending starts slowly, rises to a peak, and then tapers off. Early periods involve assigning people and agreeing contracts, the middle has the most activities and the largest team, and the end has testing and handover with fewer people. The curve's slope in each period equals that period's spending, though a big early purchase can change the shape.
How do you calculate deviation on a cumulative cost curve?
Deviation is actual cumulative cost minus planned cumulative cost at the same point in time. If 56 units have been spent against 64 planned by period 6, the deviation is minus 8. That equals 12.5 percent of the spend planned so far, but 8 percent of a 100-unit budget, so a report should state which base it uses.
Does spending below the cost baseline mean a project is saving money?
Spending below the cost baseline does not by itself mean a saving. The gap could come from work done for less, from work running behind so costs have not arrived yet, or from spending not yet recorded. The curve looks the same in all three cases. Telling them apart needs a measure of work accomplished, along with checks for unentered invoices and orders.
What makes a project dashboard useful?
A useful project dashboard shows a few measures, each tied to a decision its reader actually makes, with status lights based on agreed, written thresholds. It avoids clutter, because every chart takes attention from the others, and it displays the status date so readers know how current it is. What appears on it should come from the communication plan rather than tool defaults.

About the Project Management course

How many college credits is Project Management?
Project Management (Business 230) carries a NCCRS credit recommendation for 3 semester credits. ACE and NCCRS have over 2,100 cooperating colleges that will consider accepting credits; the final decision is with the universities.
How much does Project Management cost and what is included?
$250, paid once, with lifetime access: all 73 video lessons, a practice quiz after each, the graded work and final exam, and an official transcript when you finish. Students who want several courses choose UPI Study PRO instead.
Which universities accept UPI Study credits?
UPI Study has signed partner agreements with universities such as Thomas Edison State University, University of the People and Charter Oak State College, and works with universities such as Penn State, SNHU and SUNY. ACE and NCCRS have over 2,100 cooperating colleges that will consider accepting credits; the final decision is with the universities. Use "Find my college" on this page to check yours.
How long does Project Management take?
It is self-paced with no deadlines. The 73 lessons total about 15 hours of video; most students add reading and practice time and finish in a few weeks to a few months, on their own schedule.
How are the exams done?
Quizzes and assignments are online in the course. The final exam is taken online with proctoring; a person on the UPI Study team checks assignments, usually within two days.
How do my credits reach my college?
When the course shows 100% complete, request the official transcript from your dashboard. It is sent to the college you name, and you can send it to more than one. Check your college first with "Find my college" on this page, or ask Athena.

Ready for the full course? Earn 3 credits in Project Management.

73 video lessons, a quiz after each one, and the graded work that earns the credit. Recommended for credit by NCCRS.

Project Management
3 credits · NCCRS
Enroll →