Total Slack, Free Slack, and the Critical Path
Project Management · Chapter 9: Project Monitoring, Control, and Performance ManagementSection 9.6 · lesson 60 of 7312 min · free with a free account
Free preview
Create a free account to keep watching
It takes a minute and costs nothing. Your free account unlocks all of Chapter 1 and 3 more lessons of Project Management.
Lesson complete
Earn the 3 college credits for Project Management
Enrolling adds a quiz after each lesson, the graded work and the official transcript. Recommended for credit by NCCRS.
Next lesson: Adapting to and Controlling Schedule Changes →← Earned Value Management: Framework and ApplicationNext lesson: Adapting to and Controlling Schedule Changes →
In this lesson
Use total, free and project float to judge which delays matter.
- Calculate total float and free float from early and late dates
- Identify the critical path and near-critical paths by comparing path lengths
- Explain project float and what negative float means for a commitment
- Explain why float is shared along a path and how the critical path can shift
Free study notes
Get this lesson's notes by email
The key points and 4 practice questions with answers, in your inbox. One email, free.
One email. Unsubscribe in one click.
Transcript
Everything said in the video, section by section (1,656 words). Read along, or search it.
Opening Question
Will a Two-Day Overrun Move Handover
Back on the Riverside clinic build. On the Tuesday call, Sam reports that setting the wall frames will take 4 working days, not the planned 2. The figures are made up. Helen, the sponsor, has been told the building is handed over on day 18. She asks one question: does this move the handover? Priya won't answer from the overrun. She'll answer from the float.
Key Terms
Early Dates, Late Dates and Float
From the forward and backward passes, every activity has four dates. Early start and early finish: the earliest it can begin and end. Late start and late finish: the latest, without pushing back the finish. The project starts at day 0. Early finish is early start plus duration, and late start is late finish minus duration. Every link here is finish-to-start. Float, also called slack, is how long an activity or a path can slip before a stated consequence. Total float protects the finish. Free float protects the next activities. Project float compares the forecast with the required finish.
Example Network
The Riverside Site Network
Here's the site network, with its dates already worked out. Foundations, A, take 6 days, then three branches start on day 6. Wall frames, B, 2 days, then drywall, C, 2 days. Roof steel, D, 7 days. Drainage, E, 3 days, then the parking lot surface, F, 3 days. All three branches must finish before inspection and handover, G, 5 days, which ends on day 18.
Total Float
Late Start Minus Early Start
Total float is how long an activity can slip, or overrun, without delaying the project finish. It's late start minus early start, or, the same thing, late finish minus early finish. Drywall, C: 11 - 8 = 3, and 13 - 10 = 3. The others: A, 0. B, 3. D, 0. E, 1. F, 1. And G, 0. An activity with zero total float is critical: any delay delays the finish. And total float isn't the activity's own. It belongs to the chain through it.
Free Float
Protecting the Next Activity's Start
Free float is how long an activity can slip, without delaying the early start of anything that follows. It's the earliest early start among its successors, minus its own early finish. Wall frames, B, finish early on day 8, and drywall starts early on day 8. So B's free float is 8 - 8 = 0, though its total float is 3. C: 13 - 10 = 3. F: 13 - 12 = 1. E: 9 - 9 = 0. A, D and G: 0. For the last activity, compare with the project finish. Free float can never exceed total float. And it says who must be told: within free float, the owning team absorbs it. Beyond it, other teams' starts move. Beyond total float, the finish moves: that's for the sponsor.
Critical Path
Checking Every Complete Path Length
The critical activities, A, D and G, join end to end: the critical path, 6 + 7 + 5 = 18 days, the forecast finish. Check it with every complete path. A, E, F, G is 6 + 3 + 3 + 5 = 17. A, B, C, G is 6 + 2 + 2 + 5 = 15. Each path's gap to 18 is its activities' total float: 1 for E and F, and 3 for B and C.
Quick Check
Total and Free Float for Cabling
Quick check, from a ticket-office fit-out. Running the cabling, R, has early dates 4 and 6, and late dates 8 and 10. Its only successor starts early on day 8. What are R's total float and free float? Pause and predict. Total float 4, free float 2. Total float is 8 - 4 = 4. Free float is the successor's early start, 8, minus R's early finish, 6: two. So R can slip 4 days without moving the finish, but past 2 days it moves the next crew's start. Assuming free float equals total float is the trap.
Project Float
Required Finish Versus Forecast Finish
Now the outside world. A required finish is fixed from outside the schedule, by a contract, a sponsor, or an event. The forecast finish is what the schedule says is achievable. Project float is required finish minus forecast finish. Positive is margin; zero is none; and when the required date is earlier, it's negative float. A required date shifts every total float by the project float. Required day 21: project float +3, so critical activities carry 3, E and F 4, B and C 6. Required day 16: 16 - 18 = -2. The critical activities carry -2, E and F -1, and B and C still +1. Negative float isn't lateness already incurred. It means that even if everything goes to plan, the project lands two days after the commitment. It marks the paths that are too long. Positive float is a margin someone should own. Zero means any slip misses the date. Negative means plan and commitment disagree: compress the work, or change the commitment through the change process.
Near-Critical Paths
Watching Paths With Thin Float
A near-critical path has float small enough that a plausible overrun would make it the longest. Organizations set the threshold, in days or as a share of duration. With a threshold of 2 days, A, E, F, G, at 1 day of float, is near-critical. A, B, C, G, at 3, isn't yet. The critical path demands action on any slip. A near-critical path demands its float be watched, with a response agreed in advance. And merge points add risk. G waits for C, D and F, so several low-float paths give several chances of delay. Count near-critical paths, not just the critical one.
Path Shifts
How a Drainage Overrun Moves the Path
The critical path moves as durations change. Suppose drainage, E, takes longer, with everything else unchanged. As planned, 3 days: the paths are 18, 17 and 15, and A, D, G is critical. At 4 days, an overrun equal to its float: A, E, F, G becomes 6 + 4 + 3 + 5 = 18. The finish stays at 18, but now there are two critical paths. At 6 days: A, E, F, G is 20. The finish moves to day 20, and A, E, F, G is critical. The old critical path now has 2 days of float. The finish moved 2 days: the overrun of 3, minus the 1 day of float. The middle case is the one most likely to go unnoticed: the finish hasn't moved, but the margin is gone.
Scheduling Software
Baselines, Tracking and What-If Analysis
Scheduling software recalculates dates and floats after each update. Four kinds of feature support control. A baseline: a saved copy of the approved dates, the reference for asking whether the critical path has shifted. Progress tracking: actual dates and remaining durations at a status date. What-if analysis: testing a change, like E overrunning by 3 days, on a copy, before anything is committed. And variance views: comparing the current schedule with the baseline, often filtered by float. These features compute; they don't judge. Float is only right if the logic is complete and progress is current, and tools define critical differently, so check the definition in use.
Key Limitation
Float Belongs to the Path
Float ranks where to look: zero or negative float first, then near-critical paths with their float reported at each update, and comfortable float less often. But the biggest limit: float belongs to a path, not an activity. B and C each show 3 days. That's not 6 days in all. It's the same 3 days, shared. If B takes 1 day longer, C starts on day 9, and both show 2. If B takes 3 days longer, both show 0, and the drywall team has no float left, through no action of its own. If B takes 4 days longer, the path is 19 days, and the finish moves to day 19. Float is also a snapshot, only as good as the network, since a missing link creates float that doesn't exist. And it knows nothing of crews, cost or safety.
Quick Check
A Longer Parking Lot Surface
Quick check, on the same network. Drainage, E, finishes on time. But the parking lot surface, F, is now forecast to take 5 days, not 3. When is the project finish: still day 18, day 19, or day 20? Pause and predict. Day 19. A, E, F, G becomes 6 + 3 + 5 + 5 = 19, now the longest path. The 2-day overrun used up the path's 1 day of float, and the other day moved the finish. Day 20 would ignore the float. And day 18 forgets that E and F's float is one shared day, not one day each.
Debate
How Far Float Should Rank Attention
How far should float rank attention? One view: attention is the scarcest resource, only critical-path delays move the finish, so concentrate on zero-float work. The other: estimates are uncertain and paths converge, so watch every path whose float is small compared with its uncertainty. How often non-critical paths overrun is an empirical question, answered only by an organization's own records. How much attention to trade is about values. No side is taken here.
Case Resolved
Handover Holds but Drywall Moves
Back to Sam's wall frames: 4 days instead of 2. Priya reads the float, not the overrun. B's total float is 3 and the overrun is 2, so the finish holds. A, B, C, G becomes 6 + 4 + 2 + 5 = 17, against 18. But B's free float was 0, so drywall's early start moves from day 8 to day 10, and that booked crew must move today. B and C now share 1 day of float, and two paths sit at 1. Had the same overrun hit the roof steel, the finish would be day 20, and she'd escalate at once. So she tells Helen day 18 holds, rebooks the drywall crew, and adds the wall-frame path to the near-critical watch list. The cost: two thin paths to report at every update.
Key Takeaways
Float Types and Path Behavior in Brief
To recap. Total float is late start minus early start, and protects the finish. Free float is the successors' earliest start minus the early finish, and protects the next team. Project float is required minus forecast finish. Negative float means plan and commitment disagree. Float is shared along a path, and the critical path can shift before the finish does.
About Project Management at UPI Study
Project Management (Business 230) is a self-paced online course of 73 video lessons in 12 chapters, from starting and defining a project to planning, budgets, scheduling tools, proposals, contracts, execution, monitoring, closure, teams and certification. It carries a NCCRS credit recommendation for 3 semester credits.
Every lesson transcript is free on pages like this one, and the videos are free with a free UPI Study account. Enrolling adds a practice quiz after each lesson, the graded work and final exam that earn the credit, lifetime access, and an official transcript on completion. UPI Study has helped over 130,000 students with college credits. ACE and NCCRS have over 2,100 cooperating colleges that will consider accepting credits; the final decision is with the universities.
Enroll now → Course details Download the syllabus All Business courses Every course with PRO →
Why take it here
Why students take Project Management with UPI Study
Where the credit goes
Universities that work with NCCRS
Project Management carries a NCCRS credit recommendation. These universities work with NCCRS; some are UPI Study's signed partners. ACE and NCCRS have over 2,100 cooperating colleges that will consider accepting credits; the final decision is with the universities.
Thomas Edison State UniversitySigned partner
University of the PeopleSigned partner
Charter Oak State CollegeSigned partner
Strayer UniversitySigned partner
Columbia Southern UniversitySigned partner
Indiana TechSigned partner
Penn StateWorks with NCCRS
Southern New Hampshire UniversityWorks with NCCRS
SUNYWorks with NCCRS
+many more cooperating universitiesFind my college →Find my college → Not listed? Ask Athena in the corner of this page, or book a 15-minute call.
FAQ
Questions students ask us
About Total Slack, Free Slack, and the Critical Path
What is the difference between total float and free float?
What is a near-critical path and why should it be monitored?
What does negative float mean on a project schedule?
Why is float shared along a path instead of belonging to one activity?
About the Project Management course
How many college credits is Project Management?
How much does Project Management cost and what is included?
Which universities accept UPI Study credits?
How long does Project Management take?
How are the exams done?
How do my credits reach my college?
Ready for the full course? Earn 3 credits in Project Management.
73 video lessons, a quiz after each one, and the graded work that earns the credit. Recommended for credit by NCCRS.
3 credits · NCCRSEnroll →