Business Portfolio and Project Portfolio Management, Explained

UPI Study › Courses › Project Management › Free lessons › Lesson 1.7 Free with a free account

Business Portfolio and Project Portfolio Management

Project Management · Chapter 1: Foundations and Framework of Project ManagementSection 1.7 · lesson 7 of 7312 min · free with a free account

← Project Planning Processes and Supporting ToolsNext lesson: Global Project Management: Success Strategies →

Earn 3 college credits for Project ManagementRecommended for credit by NCCRS · Business 230 · self-paced · one payment, lifetime access

In this lesson

How organizations choose, balance and review projects as one portfolio.

  • Distinguish projects, programs and portfolios and the two meanings of portfolio
  • Calculate weighted scores to rank candidate projects
  • Explain why portfolios need balancing and the limits of scoring models
  • Apply forward net value instead of sunk cost to continue or stop decisions

Free study notes

Get this lesson's notes by email

The key points and 4 practice questions with answers, in your inbox. One email, free.

One email. Unsubscribe in one click.

Transcript

Everything said in the video, section by section (1,574 words). Read along, or search it.

Opening Question

Seven Proposals, Money for Three

A continuing-education college has seven project proposals on the table, and money for three. Expand the evening catalog. Court employers. Retrain instructors. Refresh a computer lab. And three more. Each makes sense alone, but they all need the same finance staff, the same instructors, and the same IT team. Pick them one at a time, or for whoever argues best, and two things happen. Too much starts at once, so everything slows. And attractive work gets funded that does little for what the college is trying to achieve. So how should it choose?

Hierarchy

Projects, Programs and Portfolios

Portfolio management is the set of decisions and routines an organization uses to choose, balance and review its work, so limited money and people go where they matter most. It sits on a three-level hierarchy. A project delivers one defined result by a defined end, like a rebuilt enrollment website. A program groups related projects whose combined benefit is greater together. A program to grow evening enrollment might combine a catalog project, advertising, and instructor recruitment. A portfolio is the whole collection of programs, projects, and sometimes operations, managed as one set against strategy. A stand-alone project needn't belong to any program. Each level asks its own question. Project: are we delivering this result? Program: are these projects producing the benefit together? Portfolio: are we doing the right work? So a project can finish on time and still be the wrong project. Only portfolio governance can catch that.

Key Terms

Business Portfolio Versus Project Portfolio

The word portfolio has two senses. The business portfolio is the set of lines of business, products and services an organization runs. For the college: daytime certificates, evening courses, employer training, and renting out its rooms. Which lines to grow or wind down is for senior executives and the board. The project portfolio is the set of projects and programs chosen to change, protect or extend the business portfolio. A portfolio committee governs it. So the business portfolio comes first and sets direction. A project that traces to no business portfolio decision has no reason to be funded.

Governance

Who Decides What Enters

Portfolio governance decides what enters the portfolio, who approves it, and how it's reviewed. Three elements recur. An executive group: a standing committee from finance, operations and the main business lines, with a named chair. Selection criteria, written down before any proposal is read, so they can't be shaped to fit a favorite. And an approval authority, with stated limits, so larger commitments go up to the board. The project management office supports this. It formats proposals, checks the figures, keeps the master list and prepares review packs. But the executive group decides.

Selection Inputs

Fit, Benefit, Risk and Demand

To compare candidates, a committee needs the same few facts about each one, starting with strategic fit. Fit is how directly a project advances a stated objective. Expected benefit is the gain from the finished result, in money where possible. Risk: the chance something uncertain harms the project or its benefit. And cost and resource demand: the money, plus the scarce people-time it will absorb. At this stage the inputs are deliberately rough. The aim is to compare many candidates quickly, not to certify any one. The full business case comes later.

Method

Building a Weighted Scoring Model

A weighted scoring model rates every candidate on the same criteria, and combines the ratings into one number. Choose the criteria, and weight each one so the weights sum to a hundred percent. Here: fit thirty-five, benefit thirty, risk twenty, cost and demand fifteen. Fix the scale so higher is always better. So a low-risk project scores five on risk, and a low-demand project scores five on demand. Score each candidate. These five belong to a freight company, and every number is illustrative. The weighted total is the sum, across the criteria, of each weight times the candidate's score.

Worked Example

Scoring Candidate C at 3.7

Work out candidate C. Point three five times four is one point four. Point three times three is point nine. Point two times four is point eight. Point one five times four is point six. Together: three point seven. Candidate A has the strongest fit of all, five. But it's risky and demanding, so it totals only three point three five. The others: D three point five, B three point four five, E three point two. The ranking is C, D, B, A, E. C has no outstanding score, and no weak one either.

Quick Check

Weighted Total for Candidate F

Quick check. A sixth candidate, F, scores five on fit, two on benefit, three on risk, and four on cost and demand. Using the same weights, what's its weighted total? Pause, and work it out. Three point five five. One point seven five, plus point six, plus point six, plus point six. That puts F second, just behind C. A big fit score helps, but a weak benefit drags it back.

Balancing

Judging the Portfolio as a Set

Ranking projects one by one doesn't make a good portfolio, because a portfolio is judged as a set. Balancing adjusts the set, even if that means leaving the pure ranking. A capacity check: if the top three all need the same two analysts, the set overloads them. A risk-spread check: all high-risk projects can fail together, while all safe ones may change nothing. A coverage check: five strong projects serving one objective leave the others untouched. And a horizon check. Quick wins build confidence, but long-horizon work builds capability, and starves if every review favors the quick return.

Limitations

When Weights Change the Ranking

A weighted score looks exact, and that's its main hazard. First, the weights and scores are judgments. Move ten points of weight from fit to cost and demand: twenty-five, thirty, twenty, twenty-five. No project changes. Yet D now ties C at three point seven, and E jumps from fifth to third. Small gaps mostly record the weights chosen. Second, a ranked list ignores dependencies, where one project can't deliver unless another is done. Third, the model can be gamed: inflated benefits, understated risks, a big project split up to dodge scrutiny. Whether to lean on scoring is contested. It makes criteria explicit, and blunts the most persuasive sponsor. But it can dress opinion as precision. A common compromise: the ranking starts the discussion, it doesn't end it.

Portfolio Review

Continue, Pause, Change or Stop

A portfolio isn't chosen once. A portfolio review re-examines every active and proposed project against current strategy, resources, and results so far. Many organizations review active work quarterly and funding yearly, plus extra reviews after a budget cut or a strategy change. Projects rarely announce when they've stopped making sense. Rebalancing moves money, people and priority as a result. Each project can continue, pause, change, or stop. Pause it when its people are urgently needed elsewhere, or a project it depends on has slipped. Change it when adjusting scope, timing or funding restores its value. Stop it when its reason has gone: a strategy shift, a vanished benefit, costs that outgrew the benefit, a risk that struck, or a higher-ranked rival for scarce people.

Sunk Cost

Deciding on Forward Net Value

Stopping is the hardest decision, partly because of sunk cost: money, time or effort already spent, that can't be recovered either way. Sunk cost is no reason to continue. It's the same whether you continue or stop, so it can't tell the options apart. Only the future can. The forward net value of continuing is the benefit still to come, minus the cost still to spend. Compare it with the best other use of the same money and people. A project has spent sixty thousand dollars. Finishing needs fifty thousand more, and its shrunken market now makes the benefit worth forty thousand. Forty minus fifty is minus ten thousand. The sixty already spent appears nowhere. An alternative needs the same fifty thousand, and returns seventy thousand: plus twenty. So stop the first, and redirect the money. Two cautions. Costs caused by stopping, like contract exit fees, are future costs, and belong in the sum. And where contracts are significant, ask counsel.

Quick Check

Continue Despite Past Spending

Quick check. A project has already spent two hundred thousand dollars. Thirty thousand more will finish it, and deliver fifty thousand of benefit. The best other use of that thirty thousand would return thirty-five thousand. Continue, or stop? Pause, and decide. Continue. Finishing is worth fifty minus thirty, plus twenty thousand. The alternative is worth only plus five. The two hundred thousand already spent doesn't enter it. Here the forward view says keep going, and that's fine too.

Case Resolution

Treating Dependent Projects as a Program

Back to the college. Its committee, chaired by the vice-principal Priya, agreed on its criteria before reading a single proposal. Strategic fit thirty-five percent, benefit twenty-five, risk twenty, cost and demand twenty, on a scale where higher is always better. The ranking put employer outreach first, the catalog expansion second, instructor training third, and a student-records cleanup sixth. Then the IT lead pointed to the PMO's dependency map. The new catalog couldn't publish accurate schedules until the student records were cleaned. So the committee treated the two as one program. It funded the cleanup, the catalog and the outreach, and deferred instructor training to the next review. It capped the cleanup budget, held the catalog work until the cleanup hit a milestone, and recorded in the minutes why it departed from its own list.

Key Takeaways

Scoring, Balancing and Forward Value

To recap. A portfolio holds programs and projects, and asks whether the organization is doing the right work. Weighted scoring makes the criteria explicit: the sum of each weight times each score. But the ranking is a judgment that ignores dependencies, so balance the set and start the discussion there. And review on forward value. Money already spent is never a reason to continue.

About Project Management at UPI Study

Project Management (Business 230) is a self-paced online course of 73 video lessons in 12 chapters, from starting and defining a project to planning, budgets, scheduling tools, proposals, contracts, execution, monitoring, closure, teams and certification. It carries a NCCRS credit recommendation for 3 semester credits.

Every lesson transcript is free on pages like this one, and the videos are free with a free UPI Study account. Enrolling adds a practice quiz after each lesson, the graded work and final exam that earn the credit, lifetime access, and an official transcript on completion. UPI Study has helped over 130,000 students with college credits. ACE and NCCRS have over 2,100 cooperating colleges that will consider accepting credits; the final decision is with the universities.

Why take it here

Why students take Project Management with UPI Study

How projects are planned, run and closedProject Management teaches how to deliver work on time and on budget: scope, schedules, the critical path, budgets and earned value, risk, contracts, monitoring and closing a project, and leading the team. It is a common course in business, management and engineering degrees.
Credit at a fraction of the priceThe same 3 credits can cost $750 or more at a US college. Here it is one payment, self-paced, with lifetime access.
Finish your degree soonerTransfer credits reduce the courses you still owe, so you can graduate earlier or lighten a heavy semester.
Strengthen an applicationA completed college-level course on an official transcript shows admissions and scholarship committees you can do the work.
Study on your own scheduleNo start dates, no deadlines. Watch the lessons, practice, and take the final when you are ready.
130,000+students helped with college creditsACE and NCCRS have over 2,100 cooperating colleges that will consider accepting credits; the final decision is with the universities.

Where the credit goes

Universities that work with NCCRS

Project Management carries a NCCRS credit recommendation. These universities work with NCCRS; some are UPI Study's signed partners. ACE and NCCRS have over 2,100 cooperating colleges that will consider accepting credits; the final decision is with the universities.

Find my college → Not listed? Ask Athena in the corner of this page, or book a 15-minute call.

FAQ

Questions students ask us

About Business Portfolio and Project Portfolio Management

What is project portfolio management?
Project portfolio management is the set of decisions and routines an organization uses to choose, balance and review its programs and projects, so limited money and people go where they matter most. It asks whether the organization is doing the right work. A project can finish on time and still be the wrong project, and portfolio governance is the level designed to catch that.
How do you calculate a weighted score for project selection?
Multiply each criterion's weight by the candidate's score and add the results, with weights summing to 100 percent and higher scores always better. With weights of 35, 30, 20 and 15 percent and scores of 4, 3, 4 and 4, the total is 1.4 plus 0.9 plus 0.8 plus 0.6, or 3.7.
Why is sunk cost not a reason to continue a project?
Sunk cost is money already spent that cannot be recovered whether the project continues or stops, so it cannot tell the options apart. Compare forward net value instead: benefit still to come minus cost still to spend. If finishing costs $50,000 and yields $40,000, continuing is worth minus $10,000, whatever was already spent. Future costs of stopping, such as exit fees, still belong in the sum.
What are the limitations of a weighted scoring model for portfolios?
Weights and scores are judgments, so small gaps between totals often reflect the weights chosen rather than real differences. Shifting ten points of weight can reorder the ranking. A ranked list also ignores dependencies between projects, and sponsors can game it by inflating benefits or splitting projects. A common compromise uses the ranking to start the discussion, not end it.

About the Project Management course

How many college credits is Project Management?
Project Management (Business 230) carries a NCCRS credit recommendation for 3 semester credits. ACE and NCCRS have over 2,100 cooperating colleges that will consider accepting credits; the final decision is with the universities.
How much does Project Management cost and what is included?
$250, paid once, with lifetime access: all 73 video lessons, a practice quiz after each, the graded work and final exam, and an official transcript when you finish. Students who want several courses choose UPI Study PRO instead.
Which universities accept UPI Study credits?
UPI Study has signed partner agreements with universities such as Thomas Edison State University, University of the People and Charter Oak State College, and works with universities such as Penn State, SNHU and SUNY. ACE and NCCRS have over 2,100 cooperating colleges that will consider accepting credits; the final decision is with the universities. Use "Find my college" on this page to check yours.
How long does Project Management take?
It is self-paced with no deadlines. The 73 lessons total about 15 hours of video; most students add reading and practice time and finish in a few weeks to a few months, on their own schedule.
How are the exams done?
Quizzes and assignments are online in the course. The final exam is taken online with proctoring; a person on the UPI Study team checks assignments, usually within two days.
How do my credits reach my college?
When the course shows 100% complete, request the official transcript from your dashboard. It is sent to the college you name, and you can send it to more than one. Check your college first with "Find my college" on this page, or ask Athena.

Ready for the full course? Earn 3 credits in Project Management.

73 video lessons, a quiz after each one, and the graded work that earns the credit. Recommended for credit by NCCRS.

Project Management
3 credits · NCCRS
Enroll →