Structure and Functions of a Project Management Office

UPI Study › Courses › Project Management › Free lessons › Lesson 1.3 Free with a free account

Structure and Functions of a Project Management Office

Project Management · Chapter 1: Foundations and Framework of Project ManagementSection 1.3 · lesson 3 of 7314 min · free with a free account

← Core Skills and Competencies for Effective Project ManagersNext lesson: Business Value and Strategic Benefits of Project Management →

Earn 3 college credits for Project ManagementRecommended for credit by NCCRS · Business 230 · self-paced · one payment, lifetime access

In this lesson

How organizational structure and the PMO shape project authority.

  • Compare functional, matrix and projectized structures by project manager authority
  • Distinguish weak, balanced and strong matrix organizations
  • Describe supportive, controlling and directive PMOs and the functions a PMO performs
  • Evaluate a PMO using value measures and its common failure modes

Free study notes

Get this lesson's notes by email

The key points and 4 practice questions with answers, in your inbox. One email, free.

One email. Unsubscribe in one click.

Transcript

Everything said in the video, section by section (1,806 words). Read along, or search it.

Opening Question

Two Bosses, One Thursday Deadline

On Tuesday, Imani, a systems analyst, is asked to finish a data conversion by Thursday. The same afternoon, her own department head asks her to fix a payroll fault, also by Thursday. Both requests are legitimate, and she can't meet both. Whose priority wins? That isn't a question about personalities. It's a question of structure: who controls the people, the money, and the decisions.

Key Terms

Structures and Reporting Lines

An organizational structure is the pattern of departments, reporting lines and decision rights, through which an organization divides and coordinates its work. A reporting line is the chain from an employee up through successive managers. It decides whose instructions they follow, and who evaluates them. Projects are awkward for most structures, because a project is temporary, and cuts across permanent departments. So whether a project manager can simply assign a developer, or must negotiate for the developer's time, is a structural fact, not a personal one. Three common structures, functional, matrix and projectized, each answer it differently.

Functional Structure

Departments Own the Work

A functional structure groups people into departments by the kind of work they do, such as design, production or purchasing. Each department head controls its staff, budget and priorities, and every employee has one reporting line, up through the department. A project runs inside the departments. Design might own a new product line, and borrow hours from production and purchasing. The project manager is often a coordinator: someone who tracks tasks and reminds departments, but can't direct work, approve spending or release staff. Team members' first loyalty goes to the manager who controls their careers. So project tasks compete with routine work, and often lose. The strengths are deep expertise and clear careers. The weakness is that nobody below the executives owns the whole result.

Matrix Structure

Weak, Balanced and Strong Matrices

A matrix structure keeps people in their departments, but also assigns them to projects. Departments run down the page, and projects run across it. That grid gives the structure its name. So each team member answers to two managers: the functional manager, who owns their discipline, and the project manager, who owns the project work. Matrices come in three variants, depending on where authority sits. In a weak matrix, functional managers keep most of it, and the project manager is close to a coordinator, often part-time. In a balanced matrix, authority is shared. The project manager runs the plan, but the functional manager still controls who is assigned. In a strong matrix, a full-time project manager holds most of the authority and much of the budget. Departments stay the home of expertise.

Common Problem

The Dual Reporting Clash

Every variant carries the dual reporting problem, and that's exactly Imani's Thursday. A matrix works when the two managers settle the clash themselves, through an agreed priority rule, or an escalation path to a shared senior manager. It works badly when the clash is left to the team member, who has the least authority of anyone involved.

Projectized Structure

Organizing Around Projects Full-Time

A projectized structure builds the organization around its projects. Team members work on one project full-time, and report to its project manager, who controls the budget and the staffing. A construction firm with its own site team for each building often works this way. Here the project manager has the most authority of the three. Decisions are quick, loyalty runs to the project, and communication lines are short. The cost is idle resources: people who are paid but unassigned, when one project ends before the next begins. And duplication: self-contained teams solve the same problem from scratch, and people may not know where they belong when a project ends.

Comparison

Authority, Budget and Reporting Side by Side

Put the three side by side, and a pattern appears. Project manager authority: little in functional, from low to high across the matrix variants, and high in projectized. Budget control: the functional manager or the sponsor, then split, then the project manager. Reporting lines: one, then two, then one again. No structure is simply best. Authority gained on the right is paid for in idle staff, and depth on the left is paid for in authority. Most real organizations are hybrids, so judge where control sits for a particular project, not for the whole company.

Quick Check

Identifying a Telecom Firm Structure

Quick check. At a telecom firm, each project leader works on projects all week, and signs off most project spending. The engineers on loan are still reviewed by engineering. Which structure is this? Pause, and decide. Strong matrix. The engineers keep two reporting lines, so it's a matrix. And a full-time manager holding most of the budget makes it strong. It isn't projectized, because the engineers don't move to the project, or report only to its manager.

Definition

What a PMO Does for Governance

Structures leave a coordination gap, and organizations often fill it with a project management office, or PMO. A PMO is a management unit that standardizes the governance of projects, and shares resources, methods, tools and techniques across them. Governance means the rules, roles and review points by which an organization decides which work proceeds, who may approve changes, and how progress is checked. Without it, each project manager may invent a plan format and a status report, and executives can't compare one project with another. A PMO is a small, permanent group whose job is project practice itself. It isn't a project, because it isn't temporary.

PMO Types

Supportive, Controlling and Directive PMOs

PMOs differ by how much control they hold, and three types sit along one scale. A supportive PMO consults. It offers templates, advice and lessons from earlier projects, and managers may use them or not. A controlling PMO requires compliance. It sets standards, like a required plan format or mandatory status reports, and checks them. Managers still run their projects. A directive PMO manages the projects. The project managers belong to it, and it assigns them, directs their work, and answers for results. Each step to the right asks project managers to give up more independence. It isn't a ladder every PMO must climb. A few experienced managers may need only support. A history of failed projects may call for control from day one.

Worked Example

Seven PMO Functions at a County Agency

Whatever its type, a PMO performs some mix of seven functions. Picture a county services agency. Standards: no project spends money until a sponsor signs a one-page purpose statement. Methodology: a published four-stage approach. Templates: a library with a plan outline, a risk log and a status form. Training: a quarterly workshop for new project managers. Governance: running the review points where leaders decide whether a project continues. Reporting: one monthly dashboard of every active project. And resource pooling: three business analysts sit in the PMO, and are lent to projects for set periods. A supportive PMO offers all this as optional help. A controlling PMO requires it. A directive PMO does it, as part of running the projects.

Fit

PMO Authority Is Borrowed

A PMO's authority is borrowed from the structure around it. It can only require what existing managers will give up. In a functional or weak matrix organization, a supportive PMO fits easily, but reaches only those who choose it. A controlling one must persuade the department heads. In a balanced matrix, a controlling PMO often has room, because project managers already hold part of the authority. In a strong matrix or projectized firm, managers may resist a controlling PMO as a duplicate layer. A directive PMO that employs them formalizes what exists. And a directive PMO over a functional organization, without a strong executive sponsor, stalls at the first dispute. How much control belongs in the center is contested. Central control lets leaders compare projects, and spot overloaded people. Distributed control keeps decisions with the people closest to the work. The answer depends on the work, and on how much autonomy an organization will trade.

Value Measures

Judging Whether a PMO Is Worth It

A PMO costs salaries and effort, so how do you judge whether it's worth having? With value measures: quantities an organization chooses to track, to judge whether a unit delivers what it was created for. Each uses one formula: the items that met the condition, divided by the items that could have, times one hundred. In one quarter, 28 of 40 active projects use the standard template. That's 70 percent. 45 of 60 required status reports arrived on time: 75 percent. And 9 of 12 closed projects met all their success criteria: also 75 percent. Read them with care. Template use says nothing about how well templates were filled in. And with only twelve projects, one miss moves the rate by more than eight points. Track several measures over time, and never treat one number as a verdict.

Failure Modes

Four Ways PMOs Fail

PMOs fail in four recognizable ways. Bureaucracy without value: forms, approvals and meetings that cost more than they return. Nobody can name a decision a report changed. No executive sponsor: no senior leader backs the PMO or settles disputes, so a controlling PMO shrinks to a supportive one. Standards nobody uses: templates designed without managers' input, harder than their own, or never enforced. A low template-use rate is the signal. Unclear authority: nobody knows what the PMO may require or refuse, so each dispute goes to whoever pushes hardest.

Quick Check

A PMO Without Backing

Quick check. A new controlling PMO, in a functional company, asks every team for a weekly status report. Department heads tell their staff to ignore it. When the PMO escalates, the chief executive says, work it out yourselves. Which failure mode is this? Pause, and decide. No executive sponsor. The requirement has no senior leader behind it, so department heads can ignore it at no cost. Bureaucracy is tempting, but nothing says the reports cost more than they return. The PMO simply has no backing.

Case Study

A Narrow Controlling PMO for Hospitals

Here's how one director chose. Dana runs operations for a network of four hospitals and a dozen clinics. In one year, four overlapping projects shared the same technicians and electricians, and three missed their dates. Each department head put routine work first, and nobody saw the overlap until a deadline passed. The network is a weak matrix. A supportive PMO would be easy to set up, but it wouldn't make anyone share staff calendars, the real cause. A directive PMO would fix the cause, but department heads would never hand over their staff and budgets. So Dana chose a controlling PMO with a narrow scope: one shared staffing register, one monthly report, and optional templates. She made the chief executive its sponsor, because a requirement that heads could ignore would fail the first time it was inconvenient. The trade-off: the PMO exposes conflicts, but doesn't resolve them. Limited authority the organization will grant beats broad authority it would refuse.

Key Takeaways

Structure Sets Authority

To recap. Structure sets a project manager's authority: little in functional, shared in a matrix, and high in projectized. A matrix gives people two managers, so the managers must settle clashes, not the team member. A PMO fills the coordination gap. Supportive, controlling and directive PMOs differ in how much control they hold. Its authority is borrowed from the structure and its sponsor. Judge it with several measures, and watch for the four failure modes.

About Project Management at UPI Study

Project Management (Business 230) is a self-paced online course of 73 video lessons in 12 chapters, from starting and defining a project to planning, budgets, scheduling tools, proposals, contracts, execution, monitoring, closure, teams and certification. It carries a NCCRS credit recommendation for 3 semester credits.

Every lesson transcript is free on pages like this one, and the videos are free with a free UPI Study account. Enrolling adds a practice quiz after each lesson, the graded work and final exam that earn the credit, lifetime access, and an official transcript on completion. UPI Study has helped over 130,000 students with college credits. ACE and NCCRS have over 2,100 cooperating colleges that will consider accepting credits; the final decision is with the universities.

Why take it here

Why students take Project Management with UPI Study

How projects are planned, run and closedProject Management teaches how to deliver work on time and on budget: scope, schedules, the critical path, budgets and earned value, risk, contracts, monitoring and closing a project, and leading the team. It is a common course in business, management and engineering degrees.
Credit at a fraction of the priceThe same 3 credits can cost $750 or more at a US college. Here it is one payment, self-paced, with lifetime access.
Finish your degree soonerTransfer credits reduce the courses you still owe, so you can graduate earlier or lighten a heavy semester.
Strengthen an applicationA completed college-level course on an official transcript shows admissions and scholarship committees you can do the work.
Study on your own scheduleNo start dates, no deadlines. Watch the lessons, practice, and take the final when you are ready.
130,000+students helped with college creditsACE and NCCRS have over 2,100 cooperating colleges that will consider accepting credits; the final decision is with the universities.

Where the credit goes

Universities that work with NCCRS

Project Management carries a NCCRS credit recommendation. These universities work with NCCRS; some are UPI Study's signed partners. ACE and NCCRS have over 2,100 cooperating colleges that will consider accepting credits; the final decision is with the universities.

Find my college → Not listed? Ask Athena in the corner of this page, or book a 15-minute call.

FAQ

Questions students ask us

About Structure and Functions of a Project Management Office

What is the difference between a weak, balanced and strong matrix?
The difference is where authority sits between functional and project managers. In a weak matrix, functional managers keep most authority and the project manager acts close to a coordinator. In a balanced matrix, authority is shared, though the functional manager still controls assignments. In a strong matrix, a full-time project manager holds most of the authority and much of the budget.
What are the three types of project management office?
The three types are supportive, controlling and directive, ordered by how much control they hold. A supportive PMO consults, offering optional templates and advice. A controlling PMO requires compliance with standards such as a set plan format or mandatory status reports. A directive PMO manages the projects itself, employing and assigning the project managers and answering for results.
What are the pros and cons of a projectized organization?
A projectized structure gives the project manager the most authority, with quick decisions, loyalty to the project and short communication lines. Team members work full-time on one project and report to its manager. The costs are idle resources when one project ends before the next begins, duplicated effort as self-contained teams solve the same problems, and uncertainty about where people belong afterward.
Why do project management offices fail?
PMOs commonly fail in four ways: bureaucracy that costs more than it returns, no executive sponsor to back it or settle disputes, standards nobody uses, and unclear authority over what it may require or refuse. Without a sponsor, a controlling PMO tends to shrink into a supportive one. A low template-use rate signals standards nobody uses, often because they were designed without managers' input, are harder than managers' own, or are never enforced.

About the Project Management course

How many college credits is Project Management?
Project Management (Business 230) carries a NCCRS credit recommendation for 3 semester credits. ACE and NCCRS have over 2,100 cooperating colleges that will consider accepting credits; the final decision is with the universities.
How much does Project Management cost and what is included?
$250, paid once, with lifetime access: all 73 video lessons, a practice quiz after each, the graded work and final exam, and an official transcript when you finish. Students who want several courses choose UPI Study PRO instead.
Which universities accept UPI Study credits?
UPI Study has signed partner agreements with universities such as Thomas Edison State University, University of the People and Charter Oak State College, and works with universities such as Penn State, SNHU and SUNY. ACE and NCCRS have over 2,100 cooperating colleges that will consider accepting credits; the final decision is with the universities. Use "Find my college" on this page to check yours.
How long does Project Management take?
It is self-paced with no deadlines. The 73 lessons total about 15 hours of video; most students add reading and practice time and finish in a few weeks to a few months, on their own schedule.
How are the exams done?
Quizzes and assignments are online in the course. The final exam is taken online with proctoring; a person on the UPI Study team checks assignments, usually within two days.
How do my credits reach my college?
When the course shows 100% complete, request the official transcript from your dashboard. It is sent to the college you name, and you can send it to more than one. Check your college first with "Find my college" on this page, or ask Athena.

Ready for the full course? Earn 3 credits in Project Management.

73 video lessons, a quiz after each one, and the graded work that earns the credit. Recommended for credit by NCCRS.

Project Management
3 credits · NCCRS
Enroll →