Business Value and Strategic Benefits of Project Management

UPI Study › Courses › Project Management › Free lessons › Lesson 1.4 Free with a free account

Business Value and Strategic Benefits of Project Management

Project Management · Chapter 1: Foundations and Framework of Project ManagementSection 1.4 · lesson 4 of 7311 min · free with a free account

← Structure and Functions of a Project Management OfficeNext lesson: Identifying and Managing Project Stakeholders →

Earn 3 college credits for Project ManagementRecommended for credit by NCCRS · Business 230 · self-paced · one payment, lifetime access

In this lesson

How projects create business value through alignment and realized benefits.

  • Trace a project to a strategic objective using the so that what test
  • Distinguish outputs, outcomes and benefits and explain benefits realization
  • Evidence tangible and intangible benefits with baselines, proxies and benefit owners
  • Describe how disciplined practice and maturity stages affect predictability and risk

Free study notes

Get this lesson's notes by email

The key points and 4 practice questions with answers, in your inbox. One email, free.

One email. Unsubscribe in one click.

Transcript

Everything said in the video, section by section (1,505 words). Read along, or search it.

Opening Question

Proving a Claim Form Project Is Worth It

Dana is an operations manager at Fernhill Mutual, an insurance cooperative owned by its members. Members complain that the claim forms are long and confusing, and Dana wants a project to simplify them. But the executive committee funds only projects that link to its objectives, and come with a way to tell whether they worked. So how do you prove a project is worth it, when most of the payoff arrives after the team has gone?

Definition

Vision, Strategy and Strategic Objectives

The worthwhile return an organization gets from an activity, measured against what it gave up, is its business value. Value starts with alignment. A vision is a short statement of the future position an organization wants to reach. Fernhill's vision: be the most trusted insurer in its region. Its strategy, the chosen approach: win trust through service that's easy to use. A strategy breaks into strategic objectives: specific results within a set period. One of Fernhill's: shorten the wait for a decision on a simple claim. Strategic alignment means a project is chosen because it delivers, or directly serves, an objective like that.

Alignment Test

Asking So That What

To test alignment, keep asking: so that what? A new one-page claim form exists so that members can complete claims without help. That exists so that decisions come sooner. That serves the objective of shorter waits, and that serves the strategy of easy service. If the chain breaks, the project isn't aligned. A refresh of the internal newsletter, however well run, traces to no stated objective. Alignment is necessary for value, but not sufficient. A perfectly aligned project can still deliver nothing.

Case Study

Outputs, Outcomes and Benefits at Brightwater

Here's how that happens. Brightwater Haulage, a small freight company, spends a quarter building an online booking portal. The portal is finished on time and to specification. That's the output: a thing the project produces and hands over. The intended outcome, a change in behavior when the output is used, was that customers would book online, and stop phoning the dispatch desk. The intended benefit, the advantage the outcome brings, was freeing a dispatcher's time for route planning. Six months later, the phones ring just as often. The portal asks for an account number most small customers don't know. The output was delivered. The outcome never happened, so the benefit never arrived. A project team controls the output almost completely, influences the outcome partly, and controls the benefit hardly at all.

Process

The Benefits Realization Loop

Benefits realization is the discipline of making sure the improvements a project was approved for are identified, planned, delivered, and then checked. Identifying means stating, before approval, what will be better, for whom, and by how much. Planning means deciding how and when each benefit will be measured, who is responsible, and what behavior must change. Delivering means handing over the outputs, and supporting the changes that put them to use. Checking means measuring, once they're in use, whether things improved. The four repeat as a loop, and checking falls almost entirely after the project has closed. Projects are temporary, but benefits aren't. So someone must stay responsible after the team is gone: a benefit owner.

Quick Check

A Scheduling System Nobody Uses

Quick check. A clinic's new scheduling system passes its acceptance test and goes live. Months later, the night shift still keeps paper lists, because nobody showed them the system. What failed: the output, the outcome, or alignment? Pause, and decide. The outcome. The system exists, so the output was delivered, but the change in how people work never happened. Alignment is fine: faster scheduling surely serves the clinic. The missing step was training, the bridge between output and use.

Tangible Benefits

Measuring Against a Baseline

Some benefits are tangible: expressed directly in money, hours or counts, and checkable against records. Cost reduction is spending less for the same result. Revenue is new income. Time saved is less effort or less elapsed time. Every tangible benefit is evidenced the same way: against a baseline, a measurement taken before the change. Say an office spent 30 hours a week on manual entry before a project, and 18 after. Thirty minus eighteen: 12 hours a week saved. But saved hours become a cost reduction only if something happens to them: removed from a budget, or moved to other valuable work. Two habits make the evidence credible. Define the measure before the project starts, and name a benefit owner. A benefit with no owner is nobody's job.

Worked Example

A Nine-Day Claims Baseline

Dana applies this to her claim form. The claims log already records when each claim arrived, and when it was decided. Over the last three months, simple claims took an average of nine working days. That's her baseline. She proposes a target of six days, three days faster, and names the head of claims as the benefit owner.

Intangible Benefits

Proxy Measures and False Precision

Other benefits are intangible: real and valued, but not countable directly. Reputation, learning, morale and safety culture are examples. Their trap is false precision: a figure presented as more exact than its evidence. Morale up fourteen percent sounds impressive. Unless morale was measured the same way before and after, and the change is tied to the project, the number hasn't earned its authority. Honest evidence uses proxy measures: observable quantities expected to move with the thing you can't see, like a survey score or near-miss reports. Whether to convert intangibles into money is contested. Supporters say unpriced benefits get ignored. Critics say one money figure invites false confidence. Both sides accept one rule: state the type of evidence plainly, and never dress it up as a better type.

Predictability

Narrowing the Schedule Gap

A second kind of value is about how an organization works. Predictability is how closely what a project delivers matches what it promised. Other departments plan around those promises. The schedule gap is the delivered duration minus the promised one. Two projects each promise 20 weeks. Project A takes 26, a gap of 6 weeks. Project B takes 22, a gap of 2. Disciplined practice tends to produce gaps like B's, in two ways. Planning breaks work into pieces small enough to estimate. And tracking spots a small slip while it's still small, when there's still time to respond. The limits matter. Discipline narrows the gap, but never removes it. A project can be perfectly on time and still worthless, like the portal. And padding every estimate makes promises predictable in an unhelpful way, by wasting time.

Risk and Waste

Finding Problems Earlier

Risk exposure is the overall possible harm being carried, weighing how likely problems are and how damaging they'd be. The argument for discipline here is about timing. A problem found in week two offers several remedies. Found in the last week, it offers one, and an expensive one. Waste has familiar forms: work redone after a misunderstood requirement, people waiting on an overrun task, and good staff stuck on a project that should never have started. Clear scope reduces the first, a visible schedule the second, and alignment the third. Each is a plausible mechanism, not a guarantee.

Maturity Model

Four Stages of Project Maturity

Project management maturity is how consistent, documented, measured and improved an organization's project practices are. It's usually pictured in four stages. At the ad hoc stage, every manager runs projects their own way, and success is hard to repeat. At the defined stage, written methods exist, so two managers given similar work do it in recognizably similar ways. At the measured stage, the organization collects data on how projects actually perform, such as schedule gaps. And at the continually improving stage, that data feeds deliberate changes to the methods, so lessons reach the next project. A caution: more process is not automatically more value. A small, low-risk project loaded with heavy process is wasting effort, and how much maturity pays off is disputed.

Quick Check

A Shared Playbook Without Data

Quick check. At a city agency, every project uses one shared playbook for its plans and reports. But nobody tracks how the projects actually turn out. Which maturity stage is that: ad hoc, defined, or measured? Pause, and decide. Defined. The shared playbook makes the work consistent, so it's past ad hoc. But without performance data, it hasn't reached measured, and it can't improve its methods from evidence yet.

Case Resolution

A Modest Claim She Can Evidence

Back to Dana, in front of the committee. It wants a quick decision, and the budget is small. She asks to delay the start by three weeks, to finish the baseline. It postpones the benefit, but without a baseline, nobody could ever show the project worked. For member satisfaction she offers no percentage. She'll use the survey question that asks how easy the claim process was, as a proxy, and read it as a direction. She commits firmly to six days, but only to a direction for satisfaction. A rival proposal promising a precise percentage sounds more impressive. Her reasoning answers the opening question. A modest claim she can evidence beats an ambitious one she can't.

Key Takeaways

Alignment, Benefits and Discipline

To recap. Trace every project back to an objective, by asking so that what. Outputs enable outcomes, and outcomes yield benefits, but the team controls only the output. A baseline and a named owner turn a promised benefit into one you can check. And discipline makes delivery more predictable and finds problems earlier. It narrows the gap, but never removes it.

About Project Management at UPI Study

Project Management (Business 230) is a self-paced online course of 73 video lessons in 12 chapters, from starting and defining a project to planning, budgets, scheduling tools, proposals, contracts, execution, monitoring, closure, teams and certification. It carries a NCCRS credit recommendation for 3 semester credits.

Every lesson transcript is free on pages like this one, and the videos are free with a free UPI Study account. Enrolling adds a practice quiz after each lesson, the graded work and final exam that earn the credit, lifetime access, and an official transcript on completion. UPI Study has helped over 130,000 students with college credits. ACE and NCCRS have over 2,100 cooperating colleges that will consider accepting credits; the final decision is with the universities.

Why take it here

Why students take Project Management with UPI Study

How projects are planned, run and closedProject Management teaches how to deliver work on time and on budget: scope, schedules, the critical path, budgets and earned value, risk, contracts, monitoring and closing a project, and leading the team. It is a common course in business, management and engineering degrees.
Credit at a fraction of the priceThe same 3 credits can cost $750 or more at a US college. Here it is one payment, self-paced, with lifetime access.
Finish your degree soonerTransfer credits reduce the courses you still owe, so you can graduate earlier or lighten a heavy semester.
Strengthen an applicationA completed college-level course on an official transcript shows admissions and scholarship committees you can do the work.
Study on your own scheduleNo start dates, no deadlines. Watch the lessons, practice, and take the final when you are ready.
130,000+students helped with college creditsACE and NCCRS have over 2,100 cooperating colleges that will consider accepting credits; the final decision is with the universities.

Where the credit goes

Universities that work with NCCRS

Project Management carries a NCCRS credit recommendation. These universities work with NCCRS; some are UPI Study's signed partners. ACE and NCCRS have over 2,100 cooperating colleges that will consider accepting credits; the final decision is with the universities.

Find my college → Not listed? Ask Athena in the corner of this page, or book a 15-minute call.

FAQ

Questions students ask us

About Business Value and Strategic Benefits of Project Management

What is the difference between outputs, outcomes and benefits in a project?
An output is what the project produces and hands over, an outcome is the change in behavior when the output is used, and a benefit is the advantage that outcome brings. A booking portal finished on time is an output; customers booking online is the outcome; freed dispatcher time is the benefit. The team controls outputs almost fully, outcomes partly, and benefits hardly at all.
What is benefits realization in project management?
Benefits realization is the discipline of making sure the improvements a project was approved for are identified, planned, delivered and then checked. It runs as a loop, and checking happens mostly after the project closes. Because projects are temporary but benefits are not, a named benefit owner must stay responsible for measuring results once the team has disbanded.
How do you measure a tangible project benefit?
Measure it against a baseline, a measurement taken before the change. If manual entry took 30 hours a week before a project and 18 after, the saving is 12 hours a week. Saved hours become a cost reduction only if they are removed from a budget or moved to other valuable work. Define the measure before the project starts and name a benefit owner.
What are the stages of project management maturity?
Project management maturity is usually pictured in four stages: ad hoc, defined, measured and continually improving. Ad hoc means every manager works their own way. Defined means written methods make similar work look similar. Measured means data is collected on actual performance, such as schedule gaps. Continually improving means that data feeds deliberate changes to methods, so lessons reach the next project.

About the Project Management course

How many college credits is Project Management?
Project Management (Business 230) carries a NCCRS credit recommendation for 3 semester credits. ACE and NCCRS have over 2,100 cooperating colleges that will consider accepting credits; the final decision is with the universities.
How much does Project Management cost and what is included?
$250, paid once, with lifetime access: all 73 video lessons, a practice quiz after each, the graded work and final exam, and an official transcript when you finish. Students who want several courses choose UPI Study PRO instead.
Which universities accept UPI Study credits?
UPI Study has signed partner agreements with universities such as Thomas Edison State University, University of the People and Charter Oak State College, and works with universities such as Penn State, SNHU and SUNY. ACE and NCCRS have over 2,100 cooperating colleges that will consider accepting credits; the final decision is with the universities. Use "Find my college" on this page to check yours.
How long does Project Management take?
It is self-paced with no deadlines. The 73 lessons total about 15 hours of video; most students add reading and practice time and finish in a few weeks to a few months, on their own schedule.
How are the exams done?
Quizzes and assignments are online in the course. The final exam is taken online with proctoring; a person on the UPI Study team checks assignments, usually within two days.
How do my credits reach my college?
When the course shows 100% complete, request the official transcript from your dashboard. It is sent to the college you name, and you can send it to more than one. Check your college first with "Find my college" on this page, or ask Athena.

Ready for the full course? Earn 3 credits in Project Management.

73 video lessons, a quiz after each one, and the graded work that earns the credit. Recommended for credit by NCCRS.