Developing a Thorough Project Closure Report, Explained

UPI Study › Courses › Project Management › Free lessons › Lesson 10.2 Free with a free account

Developing a Thorough Project Closure Report

Project Management · Chapter 10: Project Closure and Post-Completion ReviewSection 10.2 · lesson 64 of 7311 min · free with a free account

← Project Closeout Procedures and Their ImportanceNext lesson: Cost Variance: Definition, Calculation, and Interpretation →

Earn 3 college credits for Project ManagementRecommended for credit by NCCRS · Business 230 · self-paced · one payment, lifetime access

In this lesson

Write an evidence-based closure report and lessons future teams can use.

  • Identify the standard sections of a closure report and the evidence each needs
  • Rate objectives as met, partly met or not met using measured results
  • Rewrite opinion-based statements as evidence-based statements tied to records
  • Run a lessons-learned session and write entries with a situation, cause and recommendation

Free study notes

Get this lesson's notes by email

The key points and 4 practice questions with answers, in your inbox. One email, free.

One email. Unsubscribe in one click.

Transcript

Everything said in the video, section by section (1,550 words). Read along, or search it.

Opening Question

Leading With Budget, Blaming the Weather

The Riverside clinic is closed out, and Priya is drafting the closure report. The build finished within budget, but six weeks later than its forty-week plan. The figures are made up. Helen, the sponsor, would like the report to lead with the budget, and to put the delay down to the weather. It's tempting. Who will read this report, and what should it say about those six weeks?

Purpose

Writing for Readers Who Were Not There

A closure report is the formal record of what a project did, what it achieved, and what it taught. It's written at the end, because only then can the whole story be told, and it's written down, because the people who know it will disperse. Its readers are the sponsor, who needs to know how the money and time were used, and the governing body, which decides whether closure is complete. But most of all, it's for people who never met the project, like the manager of a future clinic build, asking what happened last time. So it must be accurate, complete, and easy to search.

Objectives Versus Outcomes

Met, Partly Met or Not Met

The report has a standard set of sections, each with its source of evidence, and a one-line test a reviewer can apply. The first compares objectives, the results the project set out to achieve, with outcomes, what it actually achieved. Each objective is marked met, partly met, or not met, with a sentence of evidence. Met: the result reaches the target. Partly met: it improves on the start, but falls short. Not met: no improvement. Riverside aimed to cut average patient check-in from nine minutes to three. The result is five. The improvement made is nine minus five, four minutes. The improvement planned was six. Four over six is about sixty-seven percent. So it's partly met, and the report says so, with the number, rather than rounding it up to met or down to not met. And an objective reached by changing its definition midway is reported as changed, not as met.

Report Sections

From Deliverables to Sign-Offs and Open Items

Then the deliverables, each with a dated acceptance behind it. Schedule performance, with planned and actual dates, and the difference. Cost performance, as a short summary pointing to the full cost analysis. Approved changes, each with its reason, approver and effect. Risks and issues: what occurred, how it was handled, and what was never resolved, because the next team needs that. Lessons learned and recommendations, kept apart. A lesson is why something happened. A recommendation is what to do differently. Mixed, they're neither clear observations nor usable instructions. And sign-offs and open items: who approved the closure, and what remains, each item with an owner and a date.

Risks and Issues

Following a Risk as It Becomes an Issue

Two distinctions help in the risks and issues section. A risk is an uncertain event that might happen. An issue is a problem that has already happened, and needs action. A risk that occurs becomes an issue, and the report follows the chain. Risk five, a supplier delay, occurred in week nine and became issue four. It was escalated, and resolved in five days with a backup supplier. A risk that never occurred is worth a line too, because it shows a precaution was effective, or unnecessary. And cross-check counts against the baseline. If fourteen deliverables were baselined and thirteen accepted, the report must account for the fourteenth: deferred to an open item with an owner, or removed by an approved change.

Quick Check

Where a Dropped Rooftop Sign Belongs

Quick check. Priya has this statement for the report: in week thirty, Helen agreed to drop the rooftop sign, saving four thousand dollars. Which section does it belong in? Pause, and decide. Approved changes. It's a formally authorized change to scope, with its approver and its effect. It also explains a gap in the deliverables count, but the change itself is recorded under approved changes. And it's a fact, not a lesson: it says what changed, not why something happened.

Core Rule

Every Statement Traces to a Record

Everything in the report follows one rule: write from evidence. Every factual statement must trace to a record, like the baseline, the change log or the issue log, not to memory or opinion. Memory is selective, especially about an uncomfortable outcome, and an opinion can't be checked by a later reader. Where no record exists, the report says so. Schedule overrun is actual duration minus planned. Riverside's baseline planned forty weeks, and the record shows forty-six. That's six weeks over, and six over forty is fifteen percent. So we ran a little late becomes: the project finished six weeks, fifteen percent, after its planned forty-week duration, according to the schedule baseline and the project record.

Strong and Weak

Statements With Figures, Records and Owners

Here's how that reads in practice. Strong: objective two, cut check-in time, was partly met: the average fell from nine minutes to five, against a target of three, per the two timing samples. Weak: the team worked hard, and the project went well overall. It's an opinion with no record, and it tells a future reader nothing. Weak: communication could have been better. No situation, no cause, no recommendation. Nobody can act on it. Strong: open item, the clinic-finder link on Willowbrook's website is unresolved; owner, the web editor; due, the end of next quarter. Strong statements carry a figure, a record, and an owner or date.

Quick Check

Choosing the Evidence-Based Statement

Quick check. Three draft statements. Stakeholders were very happy with the result. Grace's staff were trained on April twenty-eighth, according to the training log. The budget was a real challenge for the team. Which one belongs in the report as written? Pause, and decide. The training statement. It names what happened, gives a date, and points to a record anyone can check. The other two are opinions. A stronger version would cite a record, like the final cost against the approved budget, from the cost record.

Lessons Session

Preparing and Facilitating a Lessons Review

The lessons come from a lessons-learned session: a structured meeting where the team and stakeholders examine what happened, and agree what should change. First, preparation: gather the records, invite people who saw different parts of the project, circulate an agenda, and set ground rules, like discussing causes, not persons. Then neutral facilitation. Elena, from patient services and outside the build, leads. She doesn't defend decisions, doesn't let one voice dominate, and treats every contribution alike. The session covers what went well, as well as what didn't, because successes can be repeated only if they're understood. And it captures causes, by asking why, until the answer is something that could be changed.

Root Cause

Asking Why Until Something Can Change

Sam recalls a symptom from an earlier job: the fit-out schedule slipped three weeks. Why? Orders were placed late. Why? Approving the order list took too long. Why? The only approver was on leave, and no delegate had been named. That's a cause that can be changed: naming a delegate costs little. Stopping at orders were late would only produce the advice, order sooner. The group stops when it reaches something it can act on, and never stops at a person's name.

Lessons Entries

Situation, Cause and Assignable Recommendation

The session's product is a set of lessons-learned entries. A weak one: communication was poor; communicate better next time. A strong one has a situation, a cause, and a recommendation. Situation: three change requests approved in week twelve reached the supplier in week fifteen. Cause: the change log template had no step for notifying the supplier, and no one was assigned. Recommendation: add a supplier-notification field to the template. The project office template owner does it before the next kickoff. That recommendation is assignable: a named role owns it, and its completion can be checked. Then filing turns a session into learning. Entries are tagged by topic, project type, phase and cause, and stored where other managers can search. A named person reviews them before the next project starts.

Review and Release

Correcting Facts Without Removing Findings

The report is written for readers who weren't there, so it uses plain language, defines its terms, and avoids in-jokes and team shorthand. Before release, the people who hold the records review the draft, and may correct facts. Then the sponsor reviews it, and may ask for clarification. But a reviewer may not remove a finding just because it's unwelcome. A disagreement is settled by pointing to the record, or both views are noted with their evidence. Then the approved report is filed in the archive.

Case Resolved

Tracing Six Weeks to Logged Causes

Back to Helen's request. Priya's reasoning: this report is the record the next clinic build will be planned from, so an inaccurate account would mislead it. So she goes back to the issue log and the baseline. The log shows two weeks lost to a permit delay the project couldn't control, one week to weather, and three weeks to a crew-scheduling gap the project could have prevented. Two plus one plus three is six: the whole overrun. She reports the budget result honestly, as a success. She reports the delay as six weeks, fifteen percent, with each part tied to its logged cause, and a recommendation on crew scheduling. Shown the log entries, Helen agrees. The cost was an uncomfortable conversation and a less flattering report. The gain is a record the next team can trust.

Key Takeaways

An Honest, Searchable Closure Record

To recap: a closure report is written for readers who weren't there. Mark each objective met, partly met, or not met, with evidence and figures. Write from evidence: every statement traces to a record. Each lesson gets a situation, a cause, and an assignable recommendation, filed where others will find it. And a finding stays in the report, even when it's unwelcome.

About Project Management at UPI Study

Project Management (Business 230) is a self-paced online course of 73 video lessons in 12 chapters, from starting and defining a project to planning, budgets, scheduling tools, proposals, contracts, execution, monitoring, closure, teams and certification. It carries a NCCRS credit recommendation for 3 semester credits.

Every lesson transcript is free on pages like this one, and the videos are free with a free UPI Study account. Enrolling adds a practice quiz after each lesson, the graded work and final exam that earn the credit, lifetime access, and an official transcript on completion. UPI Study has helped over 130,000 students with college credits. ACE and NCCRS have over 2,100 cooperating colleges that will consider accepting credits; the final decision is with the universities.

Why take it here

Why students take Project Management with UPI Study

How projects are planned, run and closedProject Management teaches how to deliver work on time and on budget: scope, schedules, the critical path, budgets and earned value, risk, contracts, monitoring and closing a project, and leading the team. It is a common course in business, management and engineering degrees.
Credit at a fraction of the priceThe same 3 credits can cost $750 or more at a US college. Here it is one payment, self-paced, with lifetime access.
Finish your degree soonerTransfer credits reduce the courses you still owe, so you can graduate earlier or lighten a heavy semester.
Strengthen an applicationA completed college-level course on an official transcript shows admissions and scholarship committees you can do the work.
Study on your own scheduleNo start dates, no deadlines. Watch the lessons, practice, and take the final when you are ready.
130,000+students helped with college creditsACE and NCCRS have over 2,100 cooperating colleges that will consider accepting credits; the final decision is with the universities.

Where the credit goes

Universities that work with NCCRS

Project Management carries a NCCRS credit recommendation. These universities work with NCCRS; some are UPI Study's signed partners. ACE and NCCRS have over 2,100 cooperating colleges that will consider accepting credits; the final decision is with the universities.

Find my college → Not listed? Ask Athena in the corner of this page, or book a 15-minute call.

FAQ

Questions students ask us

About Developing a Thorough Project Closure Report

How do you decide whether a project objective was met, partly met or not met?
Compare the actual result with the target and the starting value. Met means the target was reached, partly met means there was improvement that fell short, and not met means no improvement. If check-in time was to fall from 9 minutes to 3 and fell to 5, the improvement is 4 of the planned 6 minutes, about 67%, so the objective is partly met.
What is the difference between a lesson learned and a recommendation?
A lesson explains why something happened, while a recommendation states what to do differently. Mixing them produces statements that are neither clear observations nor usable instructions. A strong entry gives the situation, the cause and an assignable recommendation, such as adding a supplier-notification field to the change log template, owned by a named role and checkable once it is done.
How do you find the root cause of a problem in a lessons-learned session?
Keep asking why until the answer is something that could be changed, and do not stop at a person's name. A fit-out slipped three weeks because orders were late, because approving the order list took too long, because the only approver was on leave with no delegate named. Naming a delegate is a cheap, actionable fix, while simply ordering sooner is not.
Why should a closure report be written from evidence rather than memory?
Memory is selective, especially about uncomfortable outcomes, and an opinion cannot be checked by a later reader. Every factual statement should trace to a record such as the schedule baseline, change log or issue log. Instead of saying the project ran a little late, a report states it finished 6 weeks, or 15%, after its planned 40-week duration, according to the baseline.

About the Project Management course

How many college credits is Project Management?
Project Management (Business 230) carries a NCCRS credit recommendation for 3 semester credits. ACE and NCCRS have over 2,100 cooperating colleges that will consider accepting credits; the final decision is with the universities.
How much does Project Management cost and what is included?
$250, paid once, with lifetime access: all 73 video lessons, a practice quiz after each, the graded work and final exam, and an official transcript when you finish. Students who want several courses choose UPI Study PRO instead.
Which universities accept UPI Study credits?
UPI Study has signed partner agreements with universities such as Thomas Edison State University, University of the People and Charter Oak State College, and works with universities such as Penn State, SNHU and SUNY. ACE and NCCRS have over 2,100 cooperating colleges that will consider accepting credits; the final decision is with the universities. Use "Find my college" on this page to check yours.
How long does Project Management take?
It is self-paced with no deadlines. The 73 lessons total about 15 hours of video; most students add reading and practice time and finish in a few weeks to a few months, on their own schedule.
How are the exams done?
Quizzes and assignments are online in the course. The final exam is taken online with proctoring; a person on the UPI Study team checks assignments, usually within two days.
How do my credits reach my college?
When the course shows 100% complete, request the official transcript from your dashboard. It is sent to the college you name, and you can send it to more than one. Check your college first with "Find my college" on this page, or ask Athena.

Ready for the full course? Earn 3 credits in Project Management.

73 video lessons, a quiz after each one, and the graded work that earns the credit. Recommended for credit by NCCRS.

Project Management
3 credits · NCCRS
Enroll →