Categorizing and Calculating Actual Project Costs
Project Management · Chapter 9: Project Monitoring, Control, and Performance ManagementSection 9.3 · lesson 57 of 7317 min · free with a free account
Free preview
Create a free account to keep watching
It takes a minute and costs nothing. Your free account unlocks all of Chapter 1 and 3 more lessons of Project Management.
Lesson complete
Earn the 3 college credits for Project Management
Enrolling adds a quiz after each lesson, the graded work and the official transcript. Recommended for credit by NCCRS.
Next lesson: Activity Duration Estimation and Work Value Assessment →← Project Management Metrics: Types and Practical ExamplesNext lesson: Activity Duration Estimation and Work Value Assessment →
In this lesson
Counting incurred costs, coding them, and reconciling project and finance records.
- Distinguish committed, incurred and paid cost, and calculate actual cost to date
- Apply accruals, period cut-off and cost coding to project cost entries
- Reconcile project and accounting records by explaining timing and coding differences
- Explain why sunk costs should not drive a decision to continue or stop
Free study notes
Get this lesson's notes by email
The key points and 4 practice questions with answers, in your inbox. One email, free.
One email. Unsubscribe in one click.
Transcript
Everything said in the video, section by section (1,995 words). Read along, or search it.
Opening Case
Two Records, Two Different Totals
It's March 31 on a waiting-room refit at one of Willowbrook's clinics, and Priya needs the actual cost to date. The figures here are made up. Her team's project record says $9,500. Finance's ledger says $8,090. They can't both be right. By the end of this lesson, you'll know which entries count, and you'll see both records agree on a third number.
Definition
Actual Cost Needs a Status Date
Actual cost is the cost of the work performed up to a stated date, recorded from source documents, so it can be compared with the budget at the same date. The budget is the approved plan for what the work should cost. A forecast estimates what it will cost from here on. Actual cost records what has already happened. So it always needs a status date, and a rule for which entries count.
Cost States
Committed, Incurred and Paid
One purchase passes through three states. A purchase order to a supplier creates committed cost: money promised, for goods not yet received. When the goods arrive, or the service is done, it becomes incurred cost, whether or not an invoice has arrived. When the invoice is settled, it's also paid cost. Labor usually skips the first state: hours worked are incurred, with no order. Here's the rule for this whole lesson. Actual cost to date is the sum of incurred and paid entries, dated on or before the status date. Paid entries were incurred first, so they're not added twice. Committed cost is listed as a memo, never added. And paid alone is a cash view, reported separately. A deposit, paid before delivery, is cash out without incurred cost. If a project pays deposits, it needs a written rule for them.
Worked Example
Following One Cabling Purchase
Follow one purchase: cabling for $2,400. Ordered on March 3, it's committed. Delivered and installed on March 12, it's incurred. Paid on March 27, under fifteen-day terms. Each date answers a different question: when money was promised, when the work was done, and when cash left. Actual cost counts it from March 12. Counting only when paid would show none of it until the 27th, although the cabling was already in the walls. Meanwhile, the project team entered the delivery on March 13, from the delivery note. Finance entered it on March 20, when the invoice was processed.
Accruals and Cut-Off
Recording Costs in the Period Used
That's the idea behind an accrual: a cost recorded in the period the goods or services were received or used, even before the invoice arrives or is paid. Floor tiles delivered on March 20 are used in March, though the invoice may be settled in April. As incurred cost, they're March. As cash, April. Neither is an error. They answer different questions, and a mismatch usually means two people used different counts without saying so. A cut-off is the rule that decides which period an entry belongs to, usually by delivery or performance date, not recording date. Use the same cut-off in both records.
Cost Coding
WBS Element, Cost Account and Phase
To compare actual cost with the budget, each entry needs coding: identifiers saying where in the project it belongs. A WBS element, the deliverable or work package. A cost account, like labor, materials, subcontract or equipment hire. And a phase, like strip-out, installation or finishing. The refit has four elements: 1.1 site management, 2.1 strip-out, 2.2 electrical, and 2.3 finishes. The cabling's code reads: 2.2, materials, installation. Record cost at the level the budget is held. Code at the source, from an agreed list, and split shared charges by a recorded rule, like hours. Mis-coding does damage the total hides. Move $900 of ceiling work into strip-out, and the total stays the same, but strip-out looks over budget and finishes under.
Labor Costs
Timesheet Hours Times Rates
Labor is often the largest cost, and no invoice announces it. A timesheet records the hours a person worked, by task code, approved by a supervisor. A rate table is the controlled list of hourly cost rates. Labor cost equals hours worked times the rate: here, $18 an hour for strip-out crew, $30 for the electrical lead. A missing or late timesheet understates actual cost. The labor line looks flat, then jumps when the sheet arrives, so the saving was false. The electrical lead works 8 hours on March 30, but the sheet arrives April 2. That's 8 x $30 = $240, incurred in March. Post it back to March if that period is still open, or as a dated adjustment if not. And a wrong rate misstates every hour: the figures look tidy, and are wrong.
Worked Example
The Refit's Project Record at March 31
Now the refit's project record at March 31. Each entry has a code, a state and an amount. Tiles delivered, $1,500, incurred. Light fittings ordered, $1,600, committed. Glass partitions ordered, $3,000, committed. The cabling, $2,400, now paid. Plastering, stage one complete, $2,000, incurred, though unpaid. Strip-out crew, 100 hours at $18: $1,800. Electrical lead, 40 hours at $30: $1,200. And site cabin rent for March, $600, incurred. Strike the two orders, and add only the incurred and paid entries. That's $9,500, the team's figure.
Cross-Checks
Totals by Type, State and Element
Step by step. Labor is 1,800 plus 1,200: $3,000. Materials, the cabling and the tiles: $3,900. Add the plastering invoice, $2,000, and the cabin, $600. Total: $9,500. The two orders, 1,600 plus 3,000, make $4,600. They stay out as a memo. Adding them gives $14,100: exposure, not cost incurred. Cross-check by state. Incurred-only entries come to $7,100, and the paid entry is $2,400. Together, $9,500. The cash view alone is just $2,400. By element: site 600, strip-out 1,800, electrical 3,600, and finishes 3,500. Those also sum to $9,500, so each element can be compared with its own budget.
Quick Check
Actual Cost on a June Fit-Out
Quick check, on a different fit-out, with a status date of June 30. Joinery labor, $1,200, incurred. Pipes delivered and paid, $1,100. Basins ordered, $900. Fencing hire for June, $400, incurred. Is actual cost to date $1,100, $2,700, or $3,600? Pause and predict. $2,700. Add the incurred and paid entries: $1,200 + $1,100 + $400. The basins are only ordered: a memo. Adding them gives $3,600, which is exposure. And $1,100 is the cash view, which leaves out work already done.
Reconciliation
Timing Differences and Coding Differences
Now the gap. The project record is kept by the team, coded to the work breakdown, for control. The accounting record is finance's ledger, for payment and wider reporting. Reconciliation compares two records, explains every difference, and records adjustments until they agree. Here, the difference is 9,500 minus 8,090: $1,410. A timing difference: an entry belongs in the period, but one record entered it later. A coding difference: it's charged to the wrong project, element or account. An adjustment is a new, dated, documented entry. The original entries aren't erased, so the audit trail survives.
Worked Example
Explaining the Gap Between Records
Three items explain the $1,410. First, the plastering invoice, $2,000, reached the team on March 29, but finance entered it on April 2. That's timing: finance adds $2,000, dated March. Second, an electrical timesheet, 8 hours at $30, so $240, went to payroll on March 31, but reached the team on April 2. Timing again: the team adds $240. Third, finance carries a scaffold hire charge of $350, whose hire form names another project. That's coding: finance removes it, and re-posts it to the right project. The sign rule: an item only in the team's record raises the difference, and one only in finance's ledger lowers it. So 2,000, minus 240, minus 350, is $1,410. All of it is explained. The team's record becomes 9,500 plus 240: $9,740. Finance's becomes 8,090 plus 2,000, minus 350: also $9,740. They agree. Never absorb a leftover difference into some code to force agreement. Report it as unresolved. And reconcile by element too, since a coding error inside one project leaves the total unchanged.
Data Integrity
Four Faults and Their Controls
The agreed actual cost is $9,740. By element, that's 600, 1,800, 3,840 for electrical with the late timesheet, and 3,500. Records like these need data integrity: complete, accurate, authorized and unaltered, so they can be relied on. Four faults threaten it. An unauthorized charge, raised without authority to commit money. Controls: approval limits, separate people for ordering and approving, and matching each invoice to its order and delivery. A mis-coded charge, like the scaffold. Controls: a valid-code list from the work breakdown, coding at source, and sampling entries against documents. A duplicate. Enter the tile invoice twice, and $9,740 becomes $11,240, with no work behind it. Control: each document number appears once, and same-amount checks. And delayed recording, like the late timesheet. Controls: recording deadlines, and a period-end checklist of goods received but not invoiced, and timesheets not yet in.
Case Example
Nadia Reconciles Before Reporting
Here's a harder month-end, on an office renovation. Nadia, a cost analyst, finds the project record at $42,600, and the accounting record at $44,350. That's $1,750 apart, with the ledger higher. The renovation's manager asks her to send the lower figure to the client. Instead, she compares the records entry by entry. Electricians' timesheets, $450, are in payroll but not yet with the team: timing. A carpet delivery invoice, $900, is with finance only: timing too. A scaffold charge of $700 sits in finance's ledger, but its form names another job: coding. And the team holds a delivery receipt for $300 that finance hasn't entered: timing. Net: 450 plus 900 plus 700, minus 300, is $1,750. All explained. Both records come to $43,950, with the 700 flagged until the other manager confirms it. Without that confirmation, it would be $44,650. Nadia reports a day late, without the lower figure: a number needing correction costs more credibility than a short delay.
Sunk Costs
Past Spending and Forward Decisions
Last, a trap in using actual cost. A sunk cost is a cost already incurred that can't be recovered, whatever is decided next. It belongs in the record. The question is whether it should sway a decision to continue or stop. The forward-looking view compares only the cost and benefit still to come. Suppose a refit has spent $9,740, and finishing needs $6,000 more, for a space worth $5,000. Continuing leaves 5,000 minus 6,000: minus $1,000. Stopping leaves nothing further. The $9,740 is the same under both options, so it can't change the choice. A commitment that can't be canceled is in effect sunk; one that can be canceled is still a choice.
Two Views
Can Past Spending Ever Inform a Decision
Can past spending ever properly inform a decision? The strict view says no: it's identical across options, and treating it as a reason to continue produces escalation, spending more because much was spent. The other view says it can, in limited ways: as evidence of the real cost rate, as a signal of consequences of stopping, as an obligation to funders, or as a commitment device. The strict side replies that the first two are forward costs already counted, and the last two are about duty and self-control, not money. No side is taken here. Both agree a forward decision needs a forecast of the cost still to come.
Quick Check
Finishing the Signage Project
Quick check. A clinic signage project has spent $30,000. Finishing needs $8,000 more, for a result worth $10,000. Which numbers should decide whether to finish: $8,000 and $10,000, $30,000 and $10,000, or $38,000 and $10,000? Pause and predict. $8,000 and $10,000: the cost still to come, and the benefit still to gain. Finishing comes out $2,000 ahead, so the project should finish. The $30,000 is the same whether it finishes or stops. Adding it in, as $38,000, makes finishing look like a loss, and the project would stop for the wrong reason.
Case Resolved
Both Records Agree at the Same Total
Back to Priya's two numbers. $9,500 was the team's count, missing a late timesheet. $8,090 was finance's ledger, missing a late invoice and carrying another project's scaffold. Neither was the answer. After reconciliation, both records say $9,740, and that's the actual cost to date she can compare with the budget.
Key Takeaways
Count, Code, Reconcile and Look Forward
To recap. Actual cost to date is incurred plus paid entries, up to the status date. Committed cost is a memo, and paid alone is only a cash view. Code each entry to the level of the budget, so they can be compared. Reconcile records item by item, as timing or coding, with dated adjustments. And sunk costs don't decide the future: compare only what still differs.
About Project Management at UPI Study
Project Management (Business 230) is a self-paced online course of 73 video lessons in 12 chapters, from starting and defining a project to planning, budgets, scheduling tools, proposals, contracts, execution, monitoring, closure, teams and certification. It carries a NCCRS credit recommendation for 3 semester credits.
Every lesson transcript is free on pages like this one, and the videos are free with a free UPI Study account. Enrolling adds a practice quiz after each lesson, the graded work and final exam that earn the credit, lifetime access, and an official transcript on completion. UPI Study has helped over 130,000 students with college credits. ACE and NCCRS have over 2,100 cooperating colleges that will consider accepting credits; the final decision is with the universities.
Enroll now → Course details Download the syllabus All Business courses Every course with PRO →
Why take it here
Why students take Project Management with UPI Study
Where the credit goes
Universities that work with NCCRS
Project Management carries a NCCRS credit recommendation. These universities work with NCCRS; some are UPI Study's signed partners. ACE and NCCRS have over 2,100 cooperating colleges that will consider accepting credits; the final decision is with the universities.
Thomas Edison State UniversitySigned partner
University of the PeopleSigned partner
Charter Oak State CollegeSigned partner
Strayer UniversitySigned partner
Columbia Southern UniversitySigned partner
Indiana TechSigned partner
Penn StateWorks with NCCRS
Southern New Hampshire UniversityWorks with NCCRS
SUNYWorks with NCCRS
+many more cooperating universitiesFind my college →Find my college → Not listed? Ask Athena in the corner of this page, or book a 15-minute call.
FAQ
Questions students ask us
About Categorizing and Calculating Actual Project Costs
What counts as actual cost to date on a project?
What is the difference between committed, incurred and paid cost?
How do you reconcile project cost records with the finance ledger?
What is an accrual in project cost tracking?
About the Project Management course
How many college credits is Project Management?
How much does Project Management cost and what is included?
Which universities accept UPI Study credits?
How long does Project Management take?
How are the exams done?
How do my credits reach my college?
Ready for the full course? Earn 3 credits in Project Management.
73 video lessons, a quiz after each one, and the graded work that earns the credit. Recommended for credit by NCCRS.
3 credits · NCCRSEnroll →