Project Charter: Components and Purpose
Project Management · Chapter 2: Launching and Defining a ProjectSection 2.4 · lesson 13 of 739 min · free with a free account
Free preview
Create a free account to keep watching
It takes a minute and costs nothing. Your free account unlocks all of Chapter 1 and 3 more lessons of Project Management.
Lesson complete
Earn the 3 college credits for Project Management
Enrolling adds a quiz after each lesson, the graded work and the official transcript. Recommended for credit by NCCRS.
Next lesson: Team Assembly and Role Assignment in Projects →← Project Constraints, Opportunity Cost, and Trade-off AnalysisNext lesson: Team Assembly and Role Assignment in Projects →
In this lesson
How a signed charter authorizes a project and limits the manager.
- Explain the purpose of a project charter and why the sponsor issues it
- Identify the components of a charter and write measurable objectives
- Distinguish assumptions from constraints
- Compare the charter with the scope statement and project plan
Free study notes
Get this lesson's notes by email
The key points and 4 practice questions with answers, in your inbox. One email, free.
One email. Unsubscribe in one click.
Transcript
Everything said in the video, section by section (1,231 words). Read along, or search it.
Opening Question
Who Authorized This Deposit
Theo works at a garden center, and he's been asked to lead a small project: an online plant-care guide, so staff stop answering the same questions by phone all day. Keen to start, he books a web developer, and asks two colleagues to start writing plant pages. Then Bea, the bookkeeper, refuses to pay the developer's deposit. Who authorized this? And the colleagues' supervisor wants to know why her staff are off the shop floor. Theo is competent. So what gives a project manager the right to spend money, and direct people who don't report to him?
Definition
Three Jobs of a Project Charter
Competence alone doesn't give that right. The instrument that does is a project charter: a document that formally authorizes a project, and gives the project manager authority to use organizational resources. It does three jobs. It records that the organization has decided the project should happen, so the decision can't later be denied. It transfers authority: the manager may spend, assign and decide, within the limits it states. And it gives everyone a short, shared statement of why the project exists, and what it must achieve. It rests on the business case: the case argues for the decision, and the charter records it.
Issuer
Why the Sponsor Signs
The charter is issued by the sponsor, or another authority outside the project, like a board or an executive, with the standing to commit those resources. Here, that's Marta, the owner. It is not issued by the project manager, for two reasons. A manager who authorizes their own project is granting themselves authority, which has no force with anyone else. And the manager has a personal interest in the project going ahead. In practice the manager often drafts the charter, because they know the work. But the sponsor's signature is what makes it valid.
Components
Justification, Objectives, Requirements and Budget
Theo drafts the charter, component by component. Justification says why: customers phone for plant-care advice, staff time is eaten up, and the answers vary. Objectives state measurable results. Within three months of launch, at least half of advice requests are answered by the guide instead of the phone, against a baseline taken before launch. High-level requirements say broadly what the result must do: searchable by plant name, readable on a phone, and checked by a staff horticulturist. Summary milestones: content agreed in month one, a draft in month two, launch by the end of month three. And the summary budget: twelve thousand in total, split between content and website setup.
Components
Assumptions, Constraints, Stakeholders and Approval
Assumptions list what's believed but not yet known: the horticulturist can give four hours a week. Constraints list the limits imposed from outside: launch before spring, stay under the budget ceiling, and use only photographs the shop owns. Key stakeholders: the owner, shop staff, regular customers, and the horticulturist. Not just the senior supporters. Manager authority says what Theo may decide alone. Approval is Marta's signature and the date. Without it, the whole document is only a proposal.
Objectives
Outcome, Measure, Target and Date
Look closer at objectives. A usable one names the outcome, the measure, the target, and the date or period. At least half of advice requests answered by the guide, within three months, against a baseline: someone can check that later. Compare improve customer service. Nobody could ever show it was achieved, or missed. Objectives should also trace to the benefits the business case promised. If the case claimed staff time would be saved, an objective should measure it. Otherwise the project can finish, without delivering what justified it.
Common Confusion
Assumptions Versus Constraints
Assumptions and constraints are often mixed up. An assumption is believed true, for planning purposes, but not yet verified. A constraint is a known limit imposed from outside the plan: a fixed date, a budget ceiling, a legal requirement. They're used differently. No plan may breach a constraint without the sponsor's agreement. But each assumption is something to check, and if it proves false, the plan must change. The horticulturist's four hours is an assumption: if her employer cuts them, the schedule is threatened. Launch before spring is a constraint. It won't move because the team would like it to.
Quick Check
Where the Web Host Price Belongs
Quick check. A draft charter says: the web host will keep its current prices through the year. Which component does that belong in? Pause, and decide. Assumptions. Nobody has verified it; it's a belief about the future, and if prices rise, the budget must be revisited. A constraint would be a limit imposed on the project, like a budget ceiling. And an objective is a result the project must achieve.
Authority
What the Manager Decides Alone
The authority section answers the opening question most directly. It states what the manager may decide alone, what needs the sponsor, and any spending or staffing limits. Theo may spend up to five hundred per item within the budget, and assign tasks to staff by agreement with their supervisor. Changing the total budget or the launch date needs Marta. Writing limits down isn't distrust. It prevents two opposite failures: a manager who must ask permission for every purchase, and one who commits the organization beyond what the sponsor intended.
Comparison
Charter, Scope Statement and Project Plan
Three documents often blur together. The charter authorizes the project at a high level, at the end of initiation, and the sponsor approves it. The scope statement defines precisely what will and won't be delivered, early in planning, agreed with the sponsor and key stakeholders. The project plan explains how the work will be done, with tasks, dates, resources and risks. It's built during planning, and updated during delivery. Each elaborates the one before it. So a later document that contradicts the charter signals that someone changed the project without authority.
Common Mistakes
Four Recurring Charter Defects
Four charter defects recur. Vague objectives can't be checked, so success gets argued instead of shown. Missing authority leaves the manager responsible, without power. A missing signature means the document is a draft, and anyone can say the project was never authorized. And a charter that's too long doesn't get read, which defeats its purpose. A good one fits on a page.
Quick Check
Which Purchase Needs the Sponsor
Quick check. A bakery chain is opening a central kitchen. Its charter lets the project manager buy any pre-listed equipment, and spend up to five thousand on other items. She may also hire temporary fit-out contractors, within a sixty-thousand budget line. Which of these still needs the sponsor? Pause, and decide. The permanent head baker. Nothing in her authority covers permanent hires, and they create payroll that runs on long after the project ends. The oven is on the pre-approved list, and the mixer is under the five-thousand limit. The sponsor traded control of small items for speed on the big ones.
Case Resolution
A Signed Charter Unlocks the Work
Back to Theo. Marta signs and dates the charter, and it goes to Bea and to the shop supervisor. Now the developer's deposit is within budget, and under Theo's limit, so Bea pays it. And the supervisor agrees which hours her staff give to writing, because the charter says tasks are assigned by agreement with her. That answers the opening question. Competence isn't enough. A signed charter, issued by the sponsor, gives the project manager the right to act, and says exactly where that right stops.
Key Takeaways
Authorization and Its Limits
To recap. A charter formally authorizes a project, and gives the project manager authority over resources. The sponsor issues and signs it, even when the manager drafts it. Objectives name an outcome, a measure, a target and a date. Assumptions are checked; constraints bind the plan. And the authority section says what the manager decides alone, and what needs the sponsor.
About Project Management at UPI Study
Project Management (Business 230) is a self-paced online course of 73 video lessons in 12 chapters, from starting and defining a project to planning, budgets, scheduling tools, proposals, contracts, execution, monitoring, closure, teams and certification. It carries a NCCRS credit recommendation for 3 semester credits.
Every lesson transcript is free on pages like this one, and the videos are free with a free UPI Study account. Enrolling adds a practice quiz after each lesson, the graded work and final exam that earn the credit, lifetime access, and an official transcript on completion. UPI Study has helped over 130,000 students with college credits. ACE and NCCRS have over 2,100 cooperating colleges that will consider accepting credits; the final decision is with the universities.
Enroll now → Course details Download the syllabus All Business courses Every course with PRO →
Why take it here
Why students take Project Management with UPI Study
Where the credit goes
Universities that work with NCCRS
Project Management carries a NCCRS credit recommendation. These universities work with NCCRS; some are UPI Study's signed partners. ACE and NCCRS have over 2,100 cooperating colleges that will consider accepting credits; the final decision is with the universities.
Thomas Edison State UniversitySigned partner
University of the PeopleSigned partner
Charter Oak State CollegeSigned partner
Strayer UniversitySigned partner
Columbia Southern UniversitySigned partner
Indiana TechSigned partner
Penn StateWorks with NCCRS
Southern New Hampshire UniversityWorks with NCCRS
SUNYWorks with NCCRS
+many more cooperating universitiesFind my college →Find my college → Not listed? Ask Athena in the corner of this page, or book a 15-minute call.
FAQ
Questions students ask us
About Project Charter: Components and Purpose
What is a project charter and what does it do?
Who signs a project charter?
What are the main components of a project charter?
How is a project charter different from a scope statement?
About the Project Management course
How many college credits is Project Management?
How much does Project Management cost and what is included?
Which universities accept UPI Study credits?
How long does Project Management take?
How are the exams done?
How do my credits reach my college?
Ready for the full course? Earn 3 credits in Project Management.
73 video lessons, a quiz after each one, and the graded work that earns the credit. Recommended for credit by NCCRS.
3 credits · NCCRSEnroll →