Project Management Metrics: Types and Practical Examples

Project Management · Chapter 9: Project Monitoring, Control, and Performance ManagementSection 9.2 · lesson 56 of 7312 min · free with a free account

← Inside the Project Control ProcessNext lesson: Categorizing and Calculating Actual Project Costs →

Earn 3 college credits for Project ManagementRecommended for credit by NCCRS · Business 230 · self-paced · one payment, lifetime access

In this lesson

Choosing a small set of metrics that drive real project decisions.

  • Define a project metric and distinguish leading from lagging measures
  • Calculate milestone hit rate and burn rate as a series over time
  • Set targets and tolerances that separate three statuses before data arrive
  • Recognize vanity measures and gaming, and apply defenses against them

Free study notes

Get this lesson's notes by email

The key points and 4 practice questions with answers, in your inbox. One email, free.

One email. Unsubscribe in one click.

Transcript

Everything said in the video, section by section (1,750 words). Read along, or search it.

Opening Case

Twelve Metrics and Few Decisions

Priya is running a second Willowbrook project: rebuilding the clinics' patient portal. As before, the figures are made up. At the start, the steering group asked for full visibility. So every Friday, she reports twelve metrics, and collecting them eats much of the day. As far as she can tell, nobody acts on most of them. She can't simply stop sending numbers. So which should she keep, and how can she show the others aren't needed?

Definition

Defined, Repeatable and Tied to a Decision

Start with what a metric is: a defined, repeatable measurement of some part of a project, that supports a decision. Defined means a written rule says exactly what's counted, so two people reach the same value. Repeatable means it's taken again on a regular rhythm, by the same rule. Supports a decision means someone can say in advance what they'd do differently if the value moved. Compare a one-time observation. Priya walks past the portal's test room on a Tuesday, and sees it empty. That's worth a follow-up, but it can't show direction. There's no rule behind it, and no earlier value. As a metric, it becomes: test sessions held, divided by sessions planned, calculated every week.

Leading and Lagging

Results Already Happened Versus Signals Ahead

Helen, the sponsor, asks about lagging and leading measures. A lagging measure reports a result that has already happened: milestones met on time, cost spent to date, defects found in a delivered build. A leading measure signals a result that hasn't happened yet, because it tracks a condition that tends to come first. Change requests waiting for a decision tend to bring rework and slippage. So do high-rated risks with no named owner. And a falling client rating often comes before a dispute. That word, tends, matters. A leading measure is a prediction, so check it against experience: did rises really come before trouble on this project? Lagging measures are hard to dispute, but arrive too late to change the result. Steering by them alone is steering by the rear-view mirror. Leading ones alone can never be confirmed. And the label depends on the result. Open defects lag the quality of past work, yet lead next week's fixing effort. So name the result you mean.

Coverage Check

Six Dimensions of Performance

To spot blind spots, check six dimensions of performance, each one measured separately. Schedule, by milestone hit rate. Cost, by burn rate: the cost spent per unit of time. Quality, by open defects: problems logged and not yet fixed. Scope, by open change requests. Risk, by high-rated risks with no named response owner. And satisfaction, by the client's average rating on a short survey. The dimensions interact. A project can hit every date by cutting testing, so schedule looks fine while quality quietly suffers. But coverage is a check, not a target. If no decision depends on a dimension, it can go unmeasured.

Selection Test

What Would Someone Do Differently

To choose, ask one question of every metric: if this value moved from acceptable to unacceptable, what would someone do differently, and who? A specific answer, like holding an extra meeting to decide change requests, earns a place. No answer makes the metric a candidate for removal, however easy it is to collect. Keep the set small. Each metric costs time to collect, check and explain, and a long list lets a reader pick whichever numbers look best. Add a measure only when a named decision needs it. Mix leading with lagging, and give each one a written definition, an owner, and a rhythm.

Targets and Tolerances

Three Statuses Set Before the Data

Each metric also needs a target and a tolerance. The target is the value you aim for. The tolerance is the deviation agreed in advance, before the matter is escalated. A measure can miss its target without crossing its tolerance. In that middle zone, the project manager acts on their own authority, and monitors closely. That gives three statuses: on target; target missed, but within tolerance; and outside tolerance, which means escalate. Write them down before the data arrive, by the people who'll use them. Lines drawn afterward can be placed to flatter the colors.

Trends and Dashboards

How a Dashboard Can Mislead

One value isn't enough. A trend is the direction and rate of change across readings. Eighty percent could follow a fall from a hundred, or a recovery from sixty. A dashboard is a one-page display of a few metrics, each with its current value, target and trend, so a reader takes in the position at a glance. It can mislead without one false number. A color hides how near a value sits to its limit. An axis starting well above zero makes small moves look large. Averages and running totals smooth out recent change. One overall color hides which tile drives it. And without a status date and definitions, readers guess.

Worked Example

Milestone Hit Rate Week by Week

Marcus, the developer, brings the portal's numbers. Milestone hit rate is milestones met on time, divided by milestones due. One finished a day late stays a miss. Counting from the start, two milestones were due by week one, and four by week two. All were met on time: one hundred percent. Week three: four of five, eighty percent. Week four: five of six, eighty-three. Week five: six of eight, seventy-five. Week six: eight of ten, eighty percent. The target is eighty-five, and the limit seventy-five. So it misses the target, but stays above the limit. The rate can't show how late a miss was: one day and three weeks count the same. And it weighs every milestone equally, and ignores the ones not yet due.

Worked Example

Reading the Portal's Burn Rate

Burn rate is the cost spent, divided by the time in which it was spent. The portal spent six, six, seven, seven, eight and eight cost units in weeks one to six. That's forty-two over six weeks: an average of seven a week. The last four weeks give thirty over four: seven and a half. The latest week is eight, which is the planned rate once the full team arrived in week five. A rising rate may be a planned build-up of staff, or unplanned overtime, extra people, added work, or higher prices. Here, the build-up was planned. A falling rate may mean cheap progress, or people moved off, work blocked, or invoices not yet recorded. And burn rate can't tell whether the money bought the planned work.

Series Measures

Open Change Requests and Open Defects

Some measures say little as one number, and a lot as a series. Open change requests equal last week's open count, plus requests raised, minus requests decided. On the portal, the open count went two, three, three, five, six, seven. Thirteen were raised in six weeks, and only six decided. Arrivals are steady, one to three a week. The backlog grows because decisions lag. Seven sits right at the limit of seven, and a typical week would make it eight. Open defects follow the same rule: five, eight, twelve, ten, nine, eight. They peaked when testing began in earnest, then fell as fixes outpaced finds. Eight meets the target of ten or fewer. So single values mislead both ways. And even falling defect finds need care: fewer finds can mean fewer defects, or less testing.

Quick Check

Ten of Twelve Milestones on Time

Quick check, on the Riverside clinic's fit-out. Twelve milestones are due, and ten were met on time. The target is eighty-five percent, and the limit seventy-five. What happens? Pause, and decide. Priya handles it herself. Ten over twelve is about eighty-three percent: below the target, but above the limit. That's the middle zone: she acts within her own authority and watches the trend. Escalating would be for a value below seventy-five.

Common Pitfalls

Vanity, Gaming and Measuring the Easy

Three pitfalls spoil a metric set. A vanity measure looks impressive but drives no decision: tasks completed, lines of code, meetings held, pages written, hours logged. The test is the same question as before. If nobody can name an action that changes when the number changes, it's vanity. Gaming is changing behavior to improve the number, without improving the result it stands for. It needs no bad faith: it's a natural response to being judged by a figure. A hit rate can be gamed with easy milestones, moved dates, or trivial splits. Defects can be relabeled as enhancements, and invoices entered late to lower a burn rate. The third pitfall is measuring what's easy, like items closed, instead of what matters, like the client's confidence, or the state of the risks. Four defenses against gaming: define each measure so the rule can't bend; pair measures that pull against each other; steer with them, rather than judge people; and check against the ground.

Quick Check

Agents Cutting Calls Short

Quick check. Willowbrook's call center is scored on average call length. Agents start ending calls fast, and asking patients to call back. What's going on? Pause, and decide. Gaming the measure. The number improves, while the result it stands for, patients' problems solved, gets worse. It isn't vanity: managers do act on call length, which is exactly why agents bend it. A paired measure, like repeat calls, would expose it.

Two Views

Numeric Targets or Judged Trends

Should metrics carry numeric targets at all? One side says targets focus effort, make expectations explicit, and allow early escalation. Without one, a number can't be judged. The other side says a target turns the number into the goal, inviting gaming and neglect of whatever isn't measured. Trends, discussed with judgment, are safer. How often targets help or distort is an empirical question, with no general answer here. Whether to steer by preset numbers or by discussion is about values. No side is taken.

Case Resolved

Six Metrics Kept, Six Dropped

Back to Priya's twelve metrics. She asks Helen, Marcus and the finance contact one question about each: in the last eight weeks, what did you do differently because of this number? Six draw a specific answer: milestone hit rate, burn rate, open change requests, open defects, unowned high risks, and the client rating. Six draw none: lines of code, meetings held, tickets closed, hours logged, test cases written, and documentation pages. Of the six that survive, three lag and three lead. She keeps all three leading ones, because Helen's questions were about what might go wrong next. The trade-off: Marcus liked tickets closed, since it showed his team's effort. Priya keeps the raw data in the tracking tool, and accepts that a dropped measure might have caught something. The steering group agrees, and will review the set after eight weeks.

Key Takeaways

Small, Mixed and Decision-Driven

To recap: a metric is defined, repeatable, and tied to a decision someone would make. A good set is small, and mixes leading and lagging measures. Each needs a target, a tolerance agreed in advance, and a trend, not just one value. Milestone hit rate and burn rate are simple divisions, best read as a series. And drop vanity measures, and design against gaming.

About Project Management at UPI Study

Project Management (Business 230) is a self-paced online course of 73 video lessons in 12 chapters, from starting and defining a project to planning, budgets, scheduling tools, proposals, contracts, execution, monitoring, closure, teams and certification. It carries a NCCRS credit recommendation for 3 semester credits.

Every lesson transcript is free on pages like this one, and the videos are free with a free UPI Study account. Enrolling adds a practice quiz after each lesson, the graded work and final exam that earn the credit, lifetime access, and an official transcript on completion. UPI Study has helped over 130,000 students with college credits. ACE and NCCRS have over 2,100 cooperating colleges that will consider accepting credits; the final decision is with the universities.

Why take it here

Why students take Project Management with UPI Study

How projects are planned, run and closedProject Management teaches how to deliver work on time and on budget: scope, schedules, the critical path, budgets and earned value, risk, contracts, monitoring and closing a project, and leading the team. It is a common course in business, management and engineering degrees.
Credit at a fraction of the priceThe same 3 credits can cost $750 or more at a US college. Here it is one payment, self-paced, with lifetime access.
Finish your degree soonerTransfer credits reduce the courses you still owe, so you can graduate earlier or lighten a heavy semester.
Strengthen an applicationA completed college-level course on an official transcript shows admissions and scholarship committees you can do the work.
Study on your own scheduleNo start dates, no deadlines. Watch the lessons, practice, and take the final when you are ready.
130,000+students helped with college creditsACE and NCCRS have over 2,100 cooperating colleges that will consider accepting credits; the final decision is with the universities.

Where the credit goes

Universities that work with NCCRS

Project Management carries a NCCRS credit recommendation. These universities work with NCCRS; some are UPI Study's signed partners. ACE and NCCRS have over 2,100 cooperating colleges that will consider accepting credits; the final decision is with the universities.

Find my college → Not listed? Ask Athena in the corner of this page, or book a 15-minute call.

FAQ

Questions students ask us

About Project Management Metrics: Types and Practical Examples

What is the difference between leading and lagging indicators in project management?
A lagging measure reports a result that has already happened, such as milestones met on time or cost spent to date. A leading measure tracks a condition that tends to come before a result, such as change requests awaiting a decision. Lagging measures are hard to dispute but arrive too late to change the result, while leading ones are predictions that need checking against experience.
How is milestone hit rate calculated?
Milestone hit rate is milestones met on time divided by milestones due, so a milestone finished one day late still counts as a miss. If eight of ten milestones due were met on time, the rate is 80 percent, below an 85 percent target but above a 75 percent limit. The rate cannot show how late a miss was or weigh milestones differently.
What is burn rate in project management?
Burn rate is cost spent divided by the time in which it was spent. A project spending 6, 6, 7, 7, 8 and 8 cost units over six weeks spent 42 units, an average of 7 a week. A rising rate may reflect a planned build-up of staff or unplanned overtime and added work, and burn rate alone cannot show whether the money bought the planned work.
What is a vanity metric?
A vanity metric looks impressive but drives no decision, such as tasks completed, lines of code, meetings held or hours logged. The test is whether anyone can name an action that changes when the number changes; if nobody can, it is vanity. Each one still costs time to collect, check and explain, so it is a candidate for removal however easy it is to collect.

About the Project Management course

How many college credits is Project Management?
Project Management (Business 230) carries a NCCRS credit recommendation for 3 semester credits. ACE and NCCRS have over 2,100 cooperating colleges that will consider accepting credits; the final decision is with the universities.
How much does Project Management cost and what is included?
$250, paid once, with lifetime access: all 73 video lessons, a practice quiz after each, the graded work and final exam, and an official transcript when you finish. Students who want several courses choose UPI Study PRO instead.
Which universities accept UPI Study credits?
UPI Study has signed partner agreements with universities such as Thomas Edison State University, University of the People and Charter Oak State College, and works with universities such as Penn State, SNHU and SUNY. ACE and NCCRS have over 2,100 cooperating colleges that will consider accepting credits; the final decision is with the universities. Use "Find my college" on this page to check yours.
How long does Project Management take?
It is self-paced with no deadlines. The 73 lessons total about 15 hours of video; most students add reading and practice time and finish in a few weeks to a few months, on their own schedule.
How are the exams done?
Quizzes and assignments are online in the course. The final exam is taken online with proctoring; a person on the UPI Study team checks assignments, usually within two days.
How do my credits reach my college?
When the course shows 100% complete, request the official transcript from your dashboard. It is sent to the college you name, and you can send it to more than one. Check your college first with "Find my college" on this page, or ask Athena.

Ready for the full course? Earn 3 credits in Project Management.

73 video lessons, a quiz after each one, and the graded work that earns the credit. Recommended for credit by NCCRS.

Project Management
3 credits · NCCRS
Enroll →