Precedence Diagram Method and Critical Success Factors
Project Management · Chapter 5: Project Management Tools and Analytical TechniquesSection 5.2 · lesson 31 of 7313 min · free with a free account
Free preview
Create a free account to keep watching
It takes a minute and costs nothing. Your free account unlocks all of Chapter 1 and 3 more lessons of Project Management.
Lesson complete
Earn the 3 college credits for Project Management
Enrolling adds a quiz after each lesson, the graded work and the official transcript. Recommended for credit by NCCRS.
Next lesson: Systems Development Tools and Project Management Software →← Understanding and Applying Network DiagramsNext lesson: Systems Development Tools and Project Management Software →
In this lesson
Calculating early and late dates and identifying what must go right.
- Calculate early start and early finish dates with a forward pass, including merge points
- Calculate late start and late finish dates with a backward pass, including burst points
- Identify the critical path where early and late dates match and apply lags to date calculations
- Distinguish critical success factors from project objectives and the critical path, and give each factor a measure
Free study notes
Get this lesson's notes by email
The key points and 4 practice questions with answers, in your inbox. One email, free.
One email. Unsubscribe in one click.
Transcript
Everything said in the video, section by section (1,941 words). Read along, or search it.
Opening Question
When Will the Hall Refit Finish
A volunteer committee is refitting a community hall. Seven jobs, a few days each, some waiting on others. When will the whole refit be done? And which jobs can't slip by a single day without moving that finish? A drawing alone can't say. This lesson turns the drawing into dates.
Definition
A Node Network With Date Calculation
The precedence diagram method is the node-based network, extended with date calculation. Every activity box carries its duration and four calculated dates, so the drawing that shows the logic also gives a schedule. A calculated schedule applies fixed arithmetic rules to the durations and the logic. It shows which activities govern the finish. And it's repeatable. Two people applying the same rules to the same inputs get the same dates, so the schedule can be checked and challenged.
Node Contents
Seven Items Including Four Dates
Each node carries seven items: an identifier, a name, and a duration in working days. Then four dates. Early start is the earliest day it can begin, and early finish the earliest it can be complete. Late start is the latest it can begin without pushing the project finish, and late finish the latest it can be complete. Early dates come from working forward from the start, and late dates from working backward from the finish.
Day Convention
Starting at Day Zero
Dates only mean something if everyone counts days the same way, so state the convention first. Here, the project starts at day 0, the very beginning of the first working day. Day 3 means the end of the third working day. Early finish equals early start plus duration. Start at 0 with 3 days of work, and you finish at day 3, having used days 1, 2 and 3. A successor with an early start of 3 begins at the start of day 4. The other common convention counts the first day as day 1. Mixing the two causes errors of exactly one day. Late dates use the mirror formula: late start equals late finish minus duration.
Pass Rules
Largest Finish Forward, Smallest Start Backward
The forward pass moves from the first activity to the last. An activity with no predecessor starts at day 0. One with a single predecessor starts when that predecessor finishes. A merge point, with two or more predecessors, waits for all of them, so its early start is the largest of their early finishes. Taking the smaller is a classic mistake. The backward pass mirrors it, from the last activity to the first. The last activity's late finish is the project duration. A burst point, with two or more successors, must finish early enough for every one of them, so its late finish is the smallest of their late starts. If one successor must start by day 9 and another by day 6, the activity must be done by day 6.
Worked Example
Seven Hall Refit Activities
Here's the hall refit, with every link finish-to-start, in working days. A, measure the hall, takes 3 days. B, the layout plan, takes 4, after A. C, order supplies, takes 2, after A. D, install wiring, takes 5, after B. E, build the stage, takes 3, after both B and C. F, paint the walls, takes 4, after C. And G, the final check, takes 2, after D, E and F.
Forward Pass
Early Dates and a Fourteen-Day Duration
Forward pass. A has no predecessor, so it starts at day 0, and finishes at 0 plus 3: day 3. B and C follow A, so both start at 3. B finishes at 7, and C at 5. D follows B: start 7, finish 12. E is a merge point. B finishes at 7, C at 5, and the larger governs. So E starts at 7, and finishes at 10. F follows C: start 5, finish 9. G merges D, E and F, which finish at 12, 10 and 9. The largest, 12, governs, so G runs from 12 to 14. So the project duration is 14 working days.
Backward Pass
Late Dates Working From Day Fourteen
Backward pass, from the end. G's late finish is the project duration, 14. Its late start is 14 minus 2: 12. D, E and F each feed only G, so each must finish by 12. D's late start is 7, E's is 9, and F's is 8. B is a burst point. It feeds D, which must start by 7, and E, by 9. The smaller governs, so B must finish by 7, and start by 3. C feeds E, by 9, and F, by 8. The smaller, 8, governs, so C's late start is 6. A feeds B, by 3, and C, by 6. A must finish by 3, so it can start by 0. A's late start is day 0, exactly where the forward pass began. The two passes agree.
Critical Path
Where Early and Late Dates Coincide
Now read off the critical path: the chain whose early and late dates coincide. A, B, D and G have identical early and late dates, and they join end to end, at days 3, 7 and 12. So the critical path is A, B, D, G. And 3 plus 4 plus 5 plus 2 is 14. C, E and F have late dates later than their early ones. They have room the critical chain doesn't.
Cross-Check
Four Paths and a Wiring Delay
Check against the longest-path idea. The network has four complete paths. A, B, D, G is 14 days. A, B, E, G is 12. A, C, F, G is 11. And A, C, E, G is 10. The longest is the same chain the dates found. If the two ever disagree, look for an arithmetic error. And a delay on that chain moves the finish. Suppose the wiring takes 7 days instead of 5. D now finishes at 14. G can't start until 14, so the project ends at day 16. The finish slips by exactly the two days D slipped. How far an activity off the path can slip is a question of float, in subchapter 9.6.
Quick Check
Early Finish at a Merge Point
Quick check, on a different network. Activity K follows three activities, whose early finishes are day 10, day 8 and day 8. K takes 3 days. What is K's early finish: day 11, day 13, or day 29? Pause and predict. Day 13. K is a merge point, so it waits for the latest predecessor, day 10, then adds its 3 days. Day 11 is the classic slip: taking the smaller finish gives dates that are too early. And early finishes are never added together.
Lags
Screed Drying Between Floor Activities
A lag is a fixed wait between two linked activities. It takes calendar time, but no work and no resources. A crew lays a floor screed, P, in 3 days. It must dry for 2 days before the covering, Q, which takes 2. Then a final clean, R, in 1 day. The drying is a lag on the link from P to Q, not an activity, because nobody works during it. Forward, P runs from 0 to 3. Q starts at 3 plus the 2-day lag, so at 5, and finishes at 7. R runs from 7 to 8. Backward, the lag is subtracted, and every early date equals its late date. The duration, 8, includes the lag, though no activity fills it.
Other Relationships
Start-to-Start and Finish-to-Finish Dates
The other relationship types apply the same idea to the dates they name. Start-to-start plus a lag: the successor's early start is the predecessor's early start, plus the lag. Finish-to-finish plus a lag: the successor's early finish is the predecessor's early finish plus the lag, and its start comes from subtracting its own duration. Where several constraints meet, the most restrictive governs. And label every link that isn't plain finish-to-start, or readers will misread the dates.
Critical Success Factors
Conditions That Must Go Right
A calculated schedule says which activities control the finish date. It doesn't say whether the project will be judged a success. A critical success factor is one of a few conditions that must go right, for the project to reach its intended outcome. If one fails, the project fails, whatever else goes well. It isn't an objective. An objective is a result the project is trying to achieve, like opening the hall by an agreed date, within budget. A factor is a condition that must hold to get there, like the committee approving the layout before materials are ordered. It can be checked while the project runs. And it isn't the critical path. Critical there means calculated. Here it means a judgment of what is decisive, and it may sit on an activity no calculation would flag. Factors are found through a short, structured conversation, not a calculation. First, restate the objectives in the sponsor's own words, and have the sponsor rank them. Second, ask the sponsor and the team, separately: what has to go right, and what would sink the project, whatever else we did? Third, compare the lists and merge duplicates. Fourth, cut to a short list, commonly five or six at most, and drop any factor whose failure alone wouldn't sink the project. The sponsor confirms the list, and it is reviewed whenever the plan is reconsidered.
Measures and Thresholds
Making Each Factor Observable
A factor nobody can observe can't be managed. So each one gets a measure, readable without opinion, and a threshold that says when to act. For the hall, the committee approves the layout. The measure is a signed approval, and the threshold is signed before materials are ordered. Electrical work is passed by a qualified inspector. The measure is the inspector's written pass, obtained before the stage is used. Enough trained volunteers. The measure is confirmed volunteers per work day, with a threshold of at least 6, two days ahead. These are examples, not standards. Morale is good is not a measure. A signed approval is.
Quick Check
Objective, Factor, or Critical Path
Quick check. A clinic's sponsor says: the new booking website must be live by March first, within the approved budget. Is that statement a critical success factor, a project objective, or the critical path? Pause, and decide. A project objective. It names a result, judged at the end: live, on a date, within budget. A factor would be a condition that must hold on the way, like clinic staff signing off the booking rules before the build. And a critical path is calculated, never declared.
Applied Example
Willowmere Festival Path and Safety Factors
Rosa coordinates the Willowmere Arts Festival. The organizers have two priorities: open on the announced day, and keep visitors safe. Her set-up tasks give a duration of 8 days. The critical path is site marking, the main stage, lighting and sound, and the safety walk-through: 1 plus 4 plus 2 plus 1. Training the volunteer marshals wasn't on that path, and her first thought was to treat it as routine. Then she asked what had to go right for safety. First, marshals trained and on the rota before the gates open, measured by a signed roster. Second, the walk-through passed at the first attempt, measured by the inspector's written pass. A walk-through held on time and failed is still a failure. So she watches the stage against its date, and the roster and the inspector's pass against their thresholds. The schedule asks what controls the date. The factors ask what would sink the festival.
Comparison
Precedence Method Versus Arrow Method
One last comparison. Older practice often used the arrow method, with activities on arrows and events in circles. Three differences matter. The arrow method supports only finish-to-start, while the precedence method handles all four relationship types, and lags. The arrow method needs dummy activities, and the precedence method needs none. And scheduling software is commonly built around the precedence method. Given the same logic, both give the same project duration.
Key Takeaways
Passes, Critical Path, and Success Factors
To recap. Forward pass: early start is the largest predecessor finish. Backward pass: late finish is the smallest successor late start. The critical path is where early and late dates match, and a delay on it moves the finish. And a critical success factor is a judged condition, tied to a measure and a threshold.
About Project Management at UPI Study
Project Management (Business 230) is a self-paced online course of 73 video lessons in 12 chapters, from starting and defining a project to planning, budgets, scheduling tools, proposals, contracts, execution, monitoring, closure, teams and certification. It carries a NCCRS credit recommendation for 3 semester credits.
Every lesson transcript is free on pages like this one, and the videos are free with a free UPI Study account. Enrolling adds a practice quiz after each lesson, the graded work and final exam that earn the credit, lifetime access, and an official transcript on completion. UPI Study has helped over 130,000 students with college credits. ACE and NCCRS have over 2,100 cooperating colleges that will consider accepting credits; the final decision is with the universities.
Enroll now → Course details Download the syllabus All Business courses Every course with PRO →
Why take it here
Why students take Project Management with UPI Study
Where the credit goes
Universities that work with NCCRS
Project Management carries a NCCRS credit recommendation. These universities work with NCCRS; some are UPI Study's signed partners. ACE and NCCRS have over 2,100 cooperating colleges that will consider accepting credits; the final decision is with the universities.
Thomas Edison State UniversitySigned partner
University of the PeopleSigned partner
Charter Oak State CollegeSigned partner
Strayer UniversitySigned partner
Columbia Southern UniversitySigned partner
Indiana TechSigned partner
Penn StateWorks with NCCRS
Southern New Hampshire UniversityWorks with NCCRS
SUNYWorks with NCCRS
+many more cooperating universitiesFind my college →Find my college → Not listed? Ask Athena in the corner of this page, or book a 15-minute call.
FAQ
Questions students ask us
About Precedence Diagram Method and Critical Success Factors
How do you calculate early start and early finish in a forward pass?
How do you calculate late start and late finish in a backward pass?
How do you identify the critical path using the precedence diagram method?
What is the difference between a critical success factor and a project objective?
About the Project Management course
How many college credits is Project Management?
How much does Project Management cost and what is included?
Which universities accept UPI Study credits?
How long does Project Management take?
How are the exams done?
How do my credits reach my college?
Ready for the full course? Earn 3 credits in Project Management.
73 video lessons, a quiz after each one, and the graded work that earns the credit. Recommended for credit by NCCRS.
3 credits · NCCRSEnroll →