Project Management Concepts and Real-World Applications

Project Management · Chapter 1: Foundations and Framework of Project ManagementSection 1.1 · lesson 1 of 7312 min · free with a free account

Next lesson: Core Skills and Competencies for Effective Project Managers →

Earn 3 college credits for Project ManagementRecommended for credit by NCCRS · Business 230 · self-paced · one payment, lifetime access

In this lesson

What makes work a project and how projects differ from operations.

  • Define a project using its three parts: temporary, unique and progressively elaborated
  • Distinguish project work from ongoing operations, programs and portfolios
  • Describe the four generic phases of a project life cycle
  • Compare predictive, adaptive and hybrid approaches and the work each suits

Free study notes

Get this lesson's notes by email

The key points and 4 practice questions with answers, in your inbox. One email, free.

One email. Unsubscribe in one click.

Transcript

Everything said in the video, section by section (1,687 words). Read along, or search it.

Opening Question

Is a Theater Festival a Project

Elena runs Riverbend, a small community theater, and she has a big idea: a ten-day festival of new plays this autumn. She asks Tomas, her project coordinator, to organize it. There's a catch. The weekly shows and the box office must keep running, with the same small staff. So is the festival a project, or just more of the same work? The answer decides how Tomas runs it.

Definition

Temporary, Unique and Progressively Elaborated

Start with the definition used across the field. A project is a temporary endeavor, undertaken to create a unique product, service, or result. A product is something made, like a building. A service is something people use, like a help line. A result is any other outcome, like a finished study. The definition has three working parts, and a piece of work needs all of them. It is temporary. Its outcome is unique. And it is clarified step by step, which is called progressive elaboration.

Key Terms

Temporary Does Not Mean Short

Both key words are easy to misread. Temporary means a defined beginning and a defined end. It does not mean short. A bridge can take years and still be a project, because it has a planned finish. And an afternoon task, like replacing a printer cartridge, is routine upkeep, not a project. Temporary also describes the effort, not the result. The team disbands, but the bridge may stand for a century. Unique doesn't mean that nothing like it was ever done before. A builder's twenty-first clinic is still a project: a new site, new regulators, a new client and a new crew. That uniqueness creates uncertainty, and uncertainty is the reason projects need active management.

Concept

Progressive Elaboration Versus Scope Creep

The third part, progressive elaboration, is how the plan grows. Early on, much is unknown: the exact requirements, the best approach, the real effort. Because the outcome is unique, some unknowns are resolved only by doing part of the work. So the first plan is broad, and it gets more detailed as each stage reveals new facts. Tomas does exactly this. He commits to the dates and the venue first. The lineup of plays comes next, and the detailed daily schedule last, once demand is clearer. Don't confuse this with scope creep: work added with no agreement and no decision. Elaboration adds detail to the same outcome. Creep changes the outcome, without anyone deciding to. Telling them apart needs a stated outcome to measure against.

Definition

What Project Management Means

So what is project management? It is the application of knowledge, skills, tools and techniques to project activities, to meet the project requirements. A requirement is a condition or capability the result must have, to satisfy the people who asked for it. None of the four works alone. A schedule without the skill to negotiate its dates is just a document. The project manager is the person assigned to lead the team, and accountable for the project's objectives. Accountable means answerable for the result, even when others do most of the work. That's Tomas. Actors, designers and box office staff will do the work, but he answers for the whole festival.

Comparison

Projects Versus Ongoing Operations

Now meet Gareth, who runs the box office with the same two staff he has always had. His work is operations: the ongoing, repetitive activity that keeps an organization running day to day. Selling tickets, answering queries, paying staff each month. None of it has a planned end. Line the two kinds of work up, and they answer the same questions in opposite ways. A project has a defined end. Operations continue as long as the organization needs them. A project makes a unique result. Operations deliver the same products or services again, to a settled standard. A project team is assembled, then disbands. An operations team is standing. Success differs too. A project succeeds when it delivers the agreed result, and the change it promised. Operations succeed by running steadily, to standard, at an acceptable cost, period after period. In short, operations keep the organization running as it is. Projects change what it is, or what it can do.

Handover

Where Projects Meet Operations

The two kinds of work meet at a handover. A project ends by delivering its result into operations, where it's used and maintained for years. The festival needs something new: a festival pass, a product the box office has never sold. Tomas treats creating the pass as project work, done once, by a named person. Selling it is operations, and that starts only when the pass is ready. Many projects fail right here: declared done, while no one in operations has agreed to own the result. It runs the other way too. People doing daily work spot problems worth a bounded effort to fix.

Key Terms

Programs and Portfolios Defined

Two more words come up constantly in this course. A program is a group of related projects, managed together for benefits you wouldn't get managing them separately. Suppose Elena paired the festival with a playwrights' workshop and a touring show, all serving one new-plays goal. That could be a program. A portfolio is wider still: the projects and programs an organization groups together, to compare them and decide where limited resources go. When Elena's board weighs the festival against a roof repair and a new lighting rig, that's portfolio thinking. A later lesson in this chapter builds out that hierarchy.

Quick Check

Is the Annual Gala a Project

Quick check. Every year, Riverbend holds a fundraising gala with the same theme. But each year brings a new venue contract, new guests and a new program. Is one year's gala a project, operations, or a program? Pause, and decide. A project. The theme repeats, but each year's gala has its own start, its own end, and a result that hasn't existed in that form before. The organization that stages galas year after year is operations. And a program needs several related projects, managed together for an added benefit. One gala on its own isn't that.

Life Cycle

Four Generic Project Phases

Every project moves through a life cycle: the series of phases from its start to its completion. Each phase ends at a recognizable point, where the work is reviewed before the next group begins. A generic pattern has four phases. First, start the project: Elena states the need, and authorizes the festival. Then organize and prepare: Tomas assembles a team, describes the festival in more detail, and plans the work. Then carry out the work: rehearsals, performances, and tracking progress against the plan. Finally, close: the result is accepted, the team is released, and what was learned is recorded.

Patterns

Effort, Cost of Change and Uncertainty

Across those phases, a few things follow typical shapes. These are illustrative, not industry data. Effort starts low, while a few people discuss and decide. It climbs as the team grows, peaks while the work is carried out, and falls at close as people are released. The cost of making a change takes a different path. It keeps rising. Early on, a change is cheap, because little is built or promised. By close, it may mean redoing finished work. Uncertainty runs the other way: highest at the start, then falling as facts replace assumptions. That's the bind. Early decisions matter most, yet they're made when the least is known. How steep that cost curve is, is debated. For construction it's widely accepted: poured concrete is expensive to remove. For software or documents, some argue good practice keeps it fairly flat. The evidence is mixed.

Approaches

Predictive, Adaptive and Hybrid Delivery

There are different ways to move through that life cycle. A predictive approach defines the outcome and plans most of the work in detail early. Then it carries out the plan, with changes handled formally. It suits work whose requirements are well understood, and where change is costly, like a building to a fixed design. An adaptive approach plans in short cycles. It delivers a usable piece at the end of each, and uses feedback to decide what's next. It suits work where needs are uncertain, and where real users are the best source of information. A hybrid approach mixes the two: fixed boundaries, budget and key dates, with the uncertain parts done in adaptive cycles. Tomas's festival is close to a hybrid. Its dates, venue and budget are fixed early, but the lineup is shaped by demand. Which approach works better is contested. Predictive supporters value an agreed plan that contracts and many parties can rely on. Adaptive supporters say early detail on uncertain work is false precision. Small deliveries cut the risk of building the wrong thing. Both have a point, and the answer depends on the kind of work.

Quick Check

Choosing an Approach for a Seat Picker

Quick check. Riverbend wants an online seat-picker for its subscribers. Nobody yet knows how they'll use it, and changing it is cheap. Which approach fits best: predictive, adaptive, or hybrid? Pause, and decide. Adaptive. The needs are unknown and change costs little, so short cycles, with subscribers trying each version, will teach the team fastest. A predictive plan written now would rest on guesses. And a hybrid fits when part of the work is well understood; here, almost none of it is.

Case Resolution

Tomas Separates Festival From Weekly Shows

Back to Tomas, and the question from the start. The festival is a project: authorized, bounded and unique. The weekly shows and the box office stay operations. He writes both lists down and shares them, so the festival's work is visible, not blended into everyone's week. Then he makes a trade-off. Box office staff can give the festival only a fixed number of hours each week. So the festival will have fewer performances than Elena imagined. He won't risk the weekly shows that sustain the company. He also spends time on a handover no audience will see: notes on how the pass was set up, so a future festival has something to build on. Elena accepts the smaller festival. Her board can reconsider once demand is known.

Key Takeaways

Projects, Operations and Life Cycles

To recap. A project is temporary and unique, and it's clarified step by step. Operations keep the organization running. Projects change it, then hand their results over. Every project moves through start, organize and prepare, carry out the work, and close. And predictive, adaptive and hybrid approaches move through that cycle in different ways.

Reflection

Improving a Website Forever

Something to think about. A team is told to improve the company website, forever. Is that a project? What would it need, to become one?

About Project Management at UPI Study

Project Management (Business 230) is a self-paced online course of 73 video lessons in 12 chapters, from starting and defining a project to planning, budgets, scheduling tools, proposals, contracts, execution, monitoring, closure, teams and certification. It carries a NCCRS credit recommendation for 3 semester credits.

Every lesson transcript is free on pages like this one, and the videos are free with a free UPI Study account. Enrolling adds a practice quiz after each lesson, the graded work and final exam that earn the credit, lifetime access, and an official transcript on completion. UPI Study has helped over 130,000 students with college credits. ACE and NCCRS have over 2,100 cooperating colleges that will consider accepting credits; the final decision is with the universities.

Why take it here

Why students take Project Management with UPI Study

How projects are planned, run and closedProject Management teaches how to deliver work on time and on budget: scope, schedules, the critical path, budgets and earned value, risk, contracts, monitoring and closing a project, and leading the team. It is a common course in business, management and engineering degrees.
Credit at a fraction of the priceThe same 3 credits can cost $750 or more at a US college. Here it is one payment, self-paced, with lifetime access.
Finish your degree soonerTransfer credits reduce the courses you still owe, so you can graduate earlier or lighten a heavy semester.
Strengthen an applicationA completed college-level course on an official transcript shows admissions and scholarship committees you can do the work.
Study on your own scheduleNo start dates, no deadlines. Watch the lessons, practice, and take the final when you are ready.
130,000+students helped with college creditsACE and NCCRS have over 2,100 cooperating colleges that will consider accepting credits; the final decision is with the universities.

Where the credit goes

Universities that work with NCCRS

Project Management carries a NCCRS credit recommendation. These universities work with NCCRS; some are UPI Study's signed partners. ACE and NCCRS have over 2,100 cooperating colleges that will consider accepting credits; the final decision is with the universities.

Find my college → Not listed? Ask Athena in the corner of this page, or book a 15-minute call.

FAQ

Questions students ask us

About Project Management Concepts and Real-World Applications

What is the definition of a project in project management?
A project is a temporary endeavor undertaken to create a unique product, service or result. Temporary means it has a defined beginning and end, not that it is short; a bridge taking years is still a project. Unique means each outcome differs in some way, such as a new site, client or crew, which creates the uncertainty that makes active management necessary.
How is a project different from operations?
A project has a defined end and creates a unique result, while operations are ongoing, repetitive work that delivers the same products or services to a settled standard. Project teams are assembled and then disband; operations teams are standing. Operations keep an organization running as it is, and projects change what it is or what it can do, then hand their results over to operations.
What is the difference between progressive elaboration and scope creep?
Progressive elaboration adds detail to the same agreed outcome as the work reveals new facts, while scope creep changes the outcome through work added with no agreement or decision. A planner might fix dates and venue first, then a lineup, then a daily schedule. Telling the two apart requires a clearly stated outcome to measure any new work against.
When should a project use a predictive versus an adaptive approach?
A predictive approach suits work with well-understood requirements where change is costly, such as a building to a fixed design. An adaptive approach suits uncertain needs and cheap change, delivering usable pieces in short cycles and using feedback. A hybrid fixes boundaries, budget and key dates while running the uncertain parts in adaptive cycles. The right choice depends on the kind of work.

About the Project Management course

How many college credits is Project Management?
Project Management (Business 230) carries a NCCRS credit recommendation for 3 semester credits. ACE and NCCRS have over 2,100 cooperating colleges that will consider accepting credits; the final decision is with the universities.
How much does Project Management cost and what is included?
$250, paid once, with lifetime access: all 73 video lessons, a practice quiz after each, the graded work and final exam, and an official transcript when you finish. Students who want several courses choose UPI Study PRO instead.
Which universities accept UPI Study credits?
UPI Study has signed partner agreements with universities such as Thomas Edison State University, University of the People and Charter Oak State College, and works with universities such as Penn State, SNHU and SUNY. ACE and NCCRS have over 2,100 cooperating colleges that will consider accepting credits; the final decision is with the universities. Use "Find my college" on this page to check yours.
How long does Project Management take?
It is self-paced with no deadlines. The 73 lessons total about 15 hours of video; most students add reading and practice time and finish in a few weeks to a few months, on their own schedule.
How are the exams done?
Quizzes and assignments are online in the course. The final exam is taken online with proctoring; a person on the UPI Study team checks assignments, usually within two days.
How do my credits reach my college?
When the course shows 100% complete, request the official transcript from your dashboard. It is sent to the college you name, and you can send it to more than one. Check your college first with "Find my college" on this page, or ask Athena.

Ready for the full course? Earn 3 credits in Project Management.

73 video lessons, a quiz after each one, and the graded work that earns the credit. Recommended for credit by NCCRS.

Project Management
3 credits · NCCRS
Enroll →