UPI Study › Courses › Project Management › Free lessons › Lesson 2.5 Free with a free account
Team Assembly and Role Assignment in Projects
Project Management · Chapter 2: Launching and Defining a ProjectSection 2.5 · lesson 14 of 738 min · free with a free account
Free preview
Create a free account to keep watching
It takes a minute and costs nothing. Your free account unlocks all of Chapter 1 and 3 more lessons of Project Management.
Lesson complete
Earn the 3 college credits for Project Management
Enrolling adds a quiz after each lesson, the graded work and the official transcript. Recommended for credit by NCCRS.
Next lesson: Foundational Steps in Developing a Project Plan →← Project Charter: Components and PurposeNext lesson: Foundational Steps in Developing a Project Plan →
In this lesson
How projects acquire people and make every responsibility clear.
- Describe the five recurring project roles and who works, advises and governs
- Compare negotiation, pre-assignment and external hiring as ways to assemble a team
- Build and validate a RACI matrix
- List the elements of an effective onboarding checklist
Free study notes
Get this lesson's notes by email
The key points and 4 practice questions with answers, in your inbox. One email, free.
One email. Unsubscribe in one click.
Transcript
Everything said in the video, section by section (1,087 words). Read along, or search it.
Opening Question
Borrowing Busy Maintenance Technicians
Leila manages a six-month project at a city housing agency: an online portal where tenants report repairs. She needs three technicians from the busy maintenance department. They know every repair type, and every tenant complaint. Her first idea is to ask for two full days a week from each of them. To their department head, that will sound like losing working technicians. So how does a project get the people it needs, when they don't report to it? And once they're on board, how does everyone know who decides what?
Key Roles
Who Works, Advises and Governs
Five roles recur on most projects. The sponsor provides resources, champions the project, and answers for its business result. The project manager plans and directs the work day to day, and answers for delivering within the constraints. The core team does the work, full time or for a regular share of their time. Subject-matter experts, like an accessibility specialist, advise on request. And a steering group, a senior body, oversees direction, resolves escalated disputes, and approves major changes. It governs rather than works. So the core team and project manager work, experts advise, and the sponsor and steering group govern. Functional managers sit to the side, supplying people.
Team Assembly
Negotiation, Pre-Assignment and External Hiring
Teams are assembled by three routes, each with its own risk. A functional manager runs a standing department, and controls its people's time. Negotiation asks functional managers to release people for a defined share of their time. A strong request says how many people, which skills, how many hours, over which dates, and why it matters to the department. It considers what the department gains, and records the agreement in writing. The risk is availability: promised people get pulled back to regular work. Escalate to the sponsor if needed. Pre-assignment means people are named before the project manager has a say. It saves time, but risks poor fit, or commitments nobody knew about. External hiring brings in contractors or new staff for missing skills. The risks are lead time, cost, and knowledge walking out the door. Involve human resources or counsel on how people are engaged.
Quick Check
Analysts Named in the Funding Letter
Quick check. When the project manager arrived, the funding letter already listed Ana and Raj as the project's two analysts. Which route brought them onto the team? Pause, and decide. Pre-assignment. They were named before the project manager had any say. So the manager's first job is checking fit: do Ana and Raj have the skills the work needs, and are they really free?
RACI Matrix
Responsible, Accountable, Consulted, Informed
Once people are on board, unwritten responsibilities cause two problems. A gap: something important is nobody's job. And a duplication: two people each think a task is theirs. A RACI matrix prevents both. Activities run down the side, roles across the top, and each cell holds one letter. Responsible: does the work. Accountable: answers for the result, and gives final approval. Consulted: asked for input before decisions, two-way. Informed: told of outcomes, one-way. Two rules make a matrix valid. Every activity has exactly one accountable role, and at least one responsible role.
Worked Example
A RACI for the Repair Portal
Here's the matrix for Leila's portal: eight activities, five roles. The project manager prepares the charter, and the sponsor is accountable for it. Releasing maintenance staff time: Leila does the asking, but the maintenance department's manager is accountable. It's his decision. Collecting requirements and designing the screens: the team lead is responsible, Leila accountable, and the senior technician consulted. Signing off the design: Leila arranges it, and the sponsor approves. Building and testing, and training staff, are led by the team lead, with Leila accountable. And approving go-live: Leila prepares it, and the sponsor is accountable. Every row has one A, and at least one R.
Validation
Four Checks on a RACI
Four checks catch most errors. First, no row without an A: an activity nobody can approve, or answer for. Second, no row with two A's: each assumes the other will decide, so things stall or contradict. Third, nobody overloaded. Count each column's R's against what that person can really do. Leila and the team lead carry four R's each, and the sponsor none: plausible for eight activities. Fourth, no empty role. A column with no letters is either unneeded, or overlooked.
Quick Check
A Row With No R
Quick check. A small matrix has three rows. Write the test plan: project manager A, tester R. Approve the budget: sponsor A, project manager R, finance C. Run the user trial: project manager A, sponsor I, trainer C. Which rule does it break? Pause, and decide. A row with no R. In the user trial, nobody is responsible for doing the work: there's an A, a C and an I, but no R. Every row has exactly one A, and every role has at least one letter. So the gap is the trial itself.
Onboarding
An Orientation Checklist for Newcomers
Onboarding brings a new team member up to productive work, starting with orientation. Without it, newcomers guess, and repeat mistakes the team already learned to avoid. A practical checklist. Context: why the project exists, and how it fits the organization. Goals: the charter's objectives and the current milestone. Roles: theirs and others', from the RACI. Tools: what the team uses to track work, store documents and communicate. Access: accounts, permissions and equipment, ready before day one. Working agreements: how the team meets, records decisions and raises problems. And a named buddy, for the routine questions.
Case Resolution
One Protected Day Each
Back to Leila. Instead of asking for two days, she framed the request in terms that mattered to Hector, the maintenance manager. She showed when the time was needed: heavy in the first two months, then a short burst for training. And she offered to plan around the seasonal peak in repair calls. She explained the portal would cut routine phone calls to his staff, and that his technicians would shape the repair categories. And she wrote the agreement down. Hector agreed to one day a week each, half what she wanted. Requirements and design would take about three weeks longer, but a protected day beats two promised days that get withdrawn. Then the RACI settled a quieter fight. Releasing the technicians was Hector's A, in his column. Signing off the design was the sponsor's. Before, each had assumed the other would approve the screens. Afterward, nobody had to ask.
Key Takeaways
Roles, Routes and RACI Rules
To recap. The core team and project manager work, experts advise, and the sponsor and steering group govern. Teams come by negotiation, pre-assignment or external hiring, each with its own risk. A RACI needs exactly one A and at least one R in every row. Then check for overloads and empty roles. And onboard every newcomer, so nobody has to guess.
About Project Management at UPI Study
Project Management (Business 230) is a self-paced online course of 73 video lessons in 12 chapters, from starting and defining a project to planning, budgets, scheduling tools, proposals, contracts, execution, monitoring, closure, teams and certification. It carries a NCCRS credit recommendation for 3 semester credits.
Every lesson transcript is free on pages like this one, and the videos are free with a free UPI Study account. Enrolling adds a practice quiz after each lesson, the graded work and final exam that earn the credit, lifetime access, and an official transcript on completion. UPI Study has helped over 130,000 students with college credits. ACE and NCCRS have over 2,100 cooperating colleges that will consider accepting credits; the final decision is with the universities.
Enroll now → Course details Download the syllabus All Business courses Every course with PRO →
Why take it here
Why students take Project Management with UPI Study
Where the credit goes
Universities that work with NCCRS
Project Management carries a NCCRS credit recommendation. These universities work with NCCRS; some are UPI Study's signed partners. ACE and NCCRS have over 2,100 cooperating colleges that will consider accepting credits; the final decision is with the universities.
Thomas Edison State UniversitySigned partner
University of the PeopleSigned partner
Charter Oak State CollegeSigned partner
Strayer UniversitySigned partner
Columbia Southern UniversitySigned partner
Indiana TechSigned partner
Penn StateWorks with NCCRS
Southern New Hampshire UniversityWorks with NCCRS
SUNYWorks with NCCRS
+many more cooperating universitiesFind my college →Find my college → Not listed? Ask Athena in the corner of this page, or book a 15-minute call.
FAQ
Questions students ask us
About Team Assembly and Role Assignment in Projects
What is a RACI matrix?
What are the rules for a valid RACI matrix?
How do project managers get team members from functional departments?
What is pre-assignment in project team building?
About the Project Management course
How many college credits is Project Management?
How much does Project Management cost and what is included?
Which universities accept UPI Study credits?
How long does Project Management take?
How are the exams done?
How do my credits reach my college?
Ready for the full course? Earn 3 credits in Project Management.
73 video lessons, a quiz after each one, and the graded work that earns the credit. Recommended for credit by NCCRS.
3 credits · NCCRSEnroll →